On approval of the technical regulation – Basic Provisions for the Regulation of the Use and Development of Settlement Territories

Machine translation. This text was translated from Georgian automatically and may contain inaccuracies. Only the Georgian text is legally binding: the original on legali.ge · the official publication on matsne.gov.ge. Translation of the consolidated version of 30.12.2025.

This document in other languages: ქართული (original) · Русский · Türkçe

Type of act
Resolution of the Government of Georgia
Number
№59
Date adopted
15.01.2014

Text of the document

📑 Contents (35 articles)

Government of Georgia

Resolution No. 59

15 January 2014

Tbilisi

On approval of the technical regulation – Basic Provisions for the Regulation of the Use and Development of Settlement Territories

Article 1🔗

In accordance with paragraph 2 of Article 58, paragraph 1 of Article 103 of the Code of Product Safety and Free Circulation and Article 12 of the Law of Georgia “On Normative Acts”, the attached technical regulation – “Basic Provisions for the Regulation of the Use and Development of Settlement Territories” shall be approved.

Article 2🔗

The Resolution shall enter into force from 1 January 2014. Prime Minister Irakli Garibashvili

Annex

Technical Regulation – “Basic Provisions for the Regulation of the Use and Development of Settlement Territories”

Chapter IGeneral Provisions

Article 1. Subject of Regulation of the Basic Provisions for the Regulation of the Use and Development of Settlement Territories🔗

The Basic Provisions for the Regulation of the Use and Development of Settlement Territories (hereinafter the Basic Provisions for Development) are drawn up in accordance with the requirements of the Law of Georgia “On the Fundamentals of Spatial Planning and Urban Development”, constituting part of the urban development regulation system, regulate the specific legal relations of urban development for territories, and determine the rights and obligations of participants in these legal relations and third parties.

Article 2. Objectives of the Basic Provisions for the Regulation of the Use and Development of Settlement Territories🔗

The objectives of the Basic Provisions for Development, throughout the entire territory of the country, are:

a) determination of the rules for the regulation of the use and development of settlement territories;

b) determination of the composition of the general land use plan and the development regulation plan;

c) formation, elaboration, approval of the objectives of spatial-territorial planning documents for settlements, introduction of amendments thereto, and publicity of these processes;

d) establishment of the conditions for the placement of buildings on land plot(s) and determination of their maximum heights;

e) ensuring private and public interests for the purpose of sustainable development of settlements.

Article 3. Definitions of terms🔗

1. General Land Use Plan – General Land Use Plan – an urban planning document that determines the main parameters of the use (land use) and development of settlement territories, the spatial-territorial conditions protecting amenities, the environment and immovable cultural heritage, the spatial aspects of transport, engineering and social infrastructure, as well as economic development, and the territorial issues of settlement;

2. Development Regulation Plan – an urban planning document that establishes land use zones (subzones) for settlement territories and/or specifies the architectural-planning and spatial-volumetric characteristics of individual planning units and development, the placement of buildings, their planning parameters; specifies the urban planning characteristics of the protection and development of immovable cultural heritage, the organization of relief, the improvement and greening of territories, and the provision of engineering and transport infrastructure;

3. Development Regulation Line(s) (Red Line(s)i) – an imaginary boundary established by an urban planning document for a land plot (plots), beyond which buildings and structures shall be located; one or more red lines may be established for a land plot (plots);

4. Mandatory Development Lines (Blue Lines) – an imaginary boundary established by an urban planning document for a land plot (plots), on which buildings and structures shall be located; one or more blue lines may be established for a land plot (plots);

5. Settlement – a common designation for different forms (types) of settlement (city, town, village);

6. Settlement development – the process and/or management of the development of the physical environment and infrastructure of the territories of settlements (city, town, village), which is reflected in urban planning documents;

7. Building reference surface – all surfaces of a building from the ground surface to the roof reference edge that form an angle of 70 to 90 degrees relative to the horizontal projection of the ground surface;

8. Building facade reference height – the average height of the building facade, which is equal to the average height of the facade reference surface. In the case when the total width of the dormers projecting on the side of the respective facade and other similar volumetric elements of the roof constitutes more than 1/2 of the average width of the reference surface of the same facade, then, when determining the building facade reference height, the height of the dormers projecting on the side of the respective facade and other similar volumetric elements of the roof is added to the average height of the facade reference surface;

9. Roof reference edge – in the case of a pitched roof, the imaginary line of intersection of the building reference surface and the building roof planes. In the case of a flat roof, the finishing line of the building reference surface;

10. Party wall _ a wall located on neighbourhood boundaries, part of which may constitute one of the walls of the building(s) located on the adjacent plots. A retaining wall located or to be built on the neighbourhood boundary is also shared;

11. Fence – constitutes a structure demarcating land plots, which may be located both on the cadastral boundary (shared fence) and within the boundaries of the land plot. If on different sides of the fence the mark of intersection of the fence and the ground surface is different, then the maximum height of a solid fence is determined from the higher mark;

12. Public space – a street, square, bridge, public garden, park, garden, water surface and its coastal strip, natural or artificial landscape, passage between land plots and other spaces of a similar type located within the boundaries of built-up territories;

13. Street – a public space intended for movement, located within the boundaries of built-up territories, which may consist of only a carriageway for pedestrians (sidewalk), only a carriageway intended for transport, or a carriageway intended for transport and a carriageway for pedestrians (sidewalk).

14. Above-ground floor - a floor whose average height of elevation of the floor level from the ground surface is 1.8 metres (to the nearest tenth) or more;

15. Underground floor - a floor whose average height of elevation of the ceiling from the ground surface does not exceed 1.8 metres (to the nearest tenth);

16. Ground-level floor - a floor whose average height of elevation of the floor level from the ground surface is up to 1.8 metres (to the nearest tenth), while the average height of elevation of its ceiling from the ground surface exceeds 1.8 metres (to the nearest tenth).

17. Regulation – the conditions and characteristics of the use and development of territories, which are established on the basis of the rules for regulating the use and development of the territories of settlements;

18. Veranda - a roofed space bounded by walls on one or two sides or not bounded by walls and enclosed from the open side/sides by a railing;

19. Erker - a roofed space projecting from the plane of the building facade, bounded by walls and glazed openings, which constitutes part of the main structure of the building;

20. Loggia – a dwelling recessed into the building facade, roofed, bounded by walls on three sides and open from the facade side and enclosed by a railing;

21. Balcony - a horizontal structural/cantilever plane projecting from the plane of the building facade, enclosed by a railing, which constitutes part of the main structure of the building and is connected to its interior space;

22. Mansard – the attic space existing above the upper surface of the roofing of the last storey of a building, between the external walls, the inner surface(s) of the slope(s) of a pitched roof and the rafters arranged thereon, which is used for dwelling/living. A mansard shall be considered a full storey when the average height from 3/4 of the area of the attic floor surface to the mansard ceiling is 2.4 metres (to the nearest tenth) or more;

23. Rear yard of a construction land plot – for the purpose of placing buildings on a construction land plot, that part (area) of the construction land plot which lies between the neighbourhood boundary(ies) opposite (non-adjacent) to the public boundary(ies) and the red line(s) established in accordance with Article 26 of the present Main Provisions of Development.

24. Full storey – a storey whose average height, from the floor level to the ceiling, is 2.4 metres or more.

25. Incomplete storey – a storey whose average height, from the floor level to the ceiling, is from 1.8 metres to 2.4 metres.

26. Technical storey – a storey whose average height, from the floor level to the ceiling, is less than 1.8 metres.

27. Terrace (roof terrace) – an uncovered area bounded by walls on one, two, three or four sides and, on the open side(s), where necessary, enclosed by a railing, as well as such a flat roof or part of a flat roof whose surface is finished in such a way that it can be used for living and which is bounded on the open side(s) by a railing and/or a parapet. An awning and a sunshade may be arranged on the terrace.

28. Water protection area – the surface water surfaces of the sea, lake, reservoir and river, as well as the territories of the coastal strips, floodplains and underground water catchment system necessary for their existence.

Chapter IIRules for the Regulation of the Use and Development of the Territories of Settlements

Article 4. Rules for regulating the use and development of settlement territories🔗

1. The purpose of the rules for regulating the use and development of settlement territories is to establish specific conditions for the use of territories and land plot(s) for construction activity. The said conditions shall be reflected in urban planning documents.

2. On the basis of this Chapter, the zoning part of urban planning documents shall be developed.

3. The rules for regulating the use and development of settlement territories include:

a) conditions for the development of the zoning part of urban planning documents;

b) conditions for the use and development of specific land plot(s), where no legal zoning documents exist for the relevant territory;

c) the functioning of the commission on matters of regulating the use and development of settlement territories;

d) the rule for issuing a special zoning agreement.

4. For cultural heritage and environmental protection zones, the use of territories and the regulation of development shall be carried out in accordance with the existing development, the main provisions of development, and the requirements of cultural heritage and environmental protection legislation.

Article 5. Composition of settlement territory zoning documents🔗

1. The settlement territory zoning documents are:

a) the general legal zoning document for land use;

b) the specific legal zoning document for land use.

2. The land use zoning document includes:

a) general functional zones;

b) territorial-structural zones;

c) zones of special construction regulation;

d) specific cultural heritage and environmental protection zones

3. The specific legal zoning documents for land use include:

a) conditions for regulating the use and development of settlement territories;

b) coefficients of development of the land plot, development intensity and greening;

c) specific functional zones and the requirements imposed on them by this Chapter.

d) specific cultural heritage and environmental protection zones.

Article 6. Boundaries of zones defined by documents of general legal zoning of land use🔗

1. The territory of each zone of the document of general legal zoning of land use shall be delimited by boundaries.

2. When establishing the boundaries of the territories of zones, as a rule, the following shall be used:

a) administrative boundaries of settlement territories;

b) boundaries of built-up territories of settlements;

c) natural and artificial boundaries/dividing lines;

d) boundaries of protected territories;

e) boundaries/limits of the territory of a specific cultural heritage monument and/or the territory of protection zones;

f) boundaries of residential, public-business, production, recreational territories;

g) boundaries of the territories of streets and highways;

h) boundaries of the territories of railways, pipelines and other engineering infrastructure and/or the right-of-way.

3. The delineation of the territory of the zones of general legal zoning of land use is carried out as a result of establishing the boundaries of functional, cultural heritage and environmental protection zones.

Article 7. Conditions for the regulation of the use and development of settlement territories defined by documents of specific legal zoning of land use and boundaries of zones🔗

1. For the territorial zones reflected in the document of specific legal zoning of land use, the regulations shall establish:

a) the main parameters for the regulation of the development of building land plots in the territories of the zones and their permissible indicators;

b) in the territories of the zones, a list of such objects the placement of which is inadmissible may be established.

2. The main parameters for the regulation of the development of building land plots shall include:

a) the maximum coefficient of development of land plots;

b) the maximum coefficient of intensity of development of land plots and/or the maximum height of development of land plots;

c) the minimum coefficient of landscaping of land plots;

3. The main parameters for the regulation of the development of building land plots may also include:

a) maximum indicators for the number of storeys/height of development and/or volume;

b) minimum and maximum dimensions of the area(s) of land plots;

c) development regulation lines (red lines);

d) mandatory development lines (blue lines);

e) the number of parking spaces for motor vehicles;

f) conditions of the spatial-planning arrangement of development (e.g.: placement of building facades along one line, pairing of buildings, determination of building heights, determination of the type of roofing of buildings, and others);

g) other parameters whose values and indicators are established by the development regulation plan and/or other normative acts.

4. The territory of each zone of the document of specific legal zoning of land use shall be delimited by boundaries.

5. When establishing the boundaries of the territories of zones, as a rule, the following shall be used:

a) administrative boundaries of the territory of settlements;

b) boundaries of the developed territories of settlements;

c) natural and artificial boundaries/limits;

d) boundaries of protected areas;

e) boundaries/limits of the territory of a specific cultural heritage monument and/or the territory of protection zones;

f) boundaries of residential, public-business, production, recreational territories;

g) boundaries of the territories of streets and highways and their axial and/or median lines;

h) boundaries of the territories of railways, pipelines and other engineering infrastructure and/or the right-of-way strip;

i) boundaries of individual land plots located at the edge of the territories of the zones.

6. The delineation of the territory of specific legal zones of land use is carried out as a result of establishing the boundaries of functional, cultural heritage and environmental protection zones.

7. When establishing the boundaries of legal zones, when functional zones are overlapped by cultural heritage and environmental protection zones, within the boundaries of such territory the regulation defined for cultural heritage and environmental protection zones shall apply.

Article 8. Land plot development coefficient K-1🔗

1. Land plot development coefficient K-1 determines the maximum portion of the area of a specific land plot on which the placement of buildings and structures is permissible.

2. Coefficient K-1 is determined by the area contained within the outer perimeter of the floor surface of the ground floor of the building or structure.

3. In the case where a building or structure does not have a ground floor, coefficient K-1 is determined by the area contained within the outer perimeter of the floor surface of the first above-ground floor.

4. The calculation area determined by the land plot development coefficient does not include:

a) underground floor(s) of buildings and structures;

b) a vehicle passage arranged in the building at street surface level;

c) buildings and structures which do not require a construction permit.

5. Coefficient K-1 is rounded to the nearest tenth.

Article 9. Land plot development intensity coefficient K-2🔗

1. The land plot development intensity coefficient K-2 determines, in a separate zone, the total area of the surfaces of the main structures of the floors of the ground-level and above-ground storeys of a building/structure permissible on the territory of a specific land plot.

2. The calculation area of coefficient K-2 is calculated in accordance with the list defined below:

a) The area of the surface enclosed within the outer contour of the main structure of the floor of a full ground-level and above-ground storey – is included in full in the calculation area of coefficient K-2;

b) The area of the surface of the floor structure of an incomplete storey – is included in the calculation area of coefficient K-2 by 1/2;

c) In an attic in which a mansard is arranged that constitutes a full storey, then such mansard – is included in the calculation area of coefficient K-2 by 3/4 of the area of the surface of the main structure of the floor of such attic;

d) In an attic in which a mansard is arranged that constitutes an incomplete storey, then such mansard – is included in the calculation area of coefficient K-2 by 1/3 of the area of the surface of the main structure of the floor of such attic;

e) The part of the total area of the surface of the main structure of the floor of the stairwell existing on the ground-level storey and the lift shaft existing on the corresponding storey that exceeds 60 m² – is included in full in the calculation area of coefficient K-2;

f) At the level(s) of intersection of the surface of the building and the street, the part of the total area of the road surface of the tunnel arranged in the building for the passage of a vehicle that exceeds 50 m² – is included in full in the calculation area of coefficient K-2;

g) The part of the total area of the surface of the main structure of the floor of the stairwell existing on the first above-ground storey and the lift shaft existing on the corresponding storey that exceeds 60 m² – is included in full in the calculation area of coefficient K-2;

h) The part of the total area of the surface of the main structure of the floor of the stairwell existing on an above-ground storey other than the first above-ground storey and the lift shaft existing on the corresponding storey that exceeds 40 m² – is included in full in the calculation area of coefficient K-2;

i) The part of the total area of the surface of the main structure of the floor of the balcony that protrudes from the outer wall of the facade of the building/structure by a distance of more than 1.5 m – is included in full in the calculation area of coefficient K-2;

j) The area of the surface of the main structure of the floor of the veranda, bay window, loggia – is included in full in the calculation area of coefficient K-2.

3. The calculation area of coefficient K-2 is rounded to the nearest tenth.

Article 10. Greening coefficient of a land plot K-3🔗

1. The greening coefficient of a land plot determines the minimum share of the area of the land plot territory which must not be covered or overlaid with any waterproof (construction or other) material, beneath which there must not exist any structure or premises, and which is designated for greening.

2. The greening coefficient of a land plot is the minimum indicator of the ratio of the greened surface of the land plot to the total area of the land plot.

3. Rounding of the K-3 coefficient is possible to the nearest tenth.

Article 11. Functional zones🔗

1. For the purposes of implementation of the legal zoning documents, the territories of settlements are divided into:

a) general functional zones:

a.a) landscape-recreational zone – (lsz);

a.b) agricultural zone – (sopz);

a.c) recreational zone _ (rz);

a.d) resort-recreational zone – (srz);

a.e) special zone – (spetsz);

a.f) residential zone – (sz);

a.g) transport zone – (tz);

a.h) public-business zone – (ssz);

a.i) industrial zone – (r);

a.j) sanitary zone _ (sanz);

a.k) military-purpose zone – (sdz).

b) specific functional zones:

b.a) landscape-recreational zone' – (lsz');

b.b) agricultural zone' – (sopz');

b.c) recreational zone' _ (rz');

b.d) resort-recreational zone 1 (srz-1)

b.e) resort-recreational zone 2 (srz-2)

b.f) special zone' – (spetsz');

b.g) residential zone 1 _ (sz-1);

b.h) residential zone 2 _ (sz-2);

b.i) residential zone 3 _ (sz-3);

b.j) residential zone 4 _ (sz-4);

b.k) residential zone 5 _ (sz-5);

b.l) residential zone 6 _ (sz-6);

b.m) transport zone 1 – (tz-1);

b.n) transport zone 2 – (tz-2);

b.o) public-business zone 1 – (ssz-1);

b.p) public-business zone 2 – (ssz-2);

b.q) public-business zone 3 – (ssz-3);

b.r) industrial zone 1 – (s-1);

b.s) industrial zone 2 – (s-2);

b.t) sanitary zone' _ (sanz');

b.u) military-purpose zone 1 – (sdz-1);

b.v) military-purpose zone 2 – (sdz-2).

2. The division of a territory into general functional zones is reflected in the general legal zoning document of land use corresponding to the general plan of land use.

3. The division of a territory into specific functional zones is reflected in the specific legal zoning document of land use corresponding to the development regulation plan.

Article 12. Specific functional zones🔗

1. Landscape-recreational zone (LSZ) constitutes an area of natural landscape or valuable artificial landscape within the (administrative) boundaries of a settlement, where buildings and structures ensuring its functioning may exist in accordance with legislation.

2. Agricultural zone (SOPZ) constitutes agricultural areas existing within the (administrative) boundaries of a settlement, where auxiliary buildings and structures ensuring its functioning may exist in accordance with legislation.

3. Recreational zone (RZ) constitutes a recreational zone located within the boundaries of built-up areas and includes green area (e.g.: park, garden, boulevard, square, lawn), open playgrounds and other areas of a similar type, where buildings and structures ensuring the functioning of the recreational zone (RZ) may exist in accordance with legislation.

4. Resort-recreational zone 1 (SRZ-1):

a) constitutes a zone located within the boundaries of built-up areas, where the placement of buildings and structures for recreational, therapeutic, sports and entertainment purposes is permitted.

b) maximum area of a land plot – 1000 m2

c) maximum building height on a land plot – 12 metres;

d) coefficients:

d.a) maximum land plot development coefficient (K-1) – 0.6;

d.b) land plot greening coefficient (K-3) – 0.3.

5. Resort-recreational zone 2 (SRZ-2):

a) constitutes a zone located within the boundaries of built-up areas, where the placement of buildings and structures for recreational, therapeutic, sports and entertainment purposes is permitted.

b) coefficients:

b.a) maximum land plot development coefficient (K-1) – 0.3;

b.b) land plot development intensity coefficient (K-2) – up to 3.0

d.b) land plot greening coefficient (K-3) – 0.1.

6. Special zone (SPETSZ) constitutes areas designated for cemeteries.

7. Residential zone 1 (SZ-1):

a) may exist only on the territory of rural-dacha development;

b) the dominant type of development is residential houses. The existence of buildings and structures for agricultural purposes is also permitted in accordance with legislation, including in compliance with the principles of neighbourhood tolerance.

c) coefficients:

c.a) maximum land plot development coefficient (K-1) – 0.5;

c.b) land plot development intensity coefficient (K-2) – up to 0.8;

c.c) land plot greening coefficient (K-3) – 0.3.

8. Residential zone 2 (SZ-2):

a) the dominant type of development is residential houses. The existence of public-purpose facilities is also permitted in accordance with legislation, including in compliance with the principles of neighbourhood tolerance;

b) coefficients:

b.a) maximum land plot development coefficient (K-1) – 0.5;

b.b) land plot development intensity coefficient (K-2) – up to 0.6;

b.c) greening coefficient of land plots (K-3) – 0.25.

9. Residential Zone 3 (RZ-3):

a) Low-intensity residential zone, where residential houses constitute the dominant type of development. Also permitted is the existence of public-purpose facilities in accordance with legislation, including in compliance with the principles of neighbourly tolerance;

b) Coefficients:

b.a) maximum development coefficient of the land plot (K-1) – 0.5;

b.b) maximum development intensity coefficient of the land plot (K-2) – 1.3;

b.c) greening coefficient of land plots (K-3) – 0.2.

10. Residential Zone 4 (RZ-4):

a) High-intensity residential zone, where residential houses constitute the dominant type of development. Also permitted is the existence of public-purpose facilities in accordance with legislation, including in compliance with the principles of neighbourly tolerance;

b) maximum area of the land plot – 300 m²;

c) maximum development height on the land plot 12 metres

d) Coefficients:

d.a) maximum development coefficient of the land plot (K-1) – 0.7;

d.b) greening coefficient of land plots (K-3) – 0.1.

11. Residential Zone 5 (RZ-5):

a) Medium-intensity residential zone, where residential houses constitute the dominant type of development. Also permitted is the existence of public-purpose facilities in accordance with legislation, including in compliance with the principles of neighbourly tolerance;

b) Coefficients:

b.a) maximum development coefficient of the land plot (K-1) – 0.5;

b.b) maximum development intensity coefficient of the land plot (K-2) – 1.8;

b.c) greening coefficient of land plots (K-3) – 0.1.

12. Residential Zone 6 (RZ-6):

a) High-intensity residential zone, where residential houses constitute the dominant type of development. Also permitted is the existence of public-purpose facilities in accordance with legislation, including in compliance with the principles of neighbourly tolerance;

b) Coefficients:

b.a) maximum development coefficient of the land plot (K-1) – 0.5;

b.b) maximum development intensity coefficient of the land plot (K-2) – 2.2;

b.c) greening coefficient of land plots (K-3) – 0.1.

13. Transport Zone 1 (TZ-1) constitutes a transport zone located within the boundaries of developed territories and includes streets (including sidewalks), squares, open parking lots, railway lines and train parking areas (depots).

14. Transport Zone 2 (TZ-2) constitutes a transport zone located outside the boundaries of developed territories and includes roads, open parking lots, vehicle servicing and other areas of a similar type. The existence of public premises/locations supporting the functioning of Transport Zone 2 (TZ-2) (e.g., airport, seaport, bus station, railway station, etc.) is possible in accordance with legislation.

15. Public-Business Zone 1 (PBZ-1):

a) medium-intensity public-business zone without a dominant type of development (mixed zone);

b) coefficients:

b.a) maximum coefficient of development of the land plot (K-1) – 0.6;

b.b) coefficient of intensity of development of the land plot (K-2) – up to 3.0;

b.c) coefficient of greening of land plots (K-3) – 0.1.

c) residential dwellings supporting the functioning of the public-business zone may exist in accordance with legislation.

16. Public-business zone 2 (PBZ-2):

a) high-intensity development zone where the dominant type is constituted by public-purpose facilities;

b) coefficients:

b.a) maximum coefficient of development of the land plot (K-1) – 0.7;

b.b) maximum coefficient of intensity of development of the land plot (K-2) – 5.0;

b.c) coefficient of greening of land plots (K-3) – 0.1.

c) residential buildings/dwellings supporting the functioning of the public-business zone may exist in accordance with legislation.

17. Public-business zone 3 (PBZ-3):

a) high-intensity development zone where the dominant type is constituted by public-purpose facilities;

c) maximum height of development on the land plot – 15 metres;

d) coefficients:

d.a) maximum coefficient of development of the land plot (K-1) – 0.7;

d.b) coefficient of greening of land plots (K-3) – 0.1.

18. Industrial zone 1 (I-1):

a) industrial zone where the dominant type of development is constituted by industrial facilities in which production processes hazardous/harmful to the environment and human health are not carried out;

b) public buildings/dwellings supporting the functioning of industrial zone 1 (I-1) may exist in accordance with legislation.

19. Industrial zone 2 (I-2) constitutes a zone where the dominant type of development is constituted by industrial facilities in which production processes hazardous/harmful to the environment and human health are carried out. Landfill areas also belong to this zone.

20. Sanitary zone' (SANZ') constitutes a zone which protects another zone from harmful impact and at the same time has a health-improving function.

21. Military-purpose zone 1 (MPZ-1) constitutes a military-purpose territory where military-purpose buildings and structures are located.

22. Military-purpose zone 2 (MPZ-2) constitutes a military-purpose territory where a training ground is located.

23. If a specific land plot falls within the area of operation of more than one specific functional zone, then, when developing it for the purpose of construction activity, the requirements of none of these functional zones shall be violated.

Article 13. Cultural Heritage and Environment Protection Zones🔗

1. Throughout the entire territory of the country, including in the territories of settlements, for the purpose of protecting cultural heritage and the environment, specific cultural heritage and environment protection zones may be designated, which shall be reflected in legal zoning documents.

In the general land use plan, cultural heritage and environment protection zones shall be reflected as a legal zoning document.

2. For the purpose of implementing legal zoning documents, the following main types of zones are established:

a) cultural heritage protection zones;

b) environment protection zones.

2. Cultural heritage protection zones include the following, which are defined by the Law of Georgia on Cultural Heritage:

a) individual (physical) protection zone (area) of a monument;

b) visually protective zone (area) of a monument;

c) protection zone of historical built-up area;

d) regulation zone of historical built-up area;

e) protection zone of historical landscape;

f) archaeological protection zone.

3. Environment protection zones are:

a) environment protection zone 1 (EPZ-1):

a.a) protection area of a natural monument;

a.b) the natural monument and its territory shall be protected;

a.c) construction activity on the protection area of a natural monument shall be carried out only for the purpose of its protection and/or visual perception.

b) environment protection zone 2 (EPZ-2):

b.a) territory of a protected landscape;

b.b) the territory of the protected landscape shall be protected and restored, without disturbing the visual aspect of the protected landscape;

b.c) construction activity on the territory of a protected landscape shall be permitted only for the purpose of its protection, restoration, the substantiated needs of the local population and the creation of appropriate tourist infrastructure, without disturbing the visual aspect of the protected landscape;

c) environment protection zone 3 (EPZ-3):

c.a) water protection area;

c.b) the water protection area shall be protected and restored;

c.c) construction activity on the water protection area shall be carried out only for the purpose of its protection and/or restoration.

Article 14. Conditions for changing existing zones🔗

1. The change of existing zones constitutes a change in urban planning documents and accordingly requires passing the same procedures as are established by the "Basic Provisions for Regulating the Use and Development of Settlement Territories" for their approval. The exception is the cases defined in paragraphs 2 and 3 of this article.

2. In the cases defined in this paragraph, the change of existing general functional zones shall be made in accordance with the rules of simple administrative proceedings established by Chapter VI of the General Administrative Code:

a) change of all existing functional zones defined by this chapter into a landscape-recreational zone;

b) change of all existing functional zones defined by this chapter, except the landscape-recreational zone, into a recreational zone;

c) change of industrial zone 1, public-business and residential zones defined by this chapter into an agricultural zone.

d) change of industrial and public-business zones into a residential or transport zone.

3. In the cases defined in this paragraph, the change of existing specific functional zones shall be made in accordance with the rules of simple administrative proceedings established by Chapter VI of the General Administrative Code:

a) change of industrial zone 2 (s-2) into industrial zone 1 (s-1);

b) change of public-business zone 2 (ssz-2) into public-business zone 1 (ssz-1);

c) change of residential zone 6 (sz-6) into any other residential zone, except residential zone 4 (sz-4) and residential zone 1 (sz-1);

d) change of residential zone 5 (sz-5) into residential zone 3 (sz-3) and residential zone 2 (sz-2);

e) change of residential zone 3 (sz-3) into residential zone 2 (sz-2).

Article 15. Determination of the conditions for the use and development of individual land plots during the transitional period of implementation of specific legal zoning of land use🔗

1. During the transitional period, when specific land plot(s) do not fall within the boundaries of the documents of specific legal zoning of land use of settlement territories, the development of the specific land plot(s) for construction purposes shall be carried out:

a) in accordance with the existing situation obtained on the basis of a study of a territory regulated from the planning point of view of settlement territories (e.g., a block), in the case when the land plot(s) constitute part of such a block;

b) in accordance with the existing situation obtained on the basis of a study of the territory located within 50 metres around the perimeter of the land plot(s), in the case when the land plot(s) constitute part of unregulated/unordered development. (The territory within 50 metres around the perimeter of the land plot(s) means all land plots that are in contact with the territory within 50 metres around this land plot(s)).

2. The study of the existing development in the territory adjacent to the specific land plot(s) determined by paragraph 1 of this article includes:

a) if necessary, aerial photography of the territory under study;

b) a topographic plan of the territory under study;

c) a map of the distribution of land plots in the territory under study (showing the number and area of the land plot);

d) development coefficients of land plots in the territory under study;

e) coefficients of development intensity of land plots in the territory under study;

f) landscaping coefficients of land plots in the territory under study;

g) data on legal acts, legal regimes and subordinate normative acts existing in the territory under study that may influence the development of the specific land plot(s) for construction purposes.

3. On the basis of the study of the existing development of the territory around the specific land plot(s) determined by paragraph 1 of this article, the administrative body issuing the construction permit shall adopt a decision on the conditions for the use of such land plot(s) for construction, which shall be close to the results of the study.

4. The relevant body of local self-government shall not have the right to oblige the owner(s) of the relevant land plot(s) to conduct a study of the territory adjacent to the specific land plot(s) determined by paragraph 1 of this article, if they do not have a request for the development of the specific land plot(s) for construction purposes.

Article 16. Commission on Issues of Regulation of the Use and Development of Settlement Territories, Its Rights and Obligations🔗

1. For the purpose of further improvement and effective functioning of the regulation of the use and development of settlement territories, by decision of the Sakrebulo, in agreement with self-government bodies, the “Commission on Issues of Use and Development of Settlement Territories” (hereinafter the Commission) may be established, which is subordinate to the executive authority body of the respective self-government.

2. The following may fall within the sphere of competence of the Commission:

a) preparation of regular reports for the Sakrebulos on issues of regulation of the use and development of settlement territories and provision of consultations;

b) organization, together with the relevant service of the self-government body, of public information work and discussions for the purpose of publicity of the processes of elaboration, consideration and approval of urban planning documents;

c) consideration of proposals, comments and complaints on issues of regulation of the use and development of settlement territories;

d) preparation of self-government decisions on the issuance of planning assignments for urban planning documents;

e) preparation, together with the relevant service of the self-government body, of Sakrebulo decisions for the approval of legal zoning maps of land use;

f) preparation of self-government decisions and/or conclusions on the approval of urban planning documents or their parts;

g) preparation of a Sakrebulo decision for a special zoning agreement.

3. In the event of the existence of the Commission, its function and rights and obligations shall be determined by a regulation approved, in Tbilisi and Batumi, by the Tbilisi City Hall or Batumi City Hall, respectively, and in other self-governing units, by the representative body of the local self-governing unit.

Article 17. Special (zonal) agreement🔗

1. A special (zonal) agreement provides for an increase in the value of the K2 coefficient determined for a specific land plot.

2. Within the administrative boundaries of the city of Tbilisi and the city of Batumi, the decision on a special (zonal) agreement shall be taken by the relevant body of local self-government.

3. In the remaining territory of the country, in order to adopt a special (zonal) agreement, the relevant body of local self-government shall, in accordance with the established procedure, send, together with other documents, a request to the Ministry of Economy and Sustainable Development of Georgia, which, in accordance with the procedure established for other administrative bodies, shall take a decision on the special (zonal) agreement and send it to the relevant body of local self-government.

4. In the event that the applicant for a permit wishes to increase the value of the K2 coefficient, he/she shall, in the application for the adoption of the conditions for the use of the land plot(s) for construction, state the request for the adoption of a special (zonal) agreement.

5. The decision on a special (zonal) agreement shall be taken at the first stage of the issuance of a construction permit (in the city of Tbilisi and the city of Batumi, at any stage of the issuance of a construction permit).

6. In the event that the 30-day period is insufficient for taking a decision on a special (zonal) agreement, the period of administrative proceedings shall be extended in accordance with the established procedure.

7. The fee for a special (zonal) agreement shall be determined by the Law of Georgia "On Local Fees".

Article 18. Non-compliance with the requirements of this Chapter and conditional (forced) non-compliance🔗

1. Land plots and buildings and structures that do not comply with the requirements of this Chapter shall be assigned the status of non-compliant land plots and buildings and structures, which shall be assigned by the executive body of local self-government.

2. Land plots and buildings and structures which, by their characteristics, do not comply with the requirements of the development regulation of the relevant zone and whose compliance cannot be ensured, shall be assigned the status of conditionally (forcibly) non-compliant land plots and buildings and structures.

3. Further development (expansion of the territory, change of function, reconstruction) of land plots and buildings and structures having non-compliant and conditionally (forcibly) non-compliant status shall be carried out only subject to the elimination or reduction of the non-compliance. The conditions for reduction may be determined in stages, with a view to final elimination.

4. In the event of elimination of the non-compliance, the non-compliant status shall be removed from land plots and buildings and structures having non-compliant status.

Chapter IIIComposition of the general plan of land use and the development regulation plan

Article 19. Composition of the General Land Use Plan🔗

1. The basis for the development of the General Land Use Plan is legislation, including the Law of Georgia “On the Fundamentals of Spatial Planning and Urban Development” and the planning assignment for the General Land Use Plan issued in accordance with the procedure established by legislation.

2. The General Land Use Plan includes:

a) the textual part;

b) the zoning part;

c) the engineering part;

d) the thematic part.

3. The textual part includes:

a) a description of the General Land Use Plan;

b) an explanatory note to the General Land Use Plan;

c) an assessment of the effectiveness (benefit) of the General Land Use Plan.

d) the stages and sequence of implementation of the General Land Use Plan;

4. The zoning part constitutes the general legal zoning of land use of the project territory, which includes:

a) general recommendatory data on land use intensity;

b) the location of the territory in the existing urban development context, communication and transport lines.

5. The engineering part, depending on the planning assignment, may include:

a) a map of the main water supply and domestic wastewater networks in the project territory;

b) a map of the main electricity supply network in the project territory;

c) a map of the main natural gas supply network in the project territory;

d) a map of the main stormwater drainage network in the project territory;

e) a map of the network of main roads and streets in the project territory.

6. The thematic part, depending on the planning assignment, may include, for example: the tourism development system, the protected areas system, cultural heritage, the recreational areas system, the service centers system and other thematic issues.

Article 20. Pre-design study for the development of the planning assignment of the general land use plan🔗

1. For the development of the planning assignment of the general land use plan, a pre-design study is required in accordance with this Article.

2. The pre-design study includes:

a) study of the physical environment;

b) documentary study;

c) technical-economic justification.

3. The study of the physical environment includes:

a) an orthophoto image of the project territory in its existing condition;

b) a topographic-geodetic map of the project territory;

c) general geological and seismic data of the project territory;

d) general climatic data (natural precipitation, wind, solar radiation) of the project territory;

e) data on the existing natural values of the project territory;

f) data on the immovable monuments of cultural heritage existing in the project territory;

g) the existing ecological data of the project territory;

h) the main network of water supply and domestic sewerage existing in the project territory;

i) the main electricity supply network existing in the project territory;

j) the main natural gas supply network existing in the project territory;

k) the main drainage sewerage network existing in the project territory;

l) the network of main through roads and streets existing in the project territory;

m) data on the owners of land plots existing in the project territory.

2. The documentary study includes data on the existing urban planning documents, legal acts, legal regimes and subordinate normative acts necessary for the planning of the project territory, as well as related analytical and scientific materials.

3. The technical-economic justification includes the main goals and objectives of the project territory and the expediency of planning.

4. The development of the planning assignment of the general land use plan is carried out using, from the list defined by this Article, the data necessary for the planning tasks. Also, for the planning tasks, other additional data may be defined for the pre-design study.

Article 21. Composition of the Development Regulation Plan🔗

1. The basis for the elaboration of the Development Regulation Plan shall be legislation, including the Law of Georgia “On the Fundamentals of Spatial Planning and Urban Development”, the general land use plan, if any, and the planning assignment for the Development Regulation Plan issued in accordance with the procedure established by legislation.

2. The Development Regulation Plan shall be elaborated only for an area of 2000 m² (0.2 ha) or more, and within the administrative boundaries of the city of Tbilisi – for an area of 7000 m² (0.7 ha) or more.

3. The Development Regulation Plan includes:

a) the zoning part;

b) the engineering part;

c) the textual part;

d) the thematic part.

4. The zoning part constitutes the specific legal zoning of land use of the project area, which may include:

a) land plot development coefficients;

b) land plot development intensity coefficients;

c) land plot greening coefficients;

d) a map of the distribution of land plots in the project area (indicating the land plot number and area);

e) development regulation lines (red lines);

f) mandatory development lines (blue lines);

g) schemes for the placement of buildings on land plots.

5. The engineering part may include:

a) a map of the main and local water supply and domestic sewerage networks in the project area, indicating the capacities intended for specific land plots;

b) a map of the main and local electricity supply networks in the project area, indicating the capacities intended for specific land plots;

c) a map of the main and local natural gas supply networks in the project area, indicating the capacities intended for specific land plots;

d) a map of the main and local drainage sewerage networks in the project area, indicating the capacities intended for specific land plots;

e) a map of the main and local road and street networks in the project area.

6. The textual part includes:

a) a description of the Development Regulation Plan;

b) an explanatory card of the Development Regulation Plan;

c) an assessment of the effectiveness (benefit) of the Development Regulation Plan.

d) the stages and sequence of implementation of the Development Regulation Plan;

7. In the historical development protection and regulation zones, the Development Regulation Plan, in addition to the requirements established by this article, shall additionally include the following parts:

a) requirements for the protection and rehabilitation of cultural heritage:

a.a) requirements for intervention in rehabilitation objects (monuments and other cultural heritage objects, background development, public space);

b) requirements for the development of territories and new construction:

b.a) identification of conservation and development areas, indicating buildings to be demolished and to be preserved);

b.b) permissible parameters of new construction (scale, height, spatial and planning configuration, rhythm of facades, fenestration);

b.c) requirements for the improvement of public space”.

8. The thematic part, based on the planning assignment, may cover thematic issues.

Article 22. Pre-design study for the development of the planning assignment of the development regulation plan🔗

1. A pre-design study is required for the development of the planning assignment of the development regulation plan.

2. The pre-design study includes:

a) study of the physical environment;

b) documentary study;

c) technical-economic justification.

3. The study of the physical environment includes:

a) an orthophoto image of the project territory in its existing condition;

b) a topographic-geodetic map of the project territory;

c) general geological and seismic data of the project territory;

d) general climatic data (natural precipitation, wind, solar radiation) of the project territory;

e) data on the existing natural values of the project territory;

f) data on the immovable monuments of cultural heritage existing in the project territory;

g) the existing ecological data of the project territory;

h) the main and local networks of water supply and domestic sewerage existing in the project territory;

i) the main and local networks of electricity supply existing in the project territory;

j) the main and local networks of natural gas supply existing in the project territory;

k) the main and local networks of drainage sewerage existing in the project territory;

l) the main and local network of roads and streets existing in the project territory;

m) data on the owners of land plots existing in the project territory.

4. The documentary study includes data on the legal acts of the existing urban planning documents, legal regimes and subordinate normative acts necessary for the planning of the project territory, as well as related analytical and scientific materials.

5. The technical-economic justification includes the main goals, tasks and the expediency of planning of the project territory.

6. In the zones of protection of historical development and of development regulation, the basis for the development of the planning assignment of the development regulation plan is the historical-cultural reference plan, which includes information and analytical material reflecting the cultural heritage protection zones and the monuments therein, and the historically formed environment.

7. The development of the planning assignment of the development regulation plan is carried out with the data from the list defined by this Article that are necessary for the planning tasks. Also, for the planning tasks, other additional data for the pre-design study may be determined.

Chapter IVFormation of the goals, development and approval of spatial-territorial planning documents of settlements, introduction of amendments thereto and publicity of these processes

Article 23. Procedure for approval of spatial-territorial planning documents of settlements🔗

1. The procedure for approval of spatial-territorial planning documents of settlements is carried out in two stages, each of which involves independent administrative proceedings. Only after the completion of the administrative proceedings provided for by the first stage and the issuance of a positive administrative-legal act may the administrative proceedings of the subsequent stage be commenced. The time limits for the administrative proceedings of these stages are:

a) Stage I _ approval of the planning assignment for spatial-territorial planning documents of settlements, in accordance with the procedure of simplified administrative proceedings established by Chapter VI of the General Administrative Code of Georgia _ no more than 20 days;

b) Stage II _ approval of spatial-territorial planning documents of settlements, in accordance with the procedure of public administrative proceedings established by Chapter IX of the General Administrative Code of Georgia _ no more than 30 days.

2. Both stages of the administrative proceedings related to the approval of spatial-territorial planning documents of settlements are conducted by the relevant executive body of the relevant self-government, while the administrative-legal acts are issued by the Sakrebulo:

a) Stage I _ administrative-legal act on approval of the planning assignment for spatial-territorial planning documents of settlements;

b) Stage II _ administrative-legal act on approval of spatial-territorial planning documents of settlements.

3. Administrative-legal acts related to the approval of spatial-territorial planning documents of settlements shall comply with the requirements established for an administrative act by Chapter IV of the General Administrative Code of Georgia.

4. An urban planning document that covers a cultural heritage protection zone/zones is approved by the relevant body in agreement with the Ministry of Culture, Monument Protection and Sports of Georgia, in accordance with the procedure established by legislation.

4¹. On the territory of the city of Tbilisi, the development regulation plan is approved by the Mayor of the City of Tbilisi on the basis of the commission's conclusion.

5. Amendments to the general land use plan and the development regulation plan shall be made in compliance with the procedures defined by this article, except for the cases defined by Article 14 of this Law.

6. Before the commencement of administrative procedures for the approval of spatial-territorial planning documents of settlements, the relevant executive body of the relevant self-government shall ensure the implementation of the following measures:

a) In the case of the elaboration of a general land use plan and in the case of the elaboration of a development regulation plan, when there is no general land use plan for the territory to be planned:

a.a) Presentation of the proposed considerations and goals for the development of the territory to be planned;

a.b) Determination of the period for receiving opinions/assessments from interested and third parties on the proposed views and objectives for the development of the territory to be planned;

a.c) Conducting a pre-design study for the territory to be planned;

a.d) Elaboration of a draft planning assignment for the land use general plan.

b) When elaborating the development regulation plan, in the case where the territory to be planned falls within the boundaries of the relevant land use general plan, if necessary:

b.a) Presentation of the proposed views and objectives for the development of the territory to be planned;

b.b) Determination of the period for receiving opinions/assessments from interested and third parties on the proposed views and objectives for the development of the territory to be planned;

b.c) Conducting a pre-design study for the territory to be planned.

Article 24. Publicity of the process of formation, elaboration and consideration of the goals of spatial-territorial planning documents of settlements🔗

1. Publicity of the process of formation, elaboration and consideration of the goals of spatial-territorial planning documents of settlements, in addition to the requirements defined by the Law of Georgia “On the Fundamentals of Spatial Arrangement and Urban Planning”, shall be additionally ensured in accordance with paragraphs 2, 3 and 4 of this Article.

2. In the case of elaboration of a general land use plan, by placing an information board in a visible place in front of the administrative building of the Sakrebulo of the relevant self-government and the following information on it:

a) information on the customer (orderer) of the general land use plan;

b) information on the administrative body approving the general land use plan;

c) information on the boundaries of the territory to be planned and the approximate views and goals of their development;

d) the period for receiving views/assessments from interested and third parties on the approximate views and goals of the development of the general land use plan;

e) the procurement deadlines for conducting the pre-project study for the elaboration of the general land use plan;

f) the deadlines of the administrative proceedings for the consideration and approval of the planning assignment of the general land use plan;

g) the procurement deadlines for the elaboration of the general land use plan;

h) the approximate and subsequently specified deadlines of the administrative proceedings for the consideration and approval of the general land use plan.

3. When elaborating a development regulation plan, in the case where the territory to be planned falls within the boundaries of the relevant general land use plan, by placing an information board in a visible place on the territory to be planned and the following information on it:

a) information on the customer (orderer) of the development regulation plan;

b) information on the administrative body approving the development regulation plan;

c) information on the boundaries of the territory to be planned;

d) where necessary, the deadlines for conducting the pre-project study;

e) the deadlines of the administrative proceedings for the consideration and approval of the planning assignment of the development regulation plan;

f) the deadlines for the elaboration of the development regulation plan;

g) the approximate and subsequently specified deadlines of the administrative proceedings for the consideration and approval of the development regulation plan.

4. When elaborating a development regulation plan, in the case where there is no general land use plan for the territory to be planned, by placing an information board in a visible place on the territory to be planned and the following information on it:

a) information on the customer (orderer) of the development regulation plan;

b) information on the administrative body approving the development regulation plan;

c) information on the boundaries of the territory to be planned and the approximate views and goals of their development;

d) the period for receiving opinions/assessments from interested and third parties regarding the approximate considerations and goals of the development of the development regulation plan;

e) where necessary, the timeframes for conducting pre-design research;

f) the timeframes of the administrative proceedings for the review and issuance of the planning assignment of the development regulation plan;

g) the timeframes for the elaboration of the development regulation plan;

h) the approximate and subsequently specified timeframes of the administrative proceedings for the review and approval of the development regulation plan.

5. In the event of amendments being made to the general land use plan and the development regulation plan, the requirements of this Article shall be observed.

Chapter VConditions for the placement of buildings and structures on land plot(s), determination of their maximum heights and the intrusion of their parts into public territory/space

Article 25. Conditions for the placement of buildings on land plot(s) and determination of their maximum heights🔗

1. The purpose of determining the conditions for the placement of buildings on land plot(s) and their maximum heights is:

a) establishment of conditions for the placement of buildings on land plot(s);

b) determination of the interdependence between the maximum permissible height(s) of buildings on land plot(s) and the distances from these building(s) to the neighbourhood boundaries of adjacent land plots;

c) determination of the interdependence between the maximum permissible height(s) of buildings on land plot(s) and the distance from these building(s) to adjacent streets and/or other public spaces.

2. The conditions established by this rule for the placement of buildings on land plot(s) and determination of their maximum heights shall apply if the development regulation plans do not establish different regulation for specific land plots in the cultural heritage protection zones of settlements:

a) conditions for the placement of buildings on land plot(s);

b) the interdependence between the maximum permissible height(s) of buildings on land plot(s) and the distances from these building(s) to the neighbourhood boundaries of adjacent land plots;

c) the interdependence between the maximum permissible height(s) of buildings on land plot(s) and the distance from these building(s) to adjacent streets and/or other public spaces.

3. For the public-business zone, by the development regulation plan, and for special construction regulation zones, by the respective regulation, it is also possible to establish different values of Y determined by paragraph 2 of Article 27 of this Chapter.

4. The requirements of this Chapter shall not apply to structures, including:

a) masts and towers;

b) airport, seaport and railway structures;

c) aerial cableway structures;

d) hydro-, thermal and nuclear power plants, as well as electrical substations;

e) oil, petroleum products and liquefied gas storage facilities, terminals;

f) shore protection, linear and other engineering structures of special purpose;

g) monuments.

5. The conditions for the placement of the objects provided for by paragraph 4 of this Article and their maximum heights shall be determined on the basis of other normative acts, if such exist.

6. The body issuing the construction permit shall act according to the following principle – if buildings were constructed before the entry into force of these "Basic Provisions for Development" in non-compliance with the requirements of this Chapter, during their reconstruction it shall be inadmissible to further increase the degree of existing non-compliance with the requirements of this Chapter. All possibilities shall be used to reduce it.

7. For those objects in respect of which the procedure for issuing a construction permit was commenced before the entry into force of these "Basic Provisions for Development", the regulation in force at the time of submission of the application shall apply.

8. When placing buildings on land plot(s) and determining their maximum heights, when a specific issue is regulated by several norms that do not contradict each other but impose different conditions, in such a case the requirements of all relevant norms shall be satisfied.

Article 26. Placement of buildings on a construction land plot🔗

1. For the purposes of this Chapter, the boundary (cadastral boundary) of a construction land plot is of 2 types:

a) public boundary of a construction land plot – when the construction land plot borders a street and/or other public space (except a dead end);

b) neighbourhood boundary of a construction land plot – when the construction land plot borders a construction land plot, or a non-construction land plot that does not constitute public space.

2. The boundary zone constitutes the part of the construction land plot that is less than 3.0 metres away from the neighbourhood boundaries of the land plot.

3. On a construction land plot, in accordance with paragraphs 4 and 5 of this article, for the purpose of determining the rear yard of the construction land plot, development regulation line(s) (red line(s)i) shall be established.

4. In the case when a construction land plot borders a street or other public space on only one side, then red line(s) shall be established at a distance of 3.0 metres from the neighbourhood boundary(ies) opposite (not bordering) the public boundary.

5. In the case when a construction land plot borders two mutually intersecting streets or other public spaces, then red line(s) shall be established at a distance of 3.0 metres from the neighbourhood boundary(ies) opposite (not bordering) the public boundaries, until their intersection.

6. For the purposes of this Chapter, two adjacent (intersecting) boundaries of a land plot boundary that form an angle from 160 degrees to 180 degrees with each other constitute one side of the land plot boundary.

7. If, due to the contour of the cadastral boundary of a construction land plot, it is not possible to separate the neighbourhood boundary opposite (not bordering) the public boundary of this land plot and, consequently, it is not possible to establish red line(s) for determining the rear yard of the construction land plot, then the placement of a building on the land plot shall be carried out in accordance with paragraph 24 of this article.

8. The part (area) of a construction land plot that is located between the neighbourhood boundary(ies) opposite (not bordering) the public boundary(ies) and the red line(s) established in accordance with this article is part of the boundary zone, which, for the purposes of placing buildings on the construction land plot, is called the rear yard of the construction land plot.

9. In the case when a construction land plot has public boundaries opposite (not bordering) each other and/or a neighbourhood boundary on only one side, then for the placement of a building on it, the rear yard on the construction land plot shall not be determined.

10. All calculated surfaces of a building that form an angle from zero to 45 degrees inclusive with the imaginary vertical plane of the boundary shall be considered as located on the side of the corresponding boundary.

11. Placement of a building or part thereof in the territory of the rear yard of a construction land plot shall be prohibited; the conditions defined by paragraph 12 of this article constitute an exception.

12. Placement of a building or part thereof in the rear yard area of a construction land plot shall be permissible if a building is placed in the rear yard area of the construction land plot adjacent to this construction land plot, in such a way that the requirements of this Article are observed in respect of the other bordering construction land plot(s) on which no building is placed in its rear yard area.

13. A building or part thereof that is located at a distance of less than 3.0 metres from the neighbourhood boundary shall be considered as placed in the boundary zone of the construction land plot.

14. Placement of the design surface of a building or part thereof in the boundary zone of a construction land plot shall be permissible without a door, window, vent and other open part in the wall, as well as a balcony, bay window and terrace, on the side of the neighbourhood boundary. This condition does not apply to those parts of the building which are placed on the side of the public boundary and to the cases defined by paragraphs 15, 15¹, 16 and 19 of this Article.

15. Placement of the design surface of a building or part thereof in the boundary zone of a construction land plot shall be permissible without a door, window, vent and other open part in the wall, as well as a balcony, bay window and terrace, on the side of the neighbourhood boundary. This condition does not apply to those parts of the building which are placed on the side of the public boundary and to the cases defined by paragraphs 15, 16 and 19 of this Article.

15¹. At a distance of less than 3.0 metres from the boundaries of the plots, openings may be arranged on the neighbour's side if the notarially certified consent of the owner of the neighbouring land plot registered in the public register is obtained for this.

16. In the boundary zone of a construction land plot, a door, window, vent and other open part in the wall, as well as a balcony and bay window, may be arranged on a building if the design surface of the building (on which such parts are located) forms an angle of 75 to 90 degrees with the vertical imaginary plane of the neighbourhood boundary and is at a distance of not less than 0.6 metres from the neighbourhood boundary.

17. In the case of the existence of a fire-resistant solid common fence on the neighbourhood boundary or a fire-resistant solid fence within the land plot, in the boundary zone, it is possible to arrange a window, door or other open parts in the wall of a building located in the boundary zone, provided that their upper mark is 0.6 m lower than the upper mark of the fence. In the case of dismantling such a wall, if it is not restored within a reasonable time, then the open parts existing in the boundary zone shall be filled with non-combustible construction material.

18. The height of the arrangement, on the design surface, of a door, window, vent and other open part in the wall on the side of the neighbourhood boundary of a building depends on the perpendicular distance from the design surface existing on the side of the neighbourhood boundary of the building to the imaginary vertical plane of the neighbourhood boundary, in accordance with the list given below:

a) in the case of a distance of 3.0 m – at a height of up to 7.5 m;

b) in the case of a distance from 3.0 m to 10 m – in accordance with the following ratio of the following formula: distance divided by 0.4;

c) in the case of a distance of more than 10 m – up to the maximum height of the design surface.

19. At a distance of up to 5.0 metres from the neighbourhood boundary, the use of combustible construction materials for the structure and for the cladding of a part of a building shall be inadmissible. The said condition also applies to that part of the building which is located on the side of the public boundary, in the case where the width of the street is less than 5.0 m.

20. In the case where a door, a window and another open part in a wall are arranged on the design surface of a building or on a part thereof in compliance with the requirements of this Article, then, in the distance between the neighbourhood boundary and the two nearest points of the building, such parts of the building protruding towards the neighbourhood boundary up to 1.2 metres as: a balcony, an oriel, the entrance stair(s) to the building, their roofs and other similar architectural-structural parts shall not be taken into account, and at the same time the distance from the edge of these parts to the neighbourhood boundary shall be not less than 1.8 metres. In the case where the protrusion of such architectural-structural parts is more than 1.2 metres, then the distance of the building to the neighbourhood boundary shall be determined by the distance between the imaginary vertical plane of the neighbourhood boundary and the nearest points of these parts.

21. On a construction land plot, in the boundary zone, in compliance with fire safety requirements, the following shall also be permissible:

a) the placement of an auxiliary building-structure (e.g.: the arrangement of entrance stairs and ramps of a building-structure and their roofing for the purpose of protecting them from precipitation, car parks, terraces, open playgrounds for children, a storage room for inventory, a shed, structures of agricultural purpose, including shelters for domestic animals and poultry, in those zones of settlements where such are permitted, and other similar types of building-structures), the height of which from the ground surface does not exceed 3.5 metres, and in the case of a pitched roof — 5.0 metres to the ridge;

b) the placement of such auxiliary building-structures as defined by subparagraph "a" of this paragraph, the height of which from the ground surface to the ridge exceeds 5.0 metres. In this case, the conditions established by this rule for the placement of buildings on land plot(s) and for the determination of their maximum heights shall apply to them.

22. A construction land plot does not have a public boundary when it is connected to a street and/or other public space only by a dead-end or an access road.

23. In the case where a construction land plot does not have a public boundary, then, for the placement of a building on the construction land plot, in the boundary zone established in accordance with the second paragraph of this Article, the requirements defined by this Article for the rear yard of the construction land plot shall apply, or the placement of a building on the construction land plot shall be carried out in accordance with paragraph 24 of this Article.

24. On a building constructed in the neighbourhood boundary zone, a door, a window, a gate and another open part in a wall arranged on the side of the neighbourhood boundary may not be used as an obstacle when constructing new building(s) in the boundary zone on the adjacent land plot in compliance with the requirements of this Chapter.

25. In the event that a specific land plot does not afford the possibility of placing buildings in compliance with the requirements of this Chapter, then building(s) shall be placed on it on the basis of the “Scheme for the Placement of Buildings on a Land Plot”, which shall be agreed with the owners of adjacent land plots and reflected by the body issuing the construction permit in the urban planning conditions.

26. When placing a building on a land plot, a building that has an independently functioning foundation structural system shall be considered one building.

Article 27. Determination of the maximum height of a building located on a construction land plot🔗

1. The maximum permissible height of a building on a construction land plot shall be determined from the side of its rear yard and public boundary(ies).

2. The maximum permissible height of a building on a construction land plot shall be determined by the formula H=L/Y, where:

a) L represents:

a.a) the perpendicular distance from the line of contact of the design surface of the building located on the side of the public boundary (street) of the construction land plot with the ground surface to the imaginary vertical plane at half the width of the street;

a.b) the perpendicular distance from the line of contact of the design surface of the building located on the side of the public boundary of the construction land plot with the ground surface to the imaginary vertical plane at half the distance to the opposite boundary (edge) of the public space; in the case where the land plot directly borders a public space or a street which on the other side borders a public space;

a.c) the perpendicular distance from the line of contact of the design surface of the building located on the rear yard side of the construction land plot with the ground surface to the imaginary vertical plane of the neighborhood boundary;

a.d) in the case where the design surface of the building does not constitute a plane, then on the corresponding boundary side L is determined from the nearest point of the building to the imaginary vertical plane of the boundary, respectively, either to the imaginary vertical plane at half the width of the street or to the imaginary vertical plane at half the distance to the opposite boundary (edge) of the public space.

a.e.) The maximum design value of L in residential zones is equal to 20 m, except for RZ-1 and RZ-2 zones, where the maximum design value of L is equal to 6 m. When determining L, a building or structure built in violation of legislation shall not be taken into account.

b) Y represents a coefficient whose value is:

b.a) 0.35 for public-business and special construction regulation zones of settlements;

b.b) 0.25 for industrial zones;

b.c) 0.4 for all other zones.

c) H — design height of the building facade.

3. When a construction land plot is bordered on more than one side by intersecting streets or another public space, the design height of the building facade shall be calculated from the side of the wider street or public space. This height indicator shall also apply to the part of the design surface (facade) of the building located on the narrower street which does not exceed the length of the design surface (facade) facing the wider street, but not more than 20 metres. For the remaining part of the design surface (facade) located on the narrower street, the maximum permissible height shall be determined from the side of its bordering street or other public space.

4. For a land plot that has opposite (non-adjacent) public boundaries, the maximum height of a building placed on it shall be determined from such opposite public boundaries separately, from the side of the street or other public space bordering them.

5. When a construction land plot is located within the area of operation of a public-business zone and is bordered on more than one side by a street or other public space, then the maximum height of the building from the sides of the public boundaries shall be determined from the wider street or other public space bordering such land plot.

6. When a construction land plot is located within the area of operation of a public-business zone and the perpendicular distance between the reference surface located on the rear yard side of the building placed on it and the imaginary vertical plane of the neighborhood boundary exceeds 10 meters, then the maximum height of the building shall be determined from the side of the public boundary(ies) of the construction land plot.

7. When determining the reference heights of buildings, the height of the building facade, in the case of a pitched roof, includes the height of the wall up to the reference edge of the roof, plus:

a) from the slope side

a.a) the height from the reference edge of the roof to the ridge, when the angle of inclination (sum of angles) of the roof plane(s) relative to the horizontal plane of the reference surface exceeds 70 degrees;

a.b) one third of the height from the reference edge of the roof to the ridge, if the angle of inclination (sum of angles) of the roof plane(s) relative to the horizontal plane of the reference surface is from 45 degrees to 70 degrees inclusive.

b) from the gable side

b.a) the height from the reference edge of the roof to the ridge, when the sum of the angles of inclination of the roof planes relative to the horizontal plane of the reference surface is more than 140 degrees;

b.b) one third of the height from the reference edge of the roof to the ridge, if the sum of the angles of inclination of the roof planes relative to the horizontal plane of the reference surface is from 90 degrees to 140 degrees inclusive.

Article 28. Placement of buildings on one construction land plot and determination of their maximum heights🔗

1. The requirements of this Chapter also apply to the case of placement of several different buildings on one construction land plot.

2. In the case of placement of several different buildings on one construction land plot, the requirements determined by this Chapter shall be implemented on the same construction land plot on the basis of establishing imaginary neighborhood boundary(ies) (that is, more than one different building must be placed on one construction land plot in such a way as, in accordance with the requirements of this Chapter, they are placed relative to one another on different construction land plots adjacent to one another).

Article 29. Encroachment into public territory/space of parts of a building and architectural details located on a construction land plot, which does not require agreement with the owner of the public territory/space🔗

1. The requirements of this Article apply to such encroachment into public spaces of parts of a building and architectural details located on a construction land plot, which does not require agreement with the owner of the public territory/space.

2. It is inadmissible for parts of a building and architectural details located on a construction land plot to encroach into a street or other public territory/space at a height of up to 4.5 m from the ground surface:

a) encroachment of balconies and bay windows by more than 0.3 m;

b) any encroachment of other architectural details by more than 0.3 m;

c) encroachment of window sashes/shutters (in a fully open position) by a distance of more than 0.6 m, but the perpendicular distance from the vertical imaginary plane of the pavement edge must be at least 0.8 m.

3. It is inadmissible for parts of a building and architectural details located on a construction land plot to encroach into a street or other public space at a height of more than 4.5 m from the ground surface:

a) encroachment of balconies and bay windows by more than 1.4 m;

b) approach of balconies and bay windows to the vertical imaginary plane of the pavement edge by more than 0.8 m;

c) any projection of facade architectural details by more than 0.3 m;

d) any projection of the finishing cornices of the building and the architectural details of the roof by more than 1.0 m.

4. It is inadmissible for parts of a building/structure located on a construction land plot to encroach into a street or other public space below the ground surface by more than 0.3 m.

5. The water outlet of the rainwater gutters of a building shall not be encroached into public space at a height of more than 0.3 m from the plane of the street pavement, and shall not be encroached onto the pavement at a distance of more than 0.3 m from the public boundary existing on the side of the street or other public space, when it is located above the ground surface.

6. Signs and signboards attached to a building may be encroached into public space at a height above 2.5 m from the ground surface, but the perpendicular distance from the vertical imaginary plane of the pavement edge to these signs and signboards must be at least 0.8 m.

7. A construction land plot bordering a street and/or other public space that do not have a pavement adjacent to this land plot — in such a case, from this land plot the encroachment of parts of the building and architectural details towards the street and/or public space beyond the public boundary by more than 0.3 m shall be inadmissible.

8. A land plot bordering a street that constitutes only a pavement — in such a case, from this land plot it shall be inadmissible:

a) encroachment of parts of the building and architectural details into the street and/or public space by more than 0.3 m, when such street is 3.0 m or less;

b) parts of a building and architectural details on the side of a street and/or public space, at a height of up to 4.5 m from the point of intersection of the building/structure and the pavement, protruding into the public space by more than 0.3 m, where such street is more than 3.0 m;

c) the protrusion of parts of a building and architectural details into a street and/or other public space at a height of more than 4.5 m from the point of intersection of the building and the pavement, beyond the public boundary by more than 0.5 m, where such street is more than 3.0 m.

Article 30. Such protrusion of parts of a building and architectural details located on a construction land plot into public territories/spaces as requires agreement with the owner of the public space🔗

1. The requirements of this Article apply to such protrusion of parts of a building and architectural details located on a construction land plot into public spaces as requires agreement with the owner of the public space (the relevant authorised body of local self-government) and the acquisition, on the basis of a contract, of the right to use the public territory/space.

2. It is permissible to arrange entrance stairs in a building located on a construction land plot from the ground surface up to a ground-level floor whose floor surface is located above the ground surface, or up to the first above-ground floor, but to a height of not more than 4.5 metres, provided that the perpendicular distance from the vertical imaginary plane of the pavement edge to these stairs shall be at least 1.8 metres.

3. It is permissible to arrange entrance stairs and natural lighting in a building/structure located on a construction land plot to a depth of 2.7 metres from the ground surface, provided that the perpendicular distance from the vertical imaginary plane of the pavement edge to these stairs shall be at least 1.8 metres.

4. It is permissible for parts of a building and architectural details located on a construction land plot to protrude into a street or other public territory/space at a height of 2.7 m to 4.5 m from the ground surface as roof structures, awnings, tents, marquees and other architectural parts of a similar type, provided that the perpendicular distance from the vertical imaginary plane of the pavement edge to such architectural parts shall be at least 0.6 metres. Where necessary, support columns may be arranged in such a way as not to impede the functioning of the pavement.

5. The conditions defined by this Article may be applied only in those public territories/spaces where this is permitted by the relevant executive body of self-government.

Article 31. Placement of a common wall/fence on the boundary between neighbouring plots🔗

1. On the boundary between neighbouring plots, a common wall/fence shall be placed on the basis of mutual agreement of the owners of the respective adjoining land plots.

2. A common wall/fence shall be built in such a way that, by its load-bearing capacity, in the case of the construction of blocked (paired) buildings of different heights, it satisfies the requirements of the neighbours.

3. The width of the common wall/fence shall be distributed equally from the boundary between neighbouring plots to both neighbours' sides.

4. If a building to be constructed on one of the construction land plots requires a greater width of the common wall than half of the wall, then this part of the wall shall be built within the boundaries of this plot.

5. During the construction of the foundation of a common wall, one of the neighbours may request the arrangement of such a foundation for the common wall as will be used by him for subsequent construction. The latter is obliged to reimburse the cost of the additional works for the arrangement of the foundation.

6. When using the common wall/fence, the expenses to be borne shall be distributed between both neighbours in proportion to the respective share of the wall.

7. During the reconstruction of a building, on the basis of mutual agreement of the neighbours, it is possible to demolish the common wall/fence in compliance with legislation.

8. Each owner of a construction land plot has the right to reinforce the common wall/fence on his side in compliance with legislation.

9. It is also possible, on the boundary of a construction land plot, to pair agricultural buildings with one (common) wall by agreement of the parties in those zones where the placement of agricultural buildings is permitted.

10. If, when two neighbouring walls are joined, one of the neighbours needs a greater deepening of the foundation for his building than the foundation of the existing wall is, then, in compliance with legislation, he has the right to deepen the foundation of his wall to the level provided for by the design document, in such a way as not to cause damage thereby to the already existing wall.

11. If, during the deepening of the foundation, the wall or foundation of an existing building is damaged and it is established that this was caused by the ongoing construction, then the restoration and reinforcement of the damaged foundation wall shall be borne by the neighbour who is carrying out such construction.

Article 32. Placement of a fence within the boundaries of a land plot and determination of its maximum height🔗

1. Within the boundaries of a land plot, without agreement with the owner of the respective adjoining land plot, a fence may be placed whose height shall not exceed 2.2 metres.

2. Within the boundaries of a land plot, on the basis of mutual agreement of the owners of the respective adjoining land plots, a fence of a height exceeding 2.2 metres may be placed.

Article 33. Use of a Neighbour's Construction Land Plot for the Drainage of Atmospheric Precipitation and for Connection to Main Engineering-Utility Networks🔗

1. Improvement of construction land plots shall be carried out in such a way that from this land plot:

a) water and atmospheric precipitation do not enter the neighbour's plot;

b) atmospheric precipitation that has entered a street or other public space shall not cause damage to the street or other public space and third parties.

2. The conditions specified in paragraph 1 of this Article do not apply to a ravine, gully, river and canal of common use.

3. When, due to the terrain, it is impossible to carry out the measures specified in paragraph 1 of this Article, the neighbour shall be obliged to pass through his/her plot the atmospheric precipitation flowing down from the neighbour's plot.

4. When arranging a building roof on the boundary of a construction land plot, on the side of the neighbour's construction land plot, the customer/owner shall ensure the implementation of such engineering measures as will prevent atmospheric precipitation from entering the neighbour's land plot.

5. The owner of an adjacent land plot shall not have the right to obstruct the passage of the neighbour's engineering-utility networks through his/her own land plot for the purpose of connection to the main engineering-utility networks, if there is no other technical means for this.

6. The neighbour shall be informed in advance one month before the passage of engineering-utility networks through the adjacent land plot; in addition, the adjacent land plot shall permit the carrying out of such works (it shall not affect perennial plantings and existing buildings and structures). In the event that annual crops have been sown, the said work shall be performed after harvesting or payment of compensation. Upon completion of the works, the territory where the engineering-utility networks were laid shall be restored to its original condition.

7. The requirements defined by paragraph 4 of this Article shall also apply to the repair or reconstruction of an engineering-utility network already laid in the neighbour's land plot.

8. Engineering-utility networks laid in a land plot and intended for an adjacent land plot may not be considered an obstacle to the future carrying out of construction on this land plot. Before the start of construction on such a land plot, the network shall be relocated immediately upon demand.