Resolution No. 136

11 August 2005

Tbilisi

On approval of the Regulation on the rules and conditions for issuing a mineral extraction licence

For the purpose of implementing paragraph 1 of Article 40 of the Law of Georgia "On Licences and Permits":

1. The attached Regulation on the rules and conditions for issuing a mineral extraction licence shall be approved.

2. The Resolution shall enter into force upon publication.

Prime Minister Z. Nogaideli

Regulation

On the rules and conditions for issuing a mineral extraction licence

Article 1. Purpose of the Regulation🔗

This Regulation determines the rules and conditions for issuing a mineral extraction licence (hereinafter – the licence).

Article 2. Administrative body issuing the licence🔗

The licence shall be issued by the Ministry of Environment Protection and Natural Resources of Georgia (hereinafter – the Ministry).

Article 3. Rules for issuing the licence🔗

1. The licence shall be issued by way of auction.

2. The auction shall be announced by an administrative act of the Minister of Environment Protection and Natural Resources of Georgia (hereinafter – the Minister), which shall be issued not later than one month before the auction is held.

3. The basis for issuing the administrative act provided for by paragraph 2 of this Article shall be an application of the applicant, which the Ministry considers under the public administrative procedure, or a decision of the Ministry.

4. The Ministry shall publish information on the holding of the auction in the central press not later than one month before the auction is held.

5. Before holding the auction, the Ministry may establish specific rules for the use of mineral resources, mandatory requirements for the subject of activity and a.y. Also, the quantitative, qualitative and time-defined norms and rules for the use of this resource, which are approved for each individual case by a separate subordinate normative act of the Minister.

6. The Ministry shall establish the procedure for holding the auction, identifying the winner and issuing the corresponding licence certificate.

Article 4. Rule and conditions for participation in the auction🔗

1. The right to participate in the granting of a licence by way of auction shall be held by every licence applicant that meets the licensing conditions established by law and undertakes the obligation to meet the requirements determined by the issuer of the use licence.

2. The list of documents to be submitted for participation in the auction shall be determined by the legislation of Georgia.

3. An application for participation in the auction shall be accepted not later than 15 days before the holding of the auction.

4. If a licence applicant refuses to participate in the auction before the expiry of the deadline for submitting the application, the licence fee paid by it shall be subject to refund. In the event of a breach of this deadline, the amount of the licence fee shall not be subject to refund.

5. The rule for the payment and settlement of the fee for the use of natural resources shall be determined in accordance with the legislation in force in the field of natural resource fees.

Article 5. Refusal of participation in the auction🔗

1. An applicant shall not be admitted to participation in the auction if:

a) it submitted the documentation required for participation in the auction late;

b) it submitted information that was knowingly false or inaccurate;

c) under the requirements established by legislation, it may not participate in the announced auction.

2. The applicant shall be notified of the reasoned refusal not later than 3 days after receipt of the application.

Article 6. Starting price🔗

The rule for determining and settling the starting price for the granting of a licence put up for auction shall be established by the Minister in compliance with the principles of the Law of Georgia “On Licences and Permits”.

Article 7. Licensing conditions🔗

In addition to the licensing conditions established by the relevant legislative acts of Georgia, the following additional licensing conditions may be determined for the applicant:

a) within two months after receipt of the licence, to submit, for an activity of the first category provided for by the Law of Georgia “On Environmental Permit”, an environmental impact assessment report and a conclusion of the State Ecological Expertise;

b) within two months after receipt of the licence, to submit, for an activity of the second category provided for by the Law of Georgia “On Environmental Permit”, a conclusion of the State Ecological Expertise.

Article 8. Transitional provision🔗

1. Those procedures commenced for the purpose of granting the right to use subsoil, the implementation of which commenced before the entry into force of this Resolution, shall be completed in accordance with the rule established by the Law of Georgia “On Subsoil” and the subordinate normative acts of Georgia issued on its basis.

2. The procedures related to those suspended licences which were issued before the entry into force of this Resolution shall be carried out in accordance with the rule established by the Law of Georgia “On Subsoil” and the subordinate normative acts of Georgia issued on its basis.

3. The form of the subsoil use licence shall be approved by a subordinate normative act of the Minister.