Resolution No. 255 of the Government of Georgia

31 May 2019

Tbilisi

Rules and Conditions for Issuing a Construction Permit and Commissioning a Building/Structure

Article 1🔗

In accordance with subparagraph "c" of the first paragraph of Article 142 of the Code of Georgia on Spatial Planning, Architectural and Construction Activities, the attached "Rules and Conditions for Issuing a Construction Permit and Commissioning a Building/Structure" shall be approved.

Article 2🔗

1. A construction permit issued before 3 June 2019 retains legal force. At the same time, in connection with the commissioning of a building/structure built on its basis, the requirements and rules established by the legal acts in force at the time of issuance of this permit shall apply.

2. As of 3 June 2019, buildings/structures under construction and constructed that, before 3 June 2019, were not subject to the obligation to obtain a construction permit or construction notification shall not require the said permit or notification after 3 June 2019 either.

3. If, before this Resolution enters into force, conditions for the use of a land plot for construction have been issued, then during their period of validity, for the purpose of issuing a permit, the legislation and urban planning plans in force at the time of their approval shall apply.

4. In the case of technical supervision, the legislation in force at the time of conclusion of the contract shall apply.

Article 3🔗

The Resolution shall enter into force on 3 June 2019.

Prime Minister Mamuka Bakhtadze Annex

Rules and Conditions for Issuing a Construction Permit and Commissioning a Building/Structure

Chapter I. General Provisions

Article 1. Scope of Regulation🔗

1. The Rules and Conditions for Issuing a Construction Permit and Commissioning a Building/Structure (hereinafter – the Rules) specify the requirements of the Code of Georgia on Spatial Planning, Architectural and Construction Activities (hereinafter – the Code) and shall be interpreted and applied in accordance with these requirements.

2. These Rules determine:

a) the classes of buildings/structures and types of construction that are subject to a construction permit or construction notification, except for class V buildings/structures;

b) the composition of permit documentation, the rules and conditions for conducting pre-design research for its preparation;

c) permit conditions and the process for their fulfilment;

d) the rules and conditions for recognising a building/structure as fit for commissioning.

3. In a cultural heritage protection zone, or in another special regulation zone, a construction permit shall be issued in accordance with the legal regimes established (designated) for that zone.

Article 2. Definition of terms🔗

1. For the purposes of this Rule, the terms used herein have the following meaning:

a) Non-load-bearing structure – a structure that does not affect the rigidity, strength and stability of the main structural system of a building/structure;

b) Floor/ceiling – a horizontal structural element of a building/structure that vertically separates the floors or premises/living spaces/parking spaces of the building/structure;

c) Landscaping project – a project for the arrangement of the planned landscaping area on the construction site, which may provide for the transplantation of existing green plantings on the site and/or compensatory planting, in accordance with the procedure established by legislation.

d) Ground – a generalized designation of all types of rock, including soil, contained in a land plot;

e) Covered works – construction structural works that, in their completed state, are covered with other materials or ground (e.g., reinforcement embedded in concrete, foundation waterproofing);

f) Temporary building/structure – a structural system composed of prefabricated elements, assemblable and disassemblable and/or mobile, which is connected to the ground and/or water by its own weight and/or dry non-monolithic fastening and does not have underground premises (except for a vehicle);

g) Communication line (network) – a linear structure that ensures communication connection between a supplier and/or users;

h) Stability of the structural system – the ability of a building/structure to maintain stable equilibrium under the influence of design loads;

i) Structural strength – the property of a construction product and structure, their connection joints, the foundation of a building/structure, and the ground to withstand the design load values without fractures;

j) Local engineering-technical networks – a system of engineering networks necessary for the functioning of a specific land plot;

k) Local engineering-technical networks for common use – local engineering-technical networks existing on a specific land plot and/or in a building/structure that are used for common use purposes;

l) Local engineering-technical networks for individual use – local engineering-technical networks existing on a specific land plot and/or in a building/structure that are used for individual use purposes;

m) Load-bearing structure – a structure of a building/structure whose main purpose is load-bearing capacity with respect to structures, equipment, snow, wind, water, seismic, tectonic and other loads;

n) Installation – the assembly and placement of a building/structure or part(s) thereof on a construction site;

o) Zero mark – the control conventional mark of a building/structure, which represents the floor level of the ground-level or first above-ground floor;

p) engineering-technical network – the system of water supply, sewerage, heating, oil product and various gas pipelines necessary for the servicing of a land plot and/or building, as well as electricity supply and wireless or cable communication lines/networks;

q) topographic plan – a large-scale drawing (scale 1:10000 and less) of the orthogonal projection of a part of a territory onto a horizontal plane, which, using conventional symbols, reflects the physical environment without the level curvature of the earth;

r) deformation – change of the shape and dimensions of an object and reduction of stability (settlement, deflection, creep) as a result of various loads and technogenic impacts;

s) occupancy – shall be interpreted in accordance with the Resolution of the Government of Georgia No. 41 of 28 January 2016 "on approval of the technical regulation – rules of safety of buildings";

t) recognition as suitable for acceptance of a building into operation – issuance by an authorised body of an administrative-legal act on construction completed in accordance with the permit conditions;

u) linear structure – a communication structure defined in accordance with these Rules: fence, street, motor road, railway, all types of pipelines, pipe-conduits, aerial cableway, power transmission line, communication line (network), funicular, amelioration and irrigation structure, bridge, tunnel;

v) fire-resistant separating barriers – a wall, partition and other similar [elements] defined in accordance with the Resolution of the Government of Georgia No. 41 of 28 January 2016 "on approval of the technical regulation – rules of safety of buildings".

2. Terms that are not interpreted in these Rules shall be interpreted in accordance with the terms used in the Code of Spatial Planning, Architectural and Construction Activities of Georgia, the Resolution of the Government of Georgia "on the main provisions of regulation of use and development of territories" and the Resolution of the Government of Georgia "on the rules of spatial planning and development of urban planning plans".

Article 3. Authorized Administrative Bodies and Conflict of Interest🔗

1. The administrative body authorized to issue a construction permit for the construction of Class I-IV buildings and structures shall be determined by the Code of Georgia on Spatial Planning, Architectural and Construction Activities.

2. For the purposes of Article 109 of the Code of Georgia on Spatial Planning, Architectural and Construction Activities, other administrative bodies are:

a) Ministry of Economy and Sustainable Development of Georgia – for the construction of a tunnel (including a diversion tunnel of a hydroelectric power plant) or another underground structure at a depth of not less than 25 metres from the ground surface or from the base of a building/structure (if any), as well as for such buildings/structures that are connected to the unified energy system of Georgia and/or that are directly used for electricity generation;

b) Legal Entity of Public Law of the Ministry of Economy and Sustainable Development of Georgia – Technical and Construction Supervision Agency – during the construction of an intra-field and/or intra-facility oil pipeline, a medium-pressure gas pipeline, tanks of a liquid substance storage/terminal with a total volume of up to 1000 m³, natural and/or liquefied hydrocarbon gas filling stations (except a mobile station), motor fuel filling stations, motor fuel filling complexes, a gas distribution station of a main gas pipeline with a capacity of up to 3000 m³/h;

c) Legal Entity of Public Law within the management system of the Ministry of Economy and Sustainable Development of Georgia – Civil Aviation Agency – in the process of construction of an aerodrome and/or in the aerodrome protection area (district), in cases provided for by legislation;

d) Ministry of Regional Development and Infrastructure of Georgia, if administrative proceedings for the issuance of a permit are being conducted in territories/zones of special regulation;

e) Roads Department of Georgia, a state sub-agency institution within the management system of the Ministry of Regional Development and Infrastructure of Georgia – if administrative proceedings for the issuance of a permit are being conducted on a motor road under their ownership as determined by the legislation of Georgia or in roadside zones;

f) LEPL within the management system of the Ministry of Environmental Protection and Agriculture of Georgia – Agency of Protected Areas – if administrative proceedings for the issuance of a permit are being conducted in protected areas;

g) LEPL within the management system of the Ministry of Environmental Protection and Agriculture of Georgia – National Forestry Agency – if administrative proceedings for the issuance of a permit are being conducted in the state forest fund subordinate to its management;

h) Ministry of Environmental Protection and Agriculture of Georgia – if administrative proceedings for the issuance of a permit are being conducted on the territory of the state water fund, in the coastal strip or zone;

i) The LEPL – National Agency for Cultural Heritage Preservation of Georgia – included in the management system of the Ministry of Education, Science, Culture and Sport of Georgia – if administrative proceedings on the issuance of a permit are ongoing in cultural heritage protection zones (except for immovable monuments of cultural heritage and except in the case of relevant delegation);

j) The sub-agency institution – Border Police of Georgia – included in the management system of the Ministry of Internal Affairs of Georgia – if administrative proceedings on the issuance of a permit are ongoing in the border strip and/or border zones;

k) The state sub-agency institution of the Ministry of Internal Affairs of Georgia – Emergency Management Service – for the purpose of ensuring compliance with fire safety requirements at facilities assigned to state fire supervision;

l) The Cultural Heritage Council of the Autonomous Republic of Adjara – if administrative proceedings on the issuance of a permit are ongoing in the territory of the Autonomous Republic of Adjara in cultural heritage protection zones (except for immovable monuments of cultural heritage);

m) Local self-government units – if administrative proceedings on the issuance of a permit are ongoing within their administrative boundaries;

n) In the case of new construction within the administrative boundaries of the city of Tbilisi – Tbilisi City Municipality Mayor's Office, through the structural unit responsible for environmental protection policy (except in the case where, during the construction of individual residential houses assigned to class II, the placement of a building/structure occurs on territory free from green plantings, in compliance with the requirements defined by legislation) and through the structural unit responsible for transport policy;

3. In the process of issuing a construction permit for main pipelines (oil, oil products, associated petroleum gas and natural gas and their transformation products) and for facilities related to main pipelines, in protection zones III and IV, in accordance with this Resolution, at stage I of the construction permit issuance process, a natural or legal person holding a license for the transportation of natural gas or oil provided for by the Law of Georgia "On Licenses and Permits", which operates (exploits) the main pipeline, shall participate, and in the absence of such a person – the owner of the main pipeline.

4. An employee of an administrative body issuing a construction permit and/or exercising state supervision shall not have the right to prepare permit documentation in relation to which the administrative body where he/she is employed adopts a decision.

5. If the person defined by paragraph 4 of this Article is, under Article 19 of the Tax Code of Georgia, in mutual dependence with a person interested in obtaining a construction permit, then he/she shall not participate in the preparation of a specific permit decision.

6. In the event that another administrative body fails to submit a response within the period defined by Article 109 of the Code, the conditions for the use of the land plot for construction and/or the architectural-construction project shall be deemed agreed, if it complies with the requirements established by law. In such a case, the other administrative body shall be obliged to issue written consent within 2 working days from the request.

7. A person authorised to prepare permit documentation, who has commissioned work, shall not be entitled to assume any other contractual obligation that is incompatible with the obligations already assumed. He shall also not be entitled to carry out an expert examination of a project prepared/certified by him.

Chapter II. Types of construction works and classes of buildings and structures

Article 4. Types of construction🔗

1. The types of construction are:

a) New construction (including installation);

b) Reconstruction;

c) Repair (renovation, cladding/equipping);

d) Dismantling (disassembly/demolition of an existing building/structure);

e) Landscape construction.

2. New construction of buildings and structures is construction that is carried out on the part of the land plot where no building/structure stands or where the existing one is completely replaced. New construction also includes the installation/placement of a temporary building/structure.

3. Reconstruction may be of the following types:

a) Reconstruction of a building/structure – change in the volume of the building/structure (expansion or reduction) by not more than 0.04 of the K2 indicator, subject to compliance with the established K2 indicator;

b) Exterior reconstruction – change in the dimensions of the architectural-constructive parts/details of the exterior (the building's design surface, roof) by more than 0.1 meters and/or addition/removal of such parts/details, technical means, including a change of facing material and color, which substantially changes the exterior of the building and does not cause a change in area by more than 1 m²;

c) Reconstruction of load-bearing elements – replacement of a load-bearing structure with a new and/or another type of structure, as well as reinforcement of a damaged/out-of-order load-bearing structure, removal of a load-bearing structure, cutting an opening in a load-bearing structure in the interior of the building;

d) Reconstruction of networks – alteration, replacement, addition or removal of engineering communication networks of buildings and structures;

e) Change of occupancy in Class III, IV buildings and structures;

f) Change of fire-resistant separations in Class III, IV buildings and structures.

3. Repair (renovation, equipping/cladding) does not require a construction permit. Repair is such construction during which defects are eliminated in such a way that the appearance and load-bearing structures of the building/structure are not changed, namely:

a) relocation of partitions in the interior of the building, addition and/or removal of new ones, as well as cutting an opening in them;

b) repair of engineering-technical networks for individual use of buildings and structures;

c) repair/renewal of those parts of engineering-technical systems for common use of buildings and structures that are intended for servicing apartments or other dwellings, parking spaces, storage rooms (including those parts of engineering-technical systems for common use that are located in apartments or other dwellings, parking spaces, storage rooms);

d) repair/renewal of technological equipment and technological systems, as well as local engineering-technical networks and transport mechanical devices;

e) performance of all types of repair and cladding works of a building/structure, including facade and roof works, without substantially changing the dimensions and appearance (except for immovable monuments of cultural heritage);

f) repair-renovation of linear structures without changing their capacity and characteristics, in compliance with technical norms.

4. The landscape construction defined by subparagraph „e“ of paragraph 1 of this Article means the construction of a square, garden, park, boulevard and/or the improvement of a land plot, as well as the arrangement of plantings, lawns and other vegetation cover.

Article 5. Rule for determining the classes of buildings/structures and types of construction🔗

1. For the purposes defined by Article 96 of the Code, in accordance with Annex No. 1 to this Rule, individual buildings/structures and types of construction, according to specific characteristics and parameters, are divided into respective classes.

2. A class is assigned to a building/structure and not to any of its parts. For the purposes of determining the class:

a) the height of a building/structure is determined from the lowest elevation of its foundation: in the case of a building, to the highest elevation of the building's reference surface, and in the case of a structure, to the highest elevation of the structure;

b) the depth of a building/structure is determined from the line of contact of the building/structure with the ground surface to the lowest elevation of the foundation, by the average value;

c) the area of a building is determined by the area enclosed within the outer perimeter of the surface of the floor load-bearing structure (excluding the balcony);

d) the volume of a building/structure is determined: in the case of a building, by multiplying the area enclosed within the outer perimeter of the surface of the floor load-bearing structure of all floors (including the attic) (excluding the balcony and terrace) by the floor height, and in the case of a structure, by the product of the overall dimensions (length, width, height);

e) the height of a fence is determined from the ground surface to the highest elevation of the fence. At the same time, in the case of a sloping ground surface along the fence, by the average height, and in the case of different elevations of the ground surface transverse to the fence, from the highest elevation of the ground surface.

3. If a specific building/structure has characteristics/parameters determining different classes, the assignment of the building/structure to a class is made according to its highest characteristic/parameter.

4. During reconstruction, if the class of the building/structure increases, it is determined according to the final characteristics/parameters provided for by the permit documentation, and if the class of the building/structure decreases, the assignment of the building/structure to a class is made in accordance with the characteristics/parameters of the existing building/structure under reconstruction.

5. If the characteristics determined by the Code and this Rule are not sufficient, the body authorized to issue a permit may determine other additional characteristics of classes of buildings/structures, whereby it will be possible to assign the appropriate class to a specific building/structure.

6. For the purposes of this Article, an individual building/structure is defined as an object that has an independently functioning structural system of foundation.

Chapter III. Requirements for pre-design study

Article 6. Grounds and Types of Pre-Design Study🔗

1. The purpose of conducting a pre-design study is to determine the physical conditions and characteristics of a land plot and/or building/structure and the factors of impact on the environment, and to forecast their changes.

2. A pre-design study shall be carried out:

a) to establish the conditions for the use of a land plot for construction;

b) for the preparation of an architectural-construction project;

c) in other cases provided for by legislation.

3. A pre-design study shall be carried out for the purposes of Articles 103, 106 and 108 of the Code.

4. For the purposes of this article, a pre-design study may be of the following type:

a) topographic study:

b) study of the physical condition of an existing building/structure;

c) development study;

d) documentary study;

e) study of the impact on adjacent buildings/structures;

f) engineering-geological study.

5. The conduct of the study established by subparagraph “a” of paragraph 4 of this article is mandatory during the construction of Class II-IV buildings/structures (except for such type of reconstruction that does not change the topographic picture on the design plot).

6. The conduct of the study established by subparagraph “b” of paragraph 4 of this article is mandatory during the reconstruction of Class II-IV buildings/structures.

7. The conduct of the study established by subparagraph “c” of paragraph 4 of this article is mandatory if a detailed development plan does not apply to the relevant land plot. Such a study shall be carried out in the process of establishing the conditions for the use of the land plot for construction.

8. The need for the study defined by subparagraph “d” of paragraph 4 of this article shall be determined in an individual case, on the basis of the relevant justification, by the administrative body issuing the permit.

9. The conduct of the study defined by subparagraph “e” of paragraph 4 of this article is mandatory if the construction of a building/structure is planned in conditions limited by established development (new construction and reconstruction of load-bearing elements), in the case of a Class III building/structure – within a 10-metre radius of the construction site, and in the case of a Class IV building/structure – within a 20-metre radius, as well as in the presence of another legitimate ground, in order to exclude deformation and damage to the structures of buildings/structures adjacent to the land plot caused by the planned construction.

10. The conduct of the study defined by subparagraph “f” of paragraph 4 of this article is mandatory in the case of construction of Class II-IV buildings/structures. The content of the engineering-geological study shall be determined in accordance with Article 11 of these Rules.

11. When determining the need, composition, scope and method of conducting a pre-design study, already existing information shall also be taken into account.

Article 7. Results of pre-project research🔗

1. Certain types of pre-project research shall be presented as a separate document, which shall consist of textual and/or graphic parts.

2. The result of topographic research shall be reflected in a topographic plan, which is prepared in accordance with established standards and, for the purposes of this rule, shall at minimum include:

a) absolute horizontal (in the coordinate system established by legislation) and vertical marks of the measured territory (including contour lines);

b) all characteristics of the relief of the measured territory (ground surface, description of tree plantings, etc.), all buildings and structures (including underground, above-ground and aerial engineering communications) and the cadastral boundaries of the land plot;

d) the conventional symbols used in the plan.

3. The report on the research of the physical condition of an existing building or structure shall reflect:

a) measurement of the existing building or structure;

c) if necessary, expert assessment for construction implementation documents, on the stability and deformations of load-bearing structures, on the physical impact on the environment surrounding the existing building or structure.

4. The report on the development research shall reflect:

a) photographs of the research territory and a situational plan, showing the research area (if necessary, an orthophoto plan);

b) information on the type of use, the type of development and the main parameters of development in the research area;

c) ecological research – information on pollution of groundwater, soil and/or atmospheric air, information on polluting objects existing in the surrounding territory (if necessary).

5. The report on the research of the impact on the adjacent building or structure shall reflect:

a) recording of the existing condition of adjacent buildings or structures and the degree of possible impact of the planned construction works on them;

b) if necessary, special measures ensuring the preservation of the existing condition of adjacent buildings or structures, which shall also be reflected in the construction organisation project.

6. In the case defined by paragraph 5 of this Article, a permit for the reinforcement works of an adjacent building or structure shall be issued within the framework of the main permit, on the basis of the notarised consent of the owner of the respective adjacent building or structure.

7. The documentary research report shall include the details and requirements of legal acts, legal regimes and subordinate normative acts existing in the research territory, which may have an impact on the construction development of a specific land plot.

Chapter IV. Conditions for the use of a land plot for construction

Article 8. Conditions for the use of a land plot for construction purposes🔗

1. Conditions for the use of a land plot for construction purposes shall be issued in the cases provided for by Article 103 of the Code.

2. Conditions for the use of a land plot for construction purposes shall include:

a) cadastral data and an extract from the public register;

b) main requirements in respect of the construction development of the land plot and/or building:

b.a) functional zone;

b.b) type of use;

b.c) main parameters of development;

b.d) type of development;

b.e) conditions for the placement of a building on the land plot (including development regulation lines and/or mandatory development lines) and for determining the maximum height, and, where necessary, − also the number of storeys;

b.f) type of construction activity;

c) other data:

c.a) where they exist, the regimes established by sectoral plans for the land plot (including a cultural heritage protection zone);

c.b) aspects identified as a result of a pre-design study of the land plot and/or building.

Article 9. Documentation attached to an application regarding the conditions for the use of a land plot for construction purposes🔗

1. The following documentation shall be attached to an application for the approval of the conditions for the use of a land plot for construction purposes:

a) cadastral data and an extract from the public register;

b) a copy of the document confirming the identification of the applicant for a construction permit (in the case of the use of automated management tools – only the relevant details), and, where the application is submitted by a representative, – due authorisation;

c) the applicant's request in relation to the development of the land plot/building;

d) a topographic plan of the land plot with the existing situation (scale 1:500 or 1:1000);

e) a cadastral plan of the land plot (where necessary, additionally a cadastral map) at the established scale;

f) photographs reflecting the existing situation on the land plot;

g) a photograph confirming the placement of an information board in a visible place;

h) other documentation provided for by legislation.

2. The application regarding the conditions for the use of a land plot for construction purposes shall additionally be accompanied by other documentation determined by Article 7 of these rules.

3. The application for the approval of the conditions for the use of a land plot for construction purposes and, where they exist, the attached documentation shall be signed/certified by the person authorised to draw it up (in the case of the use of automated management tools, the relevant rule shall apply).

Chapter V. Permit documentation and documentation attached to a construction notice

Article 10. Basic requirements🔗

1. The permit application shall include the documentation defined by Article 106 of the Code.

2. The graphical part of the permit documentation may include both drawings and illustrations. Drawings may be prepared at the following scales:

a) for main drawings at a scale of 1:50, 1:100 or 1:200;

b) for detailed drawings at a scale of 1:1, 1:2, 1:5; 1:10 or 1:20.

3. In the permit documentation and the documentation attached to the construction notification, each sheet shall be certified in such a way as to enable identification of the person who prepared it, including the responsible specialist.

4. In the permit documentation and the documentation attached to the construction notification, information shall be indicated as to which technical regulation and/or standard was used in preparing the permit documentation.

Article 11. Results of the engineering-geological survey🔗

1. For the purposes of subparagraph "g" of the first paragraph of Article 106 of the Code, the engineering-geological survey report shall at minimum reflect:

a) a plan of the land plot, showing the points of the survey;

b) the physical-mechanical characteristics and specification of the soil of the land plot;

c) a conclusion and/or recommendations for the construction implementation documents.

2. In the case of works carried out for the purpose of an engineering-geological survey, the interested person shall be obliged to restore the territory to its original condition.

Article 12. Architectural Sketch🔗

1. An architectural sketch may be prepared for a separate part of an architectural concept (e.g., exterior solution, placement of buildings on the land plot), in accordance with the purposes of paragraph 1 of Article 113 of the Code and Article 22 of this Rule.

2. Depending on the need (the issue raised), an architectural sketch shall include:

a) a title page, the name and address of the facility;

b) an explanatory note (regarding the design area, the structure of the building and structure, and the volumetric-spatial planning, the artistic-aesthetic solution);

c) technical indicators of the building and structure, including:

c.a) the area of the land plot;

c.b) the built-up area of the land plot;

c.c) the area of the building and structure;

c.d) the parameters determining the class of the building and structure;

d) a schematic plan of the land plot (reflecting the cadastral boundaries of the land plot, axis lines, main overall dimensions, main horizontal and vertical marks, the placement of the designed building and structure on the land plot, and other aspects);

e) schematic drawings of the facades of the building and structure (showing the projection of the cadastral boundary, axis lines, main overall dimensions, main vertical marks, levels of intersection with the ground surface, as well as indicating the main facing material used on the facades and their colors);

3. If necessary, the following shall be additionally submitted:

a) a situational plan reflecting the existing condition of the land plot with appropriate detailing (location according to city streets) and/or an orthophoto plan;

b) characteristic schematic sections of the building and structure (showing the projection of the cadastral boundary, axis lines, main overall dimensions, main vertical marks, levels of intersection with the ground surface);

c) schematic plans of all floors and the roof of the building and structure (showing the projection of the cadastral boundary, axis lines, main overall dimensions, main vertical marks);

d) an axonometric drawing and/or photomontage of the building and structure (indicating the main facing material and their colors).

4. If an architectural sketch is prepared for a Class I building and structure or for a part of an architectural concept, then the documentation defined by paragraphs 2-3 of this Article shall be required accordingly.

Article 13. Architectural Project🔗

1. For the purposes of Article 108 of the Code, the architectural project shall at a minimum include:

a) a title page, the name and address of the object;

b) a table of contents;

c) the conventional notations used;

d) an explanatory note (on the project area, as well as on the structure of the building/structure and volumetric-spatial planning, determination of the zero mark and its relation to the absolute zero mark, and the artistic-aesthetic solution);

e) the technical indicators of the building/structure, including:

e.a) the area of the land plot;

e.b) the built-up area of the land plot;

e.c) the established, existing and used K1, K2 (for each floor) and K3 indicators and their calculated areas;

e.d) the area of the building/structure and, if any: the areas of residential, office-commercial, parking, warehouse, common use (including stairwells, entrances) and other auxiliary spaces (including summer spaces);

e.e) the parameters determining the class of the building/structure.

f) a land plot plan (reflecting the cadastral boundaries of the land plot, axis lines, overall and axial dimensions, placement of the designed building/structure on the land plot, absolute horizontal (in a coordinate system different under the legislation) and vertical marks, landscaping of the land plot and other aspects);

g) a plan of all floors and the roof of the building/structure (showing the projection of the cadastral boundary, axis lines, overall, axial and external architectural part dimensions, vertical marks of the floor surface and the zero mark in relation to the absolute zero mark);

h) characteristic sections of the building/structure (showing the projection of the cadastral boundary, axis lines, main overall and axial dimensions, vertical marks according to floors and architectural parts, and levels of intersection with the ground surface in relation to the zero mark);

i) facade drawings of the building/structure (showing the projection of the cadastral boundary, axis lines, main overall and axial dimensions, marks according to floors and architectural parts, and levels of intersection with the ground surface in relation to the zero mark, as well as indicating all types of facing materials used on the facades and their colours);

j) an axonometric drawing and/or photomontage of the building/structure (indicating the facing construction materials and colours).

2. If necessary, the following shall additionally be submitted: a situational plan reflecting the existing condition of the land plot with appropriate detailing (location according to city streets) and/or an orthophoto plan, a plan of changes to the ground surface of the land plot, a territory improvement plan, drawings reflecting works envisaged outside the cadastral boundaries (for example, paving of a sidewalk, modification of an existing ramp) and other aspects of territory organization.

3. Where necessary, the facade drawing of a building/structure shall reflect the dimensions of all openings and architectural details placed on the facade, and a schematic facade of the building existing on the adjacent land plots (e.g., street elevation).

4. Where necessary, the land plot plan shall be developed on the topographic plan of the land plot.

Article 14. Detailed architectural project🔗

1. Proceeding from the purposes of the first paragraph of Article 106 of the Code, the detailed architectural project shall include the information provided for by Article 13 of these Rules in a refined, specified form and shall provide exhaustive information for the implementation of construction.

2. The detailed architectural project shall additionally include:

a) detailed drawings of individual units;

b) the specification of architectural elements (doors and windows, blinds, etc.), details (finishing elements, products and a.y.) and construction and facing materials;

c) the schemes of engineering communication networks (electrical wiring, gas supply, heating and ventilation, water supply and sewerage), their detailed drawings and specifications;

d) on the territory of the city of Tbilisi, as well as the land plot landscaping project, which, along with other data, must necessarily include the information provided for by subparagraphs „a“, „c“, „d“, „e“ and „f“ of paragraph 5 of Article 19 of this Resolution (except for individual residential houses assigned to class II, as well as the architectural projects of those buildings/structures whose approval is required in the functional zone of the land plot in which the k-3 coefficient is not defined);

e) on the territory of the city of Tbilisi, the road traffic organisation scheme, with the transport/road infrastructure of the project territory shown in connection with the study area (except for class II buildings/structures), as well as an assessment of the impact of the design decision on the existing study transport/road infrastructure (except for the construction of buildings/structures with an area of less than 6000 sq. m and/or a night club, warehouse, production and industrial facilities, a museum, a library, a place of worship).

3. In addition to the technical indicators defined by subparagraph „c“ of paragraph 2 of Article 12 of these Rules, the detailed architectural project shall also include: the construction area of the building/structure; the construction volume of the building/structure; the characteristics of the engineering communication networks of the building/structure.

Article 15. Structural scheme🔗

1. Proceeding from the purposes of the first paragraph of Article 106 of the Code of Spatial Planning, Architectural and Construction Activities of Georgia, the structural scheme consists of a textual and a graphic part, which define the overall dimensions of the main load-bearing structural elements of buildings and structures; the type of foundation, roof covering and vertical elements (columns, pylons, load-bearing walls); the initial data for calculating the strength, stability and deformation of the building/structure (physical-mechanical properties of materials, stiffnesses, values of static and dynamic loads), the name of the computer calculation package used for the spatial analysis and the results of the calculations (illustrated stress-strain state, displacement and oscillation period), which must satisfy the requirements of the technical regulation/regulations indicated in the respective and in the same structural scheme.

2. The structural scheme shall include at minimum:

a) a title page, the name and address of the object;

b) an explanatory note (on the seismicity of the design territory, the structural solution of the structure of the design building/structure, the main construction materials, as well as, in the case of conducting a pre-design study, on taking into account the results of the study).

Article 16. Structural design🔗

1. Proceeding from the purposes of the first paragraph of Article 106 of the Code, the structural design shall include all the information provided for by Article 15 of this rule in a refined, specified form and shall provide exhaustive information for the implementation of construction.

2. The structural design shall additionally include:

a) the main drawings of the arrangement of the base, the foundation and the roof covering (showing the types of vertical load-bearing structures (columns, pylons, load-bearing walls, etc.), the lines of axes, the main overall and axial dimensions, the vertical elevations of the roof covering surface);

b) detailed drawings of individual joints;

c) a specification of structural elements, details and construction materials.

Article 17. Technological scheme🔗

1. Proceeding from the purposes of the first paragraph of Article 106 of the Code, the technological scheme shall include at minimum:

a) a title page, the name and address of the object;

b) the technical indicators of the equipment-unit and/or system;

c) an explanatory note (on the technological description of the design territory and the building/structure, the technological solution of the equipment-unit and/or system);

d) the main drawings of the equipment-unit and/or system (showing the location in the building/structure, the main overall dimensions) and their calculations (for strength, stability and deformation).

2. Where necessary, the following shall additionally be submitted:

a) detailed drawings of individual joints;

b) specification of technological parts, by types;

c) other information, proceeding from the technological peculiarity and need.

Article 18. Construction Organisation Project🔗

1. Proceeding from the purposes of the first paragraph of Article 106 of the Code, the construction organisation project shall include at least:

a) a title page, the name and address of the facility;

b) an explanatory note with the following information:

b.a) description of the organisation of the construction site and the carrying out of preparatory works;

b.b) description of the construction sequence, stages and their duration determined by these rules;

b.c) if any, a list of the acts of concealed works, inspection and testing that must be drawn up during the construction process;

b.d) description of the methods and measures for ensuring safety.

c) a construction site plan (showing the cadastral boundaries of the land plot, the boundaries of the construction site, the placement of the designed building/structure, the scheme of movement and placement of construction machinery on the construction site, as well as the locations of construction materials and temporary buildings/structures);

d) a calendar schedule for the implementation of construction, according to the construction sequence, stages and their duration:

d.a) for Class II construction – at least 3 and at most 5 stages;

d.b) for Class III construction – at least 5 and at most 10 stages;

d.c) for Class IV construction – at least 10 stages.

2. In the construction organisation project, where necessary, the following shall additionally be reflected:

a) measures to be implemented in respect of the land plot adjacent to the construction site and/or public space (e.g., expansion of the construction site and/or arrangement of a temporary road), indicating the optimal period and time;

b) special measures to be implemented in respect of adjacent buildings/structures that ensure their stability/strength during the construction process and/or do not cause deterioration of their stability/strength.

3. The construction organisation project shall be detailed enough to provide comprehensive information for the implementation of the construction.

Article 19. Information Board🔗

1. The purpose of the regulation of this article is to create appropriate preconditions for the implementation of Articles 106, 110, 128 and 134 of the Code.

2. Before the commencement of administrative proceedings on the approval of the conditions for the use of a land plot for construction, the information board shall contain:

a) contact information of the applicant for a construction permit;

b) the address of the land plot;

c) the type of construction and the functional purpose of the building/structure;

d) the name/address of the body issuing the construction permit and the time limits for consideration of the application;

e) the estimated number of floors and/or dimensions of the building/structure.

3. Before the commencement of administrative proceedings on the issuance of a construction permit, the information board shall, in addition to the information established by paragraph 2 of this article, additionally contain the particulars of the conditions for the use of the land plot for construction or of the detailed development plan, as well as the specified number of floors and/or dimensions of the building/structure.

4. Within ten days after the issuance of the permit, the permit holder shall update the information on the existing information board and enter the following information:

a) the name and address of the body issuing the construction permit, the permit number and its validity period;

b) the time limits for the commencement and completion of construction;

c) the function and architectural appearance of the facility;

d) the identity of the author(s) of the project.

5. In the territory of the city of Tbilisi, the permit holder shall, within ten days after the issuance of the permit in accordance with the established procedure, place another information board next to the existing information board, which shall contain information reflecting the main aspects and parameters of the landscaping project for the development of the K-3 coefficient at the construction site, namely:

a) the area of the K-3 coefficient;

b) the date of approval of the landscaping project;

c) the species of green plants to be planted (including characteristics – age, height);

d) the completion date of the landscaping project;

e) the person responsible for the care and maintenance of the planted green plants;

f) the duration of care of the planted green plants;

g) the approved landscaping project, which shall be visually represented by a model and/or photo montage.

6. In the case of three-stage proceedings, the applicant for a construction permit shall additionally place on the information board information related to the submission of an application for the approval of the architectural project and to the approval of the architectural project.

7. Any change made to the construction documentation that alters the substance of the information placed on the information board shall be immediately reflected on the information board.

8. The dimensions of the information board and the conditions for placing information on it, for the purpose of ensuring publicity and visibility, may be specified by the bodies issuing construction permits according to the multiplicity of the minimum dimensions. The minimum dimension of the information board is A2 size format.

9. The information board shall be placed throughout the entire period of performance of construction works and shall be removed after the building or structure is recognized as fit for commissioning.

10. Only the information defined by this Article shall be placed on the information board, and its use for advertising purposes shall be prohibited.

11. In the case of planned construction outside the boundaries of built-up territories, the information board shall additionally be placed near the administrative building of the executive body of the municipality in whose area of operation the planned construction is located, at a place specially allocated for this purpose.

12. In the case provided for by paragraph 11 of this Article, the location of the relevant land plot shall additionally be indicated on the information board.

Article 20. Sequence and stages of the construction implementation process🔗

1. For the purposes of Article 18 of this Rule, the construction implementation process is divided into phases, and the phases into stages.

2. The sequence and stages of the construction implementation process shall be determined by the construction organisation project.

3. The construction organisation project shall determine at least two phases of the construction implementation process:

a) Phase I – preparatory works for the construction implementation;

b) Phase II – main works for the construction implementation.

4. The works of the preparatory phase of the construction implementation consist of two stages, and in the case of a change in the ground surface – of three stages:

a) preparatory works related to the arrangement of the construction site, including the demolition of depreciated or other existing structures and the removal of construction waste, the protection of green plantings to be preserved, and the relocation of underground engineering communications;

b) setting out the building/structure on the ground and fixing the main axes;

c) in the case of a change in the ground surface of the land plot, setting out the building/structure on the ground and fixing the main axes after the changed ground surface.

5. Preparatory works include both organisational measures and external and internal works of the construction site, which shall be performed in accordance with the construction implementation documents.

6. The works of the main phase of the construction implementation of a building/structure are divided into the following stages:

a) earthworks for buildings/structures;

b) works for the arrangement of the base of buildings/structures;

c) works for the arrangement of the foundation of buildings/structures;

d) arrangement of the main structural system up to the zero level of the building/structure;

e) arrangement of the main structural system (excluding non-load-bearing structures) from the zero level of the building/structure at a height of at most every 7.0 metres (in the case of floors – in multiples of floors);

f) arrangement of the roof and roofing of buildings/structures;

g) arrangement of non-load-bearing structures;

h) arrangement of local common-use engineering and technical networks of buildings/structures;

i) installation of technological equipment;

j) external cladding works of buildings/structures;

k) landscaping works of the land plot.

7. The works of the main phase of the construction implementation of a linear structure are divided into the following stages:

a) earthworks (e.g.: arrangement of earth embankments, trenches, channels, pits);

b) works for the arrangement of the base of linear structures;

c) works for the arrangement of the grillage;

d) works for the arrangement of pipelines, cable or ropeway lines and other lines;

e) works for the arrangement of piers and supports;

f) works for the arrangement of spans;

g) construction/installation works of buildings/structures necessary for the functioning of the linear structure provided for by the construction document (e.g.: masts, stations, substations, distribution points, storage facilities, terminals and/or other buildings/structures);

h) works for the arrangement of the covering, pavement or track;

i) testing works for a linear structure;

j) improvement works.

8. In the construction organisation project, it is possible to merge, divide and/or remove (in the absence of works) the main sequence stages of construction implementation in accordance with the classes of buildings and structures determined by this Resolution.

9. 10 days before the completion of the construction stage provided for by the permit conditions, the permit holder shall notify the public supervision body of the completion of the construction stage.

10. A record on the completion of construction by the person determined by the Code shall be drawn up on the basis of an inspection of the works carried out at the construction site and the determination of compliance with the permit conditions.

11. The procedure for the acceptance of an individual stage, as well as the issue of measures to be implemented in the event of non-acceptance of a stage, shall be regulated in accordance with the Code.

Article 21. Purpose, scope and types of expert assessment in construction activity🔗

1. Expert assessment in construction activity constitutes confirmation of compliance with legislation, including this Resolution and construction regulations.

2. Mandatory expert assessment shall apply to draft permit documents:

a) detailed architectural project – in the case of class III-IV;

b) engineering-geological – in the case of class II-IV;

c) structural – in the case of class II-IV (except in the case of construction notification);

d) technological – where necessary.

3. Mandatory expert assessment shall also apply to:

a) a building or structure constructed without a permit, or part thereof;

b) a stage of construction of a building or structure that has not been handed over;

c) the existing condition of a building or structure – in the case of reconstruction;

d) the case provided for by paragraph 1 of Article 27 of this rule.

4. The basis for expert assessment may also be:

a) a substantiated request of an interested person;

b) a decision of the customer or the owner;

c) a court judgment;

d) a substantiated decision of the administrative body exercising public supervision of construction.

5. The expert assessment determined under subparagraph „a“ of paragraph 2 of this Article implies compliance with Resolution No. 41 of 28 January 2016 of the Government of Georgia „on approval of the technical regulation – rules for the safety of buildings and structures“, indicating at least the following parts:

a) assessment of occupancy(ies) and occupancy loads;

b) assessment of structural types;

c) assessment of height and area;

d) assessment of exits, approaches to exits, passages and exits from the building;

e) assessment of the capacity of stairways and other means of egress;

f) assessment of accessibility;

g) assessment of requirements for external walls;

h) assessment of roof assemblies;

i) assessment of fire-resistance-rated required separations;

j) assessment of fire protection systems;

k) assessment of fixed devices of the water supply system;

l) where necessary, assessment of other requirements.

6. The expert assessment shall include the method of conducting the expertise, substantiation of the comments and of the positive assessment. The final assessment shall be unambiguously positive or negative. A negative assessment is a ground for refusal to issue a construction permit.

7. The expert assessment defined by this Article shall be carried out by an accredited inspection body and/or a certified expert.

Chapter VI. Construction notification

Article 22. Documentation attached to a simple construction notice🔗

1. A simple construction notice shall include:

a) information on ownership of the land plot and/or the building/structure;

b) an architectural sketch;

c) where necessary, the results of a pre-design study;

d) a preliminary decision (if any).

2. In the case of construction/installation of a structure provided for by an outdoor advertising placement permit, in addition to the documents provided for by paragraph 1 of this Article, the holder of the outdoor advertising placement permit shall attach the outdoor advertising placement permit to the notice.

3. In the case of laying/installation in existing engineering communication channels, shafts and tunnels of communication lines (networks), as well as on existing poles and masts, as well as on other buildings/structures, and in the case of trenching, the simple notice shall include:

a) the consent of the owners of the installation area, the land plot and/or the existing engineering communication structure and/or the condominium owners' association, and in the case of use of public space – also the consent of the executive body of the municipality;

b) the design of the route for laying/installation of communication lines (networks), including a topographic map, showing the existing infrastructure.

4. In the case of construction/installation of Class I linear structures, the notice shall be accompanied by:

a) in the case of construction/installation of underground linear structures: a schematic drawing of the route of the linear structures, and in the case of construction/installation of above-ground linear structures, additionally a schematic drawing of load-bearing structures;

b) the consent of the owners of the installation area, the land plot and/or the existing engineering communication structure and/or the condominium owners' association, and in the case of use of public space – also the consent of the executive body of the municipality.

5. During the construction of a Class I power transmission line, gas pipeline, water supply pipe or sewer pipe, it is not mandatory that the application be accompanied by the consent of an administrative body regarding the placement of this linear structure on a land plot in state/municipal ownership or in public space. In such a case, the administrative body authorised to issue the permit shall, within 5 days, determine the compliance of the application and submit the application, together with copies of the attached documents, to another administrative body (including the administrative body authorised to manage and dispose of land plots in state/municipal ownership, except where it is itself authorised to dispose thereof). The other administrative body shall adopt the relevant decision no later than within 15 days from the submission of the application to the body issuing the construction permit. The compliance of such construction with urban planning documents and the possibility of its implementation shall be confirmed in writing by the administrative body authorised to issue the permit within 20 days from receipt of the application, on the basis of the submitted complete document(s) and the decisions adopted by the other administrative body(ies).

6. In the case of landscape construction, in addition to the documents provided for by paragraph 1 of this Article, the notification shall be accompanied by:

a) a tree and plant inventory plan (with an explanatory card and a data table describing the trees and plants), where necessary;

b) a dendroproject (where necessary);

c) a landscape improvement plan.

7. The architectural sketch defined by subparagraph „b“ of paragraph 1 of this Article shall not be required if the interested person submits an architectural project.

Article 23. Documentation attached to a detailed construction notification🔗

A detailed construction notification shall include:

a) information on the ownership of the land plot and/or building/structure;

b) an architectural project;

c) the results of a pre-design study, where necessary;

d) a preliminary decision (if any);

e) photographs showing the information board.

Article 24. Rule for construction notification/detailed construction notification, temporary buildings and structures🔗

1. Construction notification/detailed construction notification shall be made in accordance with the procedure established by the Code.

2. A decision on a simple construction notification shall be taken within 5 working days, and in the case of a detailed construction notification, within 10 working days.

3. Temporary structures related to the construction of the facility shall be placed for the period determined by the conditions for the use of the land plot for construction.

4. The maximum period of use of a temporary building and structure located in a public and/or adjacent territory is 1 year, and after each expiration of the period, the period may be extended by a maximum of 1 year. After the expiration of the period, when the period is not extended, it is necessary to dismantle (demolish/destroy) the temporary building and structure, remove it from the territory, as well as improve the territory and/or restore it to its original condition.

5. The period of use of a temporary building and structure located in a public territory shall be determined, in each specific case, by the executive body of local self-government by the relevant administrative-legal act.

6. The period of use of a temporary building and structure necessary for carrying out construction, as determined in accordance with the construction implementation documents at the construction site, shall be determined by the construction implementation document.

7. A temporary building and structure located on a non-public, private land plot, except for a building and structure with characteristics subject to Class I under this Resolution, requires a construction permit in accordance with the Resolution.

Chapter VII. Construction permit, fulfilment of construction/permit conditions

Article 25. Content of the construction permit🔗

1. A construction permit shall be issued by an individual administrative-legal act.

2. The following information shall be included in the construction permit:

a) address and registration data of the land plot;

b) date of issuance of the construction permit;

c) number of the construction permit;

d) validity period of the construction permit;

e) functional purpose of the building and structure;

f) stages of construction (supervision);

g) identification data of the holder of the construction permit;

h) class of the building and structure;

i) construction/permit conditions;

j) position and signature of the person issuing the construction permit.

3. In the case of the use of automatic management means, the relevant rule established by legislation shall apply in connection with the signature.

Article 26. Construction/Permit Conditions🔗

1. The holder of a construction permit shall comply with the following construction/permit conditions:

a) have on the construction site a duly certified copy of the construction documentation;

b) carry out construction within the timeframes determined by the construction permit;

c) carry out construction without violating the conditions for use of the land plot for construction and/or the requirements of the detailed development plan;

d) carry out construction without violating the construction documentation;

e) carry out construction in compliance with the requirements of technical regulations;

f) draw up a record on completion of the construction (supervision) stage;

g) ensure completion of the construction works of the main structural system and the exterior, and in the case of buildings/structures of class III-IV, additionally ensure completion of the works for the common and/or public use parts of the interior, the engineering communication networks of local common use, and the arrangement of the territory of the land plot;

h) in the case of new construction and reconstruction of a building/structure, within 6 months after expiry of the construction permit, submit to the authorized body, for recognition as suitable, the building/structure prepared for recognition as suitable for commissioning;

i) immediately upon the request of the authorized administrative body and/or official, make the construction documentation available to it;

j) fulfillment of the obligation determined by Article 97(2) of the Code;

k) other requirements established by legislation.

2. In case of violation of the requirements provided for by paragraph 1 of this article, the holder of the construction permit shall be held liable under the Code of Georgia on Spatial Planning, Architectural and Construction Activities.

3. Compliance with the construction/permit conditions shall be carried out in accordance with this rule and the technical regulations in force in Georgia.

4. Compliance with the sequence of construction (supervision) stages provided for by the construction documentation shall be mandatory.

5. The record on completion of the construction stage shall be signed by the holder of the construction permit and another authorized person participating in the construction activities.

6. The record drawn up on completion of the construction stage of buildings/structures assigned to classes II, III and IV shall, before completion of the next stage established by the construction/permit conditions, be submitted in writing to the relevant body authorized to recognize the building/structure as suitable, and it shall be a document with legal force only after registration with this body.

7. Responsibility for the correctness of drawing up the record on completion of the construction stage shall be borne by the person drawing up the record.

Article 27. Permissible (Minor) Changes in Construction🔗

1. A change in the construction document does not require a new construction permit or a construction notification if the implemented change complies with the requirements of technical regulations, the requirements of the detailed development plan (if any) and/or the conditions for use of the land plot for construction, and an expert opinion on compliance is submitted, which are reflected in the protocol of the relevant stage (except for a change in the class of the building/structure, a change of the facade, the addition of a floor and/or a change by more than 20% of the area of the design building).

2. Undergoing the procedure under paragraph 1 of this article is not required in the case of the following changes to the construction documentation:

a) Minor change of the main dimensions of the load-bearing structural elements of buildings/structures, but not more than 0.1 metres (except for changes in the horizontal cross-section of columns, the width of the supporting wall, the vertical cross-section of girders, and the cross-section heights of inter-floor slabs and cantilevers), which must not cause weakening of the stability of the structural system determined, in accordance with the construction regulations, by the documents for the implementation of the construction of buildings/structures;

b) Change of the built-up area of each floor for facilities assigned to classes I and II, with an accuracy of 1.0 m² for every area up to 100 m²; change of the built-up area of each floor for facilities assigned to classes III and IV, with an accuracy of 1.0 m² for every area up to 200 m², which must not cause weakening of the stability of the structural system determined, in accordance with the construction regulations, by the construction documentation of the buildings/structures;

c) Change of floor height by a maximum of 0.2 metres (for individual residential houses assigned to class II, by a maximum of 0.3 metres), which must not cause weakening of the stability of the structural system determined, in accordance with the construction regulations, by the construction documentation, conversion of a technical floor into an incomplete floor and conversion of an incomplete floor into a full floor;

d) Change of exterior dimensions by not more than 0.4 metres, and change of the dimensions of the building/structure by not more than 0.3 metres, if the cadastral boundaries and the boundary zone are not violated and no such change is made that is not provided for in the permissible changes;

e) Displacement/change and/or addition/removal of non-load-bearing and self-supporting structural elements of the interior;

f) Change, addition or removal of individual local engineering and communication networks of buildings/structures;

g) Replacement of construction materials and products with other construction materials and products having the relevant technical and aesthetic characteristics;

h) Displacement/change of such parts of buildings/structures as, in accordance with this rule, do not require a construction permit;

i) Horizontal displacement of the above-ground and/or underground part of a building/structure in relation to the ground surface by not more than 1.0 metres, subject to observance of the boundaries of the cadastral unit;

j) vertical change of the zero elevation of a building-structure in relation to absolute zero by not more than 0.4 metres (including any type of change conditioned by this change), which must not cause the conversion of a basement floor into a ground-level or above-ground floor;

k) depending on the properties of the ground, additional change of the foundation of the building-structure (in the case of point, strip and monolithic slab foundations) by not more than 0.5 metres;

l) depending on the properties of the ground, additional or lesser deepening of the pile foundation of the building-structure down to the solid part of the ground.

3. Changes permitted by this Article in the construction documentation shall not violate other permit conditions, the requirements of technical regulations, and shall not infringe the rights of third parties.

4. Changes defined in paragraphs 1 and 2 of this Article in the construction documentation (except for the case provided for by paragraph 3 of this Article) constitute permissible changes during the procedure of recognition of the building-structure as suitable for commissioning.

5. Such change of a construction document which provides for the construction of new floor(s) on an agreed object, a change of the development area of the object by more than 20% or a change of the function of this object is prohibited. In such a case, the procedure for obtaining a construction permit must be started anew, in accordance with the applicable legislation.

Article 28. Conservation of construction🔗

1. In the event of suspension of the construction process for more than 6 months by the holder of the construction permit or on another ground, the conservation of the object under construction shall be carried out, of which the administrative body exercising public supervision of construction shall be notified.

2. Conservation implies the observance of the stability, safety and sanitary norms of the object, the maintenance of its structural elements without damage, which ensures the possibility of the subsequent continuation of construction measures, as well as the safety of adjacent buildings and territories.

3. The process of conservation of the object under construction includes:

a) suspension of the performance of the construction works envisaged by the construction documentation;

b) determination of the conditions of conservation and implementation of the measures necessary for conservation;

c) periodic inspection of the object by the holder of the construction permit for safety purposes;

d) placement of a note on the conservation of the object on an information board, in a visible place.

4. The conditions of conservation of the object under construction shall be determined in compliance with the requirements of the relevant construction regulations. Conservation shall be carried out in such a way that its physical wear does not occur, in particular:

a) garbage and construction waste shall be removed from the object;

b) the object shall be arranged so that corrosion of metal structures, articles and elements does not occur; reinforced concrete joints shall be covered with concrete;

c) the foundation and the pit shall be protected from the collapse of slopes, as well as from atmospheric precipitation and water accumulation;

d) safety requirements shall be observed at the object and the construction site;

e) any material (boards, formwork, cement, gypsum, etc.) shall be stacked so that their falling, dropping, spilling, pollution or damage of the adjacent territory does not occur, and no other unforeseen consequences ensue;

f) the impenetrability of the construction site to unauthorized persons shall be ensured (safety fence, locked gate);

g) the object under construction shall not be used as a warehouse, storage, temporary dwelling, or for other purposes;

h) the safety of persons admitted to the construction site shall be ensured;

i) cranes and mechanisms shall be brought into such a state as ensures the avoidance of negative consequences in any weather conditions;

j) a visible note on the conservation of the object shall be made on the information board;

k) in the places and cases determined by legislation, the object shall be wrapped with a protective net by the municipality;

l) depending on wear, the protective net shall be periodically renewed and replaced, as well as the safety fence shall be renewed and repainted;

m) the permit holder/customer shall regularly inspect the conserved object, with the periodicity necessary to ensure the established requirements.

5. In the decision taken by the holder of the construction permit on the conservation of the object under construction and in the notification to the administrative body exercising public supervision of construction, the period requested for the conservation of the object under construction and the conditions of conservation of the object determined in compliance with the requirements of the relevant construction regulations shall be specified.

6. When a building or structure is transferred to the conservation regime, a conservation act shall be drawn up, signed by the holder of the construction permit and the person(s) responsible for public supervision of the specific object. In the event of the non-appearance of the representatives of the administrative body exercising public supervision of construction, the conservation record shall be drawn up by the holder of the construction permit, which shall be valid upon its submission to the administrative body exercising public supervision.

7. From the day of submission of the act provided for by paragraph 6 of this article to the administrative body exercising public supervision, the running of the term of the construction permit shall be considered suspended. The running of the term of the construction permit shall resume after the completion of the conservation regime.

8. The conservation of a building or structure may be effected for no more than three years, and in a territory/zone of special regulation — for no more than one year.

9. After the expiry of the period determined by paragraph 8 of this article, the holder of the construction permit shall be obliged to resume the construction of the conserved building or structure or to carry out demolition.

10. In the event of the elimination of the reasons that caused the conservation of the object, a decision on the continuation of construction shall be taken, which shall be notified to the administrative body exercising public supervision of construction.

11. The requirements of this article shall apply only to buildings and structures determined in accordance with this procedure, including such dilapidated, burnt and unsuitable for recognition as fit for commissioning buildings and structures whose demolition is not provided for.

12. The conservation regime determined by this article shall not apply to demolition works to be carried out on the basis of the relevant decision of the administrative body exercising public supervision of construction or of a court.

13. Liability for violation of the conservation rules shall be determined in accordance with the Code.

Chapter VIII. Recognition of a building or structure as fit for commissioning

Article 29. Concept and Basic Requirements🔗

1. Recognition as suitable for commissioning means the final determination of compliance of completed construction with the construction/permit conditions.

2. The following shall not be subject to recognition as suitable for commissioning:

a) construction assigned to Class I;

b) reconstruction of the exterior (where aesthetic parameters are not regulated);

c) reconstruction of engineering communication networks;

d) dismantling.

3. Recognition as suitable for commissioning of implemented construction is possible if, as a result of the construction carried out, the obligations defined by the construction/permit conditions have been fulfilled and are not violated.

4. An independent (structurally and functionally) object of a complex of buildings and structures, the construction of which has been completed in accordance with the construction/permit conditions, may be recognized as suitable for commissioning if the main-order works have been carried out, the construction/permit conditions are not violated, and it is possible to continue the works in compliance with construction safety norms, subject to ensuring the safety of users, for which the holder of the construction permit and other persons participating in construction activities are responsible.

Article 30. Documentation required for the recognition of a building/structure as fit for commissioning🔗

1. For the recognition of a building/structure as fit for commissioning, it is inadmissible to impose other requirements, except those determined by the construction/permit conditions.

2. Within the period determined for the recognition of the corresponding class of building/structure as fit for commissioning by the body authorised to recognise a building/structure as fit for commissioning, the holder of the construction permit shall apply with an application, which must meet the requirements determined by Article 78 of the General Administrative Code of Georgia.

3. The application shall be accompanied by:

a) milestone protocols drawn up in accordance with this rule on the completion of the construction stages determined by the construction/permit conditions;

b) a measurement reflecting the final state of the building/structure, in 3 copies; in the absence of changes, a declaration on the absence of changes. In such a case, the submission of drawings is not mandatory;

c) submission of photographs reflecting the building/structure;

d) a cadastral measurement drawing, with the building/structure plotted thereon;

e) in the case of the presence of mechanical and technological devices in the building/structure, including lifts and escalators, the acts of testing the installed technological equipment (including, in cases provided for by legislation, fire protection systems) and/or lines, certified by the relevant body. In the absence of such bodies, the results of the test carried out in accordance with the installation documentation of the devices shall be submitted, certified by the installation organisation and the holder of the construction permit.

4. If the holder of the construction permit submits an application to the authorised body for the purpose of recognising the building/structure as fit for commissioning in violation of the period determined for the recognition of the corresponding class as fit for commissioning, the application shall additionally be accompanied by a receipt for the payment of the fine imposed for the violation of the corresponding permit condition.

5. If, at the time of completion of the construction stage of the building/structure submitted for recognition as fit for commissioning, the protocols were not drawn up or were not drawn up in the proper manner, the holder of the construction permit shall be obliged to attach to the application an expert opinion on the compliance of the works envisaged by the construction stages determined by the construction/permit conditions with the permit conditions, and a receipt for the payment of the fine imposed for the violation of the corresponding permit condition.

6. Responsibility for the correctness of the documents submitted for the recognition of a building/structure or part(s) thereof as fit for commissioning shall be borne by the holder of the construction permit and the person who compiled them.

Article 31. Recognition as suitable for commissioning🔗

1. A decision on recognition of completed construction as suitable for commissioning or on refusal to recognize it as suitable for commissioning shall be adopted by the relevant authorized body in accordance with the procedure for proceedings established by Chapter VI of the General Administrative Code of Georgia.

2. The authorized body may inspect and/or measure the building/structure for the purpose of establishing compliance with the construction documentation. In the event of detection of non-compliance, the authorized body shall respond in accordance with legislation.

3. A decision on recognition of the buildings/structures defined by this procedure as suitable for commissioning shall be adopted:

a) in the case of a Class II building/structure – within 15 working days;

b) in the case of a Class III building/structure (up to 1500 m2) – within 15 working days;

c) in the case of a Class III building/structure (more than 1500 m2) – within 20 working days;

d) in the case of a Class IV building/structure – within 30 working days.

4. After expiry of the period provided for by paragraph 3 of this Article, if during this period the relevant administrative legal act on recognition of the buildings/structures as suitable for commissioning or on refusal to recognize them as suitable for commissioning has not been issued, the building/structure shall be deemed recognized as suitable for commissioning, if the completed construction does not contradict the requirements established by legislation. In such case, upon the request of the holder of the construction permit, the authorized body shall be obliged to immediately issue an administrative legal act on recognition of the buildings/structures as suitable for commissioning.

5. By a decision on recognition of completed construction as suitable for commissioning, compliance with construction/permit conditions and/or permissible changes shall be confirmed. The act shall be issued in 3 copies and shall be accompanied by a measurement reflecting the final condition of the building/structure recognized as suitable for commissioning, duly certified by the body issuing the act.

6. Grounds for refusal to recognize a building/structure as suitable for commissioning shall be:

a) failure to submit the documents provided for by Article 30 of this procedure or submission of incorrect documents;

b) in the case provided for by paragraph 2 of this Article, refusal by the holder of the construction permit or his/her representative to allow the authorized body to inspect the completed construction, obstruction, or failure to create appropriate conditions for the inspection;

c) violation and/or non-fulfilment of construction/permit conditions, except for the cases provided for by Article 27 of this procedure.

7. In the case provided for by subparagraph „c“ of paragraph 6 of this Article, which does not cover the case defined by Article 27 of this same procedure, a new permit must accordingly be submitted or an amendment must be made to the permit act.

8. The issue of making amendments to a new permit or to a permit act as defined by paragraph 7 of this Article shall be determined by the Code.

Chapter IX. Simplified procedure for issuing a construction permit

Article 32. Issuance of a construction permit in force majeure situations🔗

1. In the event of extreme necessity (a natural, technogenic and/or other force majeure situation), an authorised state or municipal body may carry out construction activity before obtaining a construction permit. In this case, the said body, while carrying out the construction activity or after its completion, shall apply to the administrative body issuing the construction permit with a reasoned petition for the issuance of a construction permit.

2. In the case defined by paragraph 1 of this Article, an architectural project shall be submitted to the issuer of the construction permit in order to obtain the construction permit.

3. For the purposes of this Article, an architectural project consists of the following documentation:

a) an explanatory card;

b) a land plot plan placed on the topographic plan of the land plot (e.g., where the cadastral boundaries of the land plot, existing engineering-technical networks, the placement of a building/structure on the land plot, access roads, parking areas, fences, landscaping and other parts may be shown);

c) where necessary, a building roof plan (showing the projection of the cadastral boundary) and a plan of all floors of the building showing the projection of the cadastral boundary, the elevation marks of the floor surfaces, the zero mark of the building/structure in relation to the absolute zero mark;

d) the facades of the building/structure;

e) characteristic sections of the building (showing the projection of the cadastral boundary, the elevation marks of the floor surface, the zero mark of the building/structure in relation to the absolute zero mark);

f) photographic material reflecting the existing situation (with distant and close views);

g) photo montage;

h) where necessary, a project for the improvement of the territory of the land plot;

i) information about the designer of the building/structure, which includes the name/designation of the designer, contact information (telephone number and e-mail address), the registration data of the registry of entrepreneurs and non-entrepreneurial (non-commercial) legal entities, as well as the number of the identity document and the personal number.

4. The body authorised to issue a construction permit shall approve the architectural project within a period of no more than 20 working days and shall issue the relevant permit.

5. In the case provided for by this Article, no permit fee shall be paid.

Article 33. Issuance of a construction permit in free economic, industrial and tourist zones🔗

When issuing a construction permit in free economic, industrial and tourist zones, the benefits and requirements provided for by the relevant legislation shall be taken into account.

Article 34. Preliminary decision (approval of architectural sketch)🔗

1. A preliminary decision shall be issued in accordance with Articles 113-114 of the Code and this Rule.

2. In connection with obtaining a preliminary decision, the architectural sketch (construction concept) prepared by an interested person in connection with the construction of a planned building or a part thereof shall include the requirements defined by Article 12 of this Rule.

3. A preliminary decision on the approval of the sketch shall be adopted by the administrative body authorised to issue a permit within 10 working days.

Chapter X. Transitional Provisions

Article 35. Transitional Provisions🔗

Paragraph 5 of Article 22 of this Rule shall enter into force in the city of Tbilisi upon publication, in other self-governing cities – from 1 September 2019, and in all other municipalities – from 1 January 2022.

Annex 1. Classes of buildings and structures and types of construction

No.

Name

Characteristics and parameters

Class

Area

Volume

Height

Depth

Of a span, truss or other structural element

Length

Diameter

Other characteristic

Buildings

up to 50 m²

-

up to 5 m

up to 2 m

up to 6 m

-

except for residential function

I

up to 500 m²

-

up to 12 m

up to 4 m

up to 7 m

-

including a building of class I of residential function

II

up to 6000 m²

-

up to 22 m

more than 4 m

up to 12 m

-

-

III

more than 6000 m²

-

more than 22 m

-

12 m and more

-

-except for bridges with a span of more than 24 m

IV

-

-

-

-

-

-

with pile foundation

Structures

-

up to 20 m³

up to 10 m

up to 10 m

up to 5 m

-

-

I

-

up to 60 m³

up to 15 m

up to 15 m

up to 7 m

-

-

II

-

up to 200 m³

up to 30 m

up to 20 m

up to 12 m

-

-

III

-

up to 1000 m³

up to 50 m

up to 30 m

up to 24 m

-

-

IV

-

-

-

-

-

-

with pile foundation

Linear structures

Oil pipeline

-

-

-

-

-

-

intra-enterprise and/or intra-facility

IV

Gas pipeline

-

-

-

-

-

-

low pressure

I

-

-

-

-

-

-

-

-

-

-

-

-

medium-pressure gas pipeline intended for gas supply to a consumer, with a capacity of up to 500 m³/h

high-pressure gas pipeline intended for gas supply to a consumer, with a capacity of 500 m³/h and above

III

IV

Water pipeline

-

-

-

-

-

up to 500 mm

up to 10 atmospheres

I

-

-

-

-

-

up to 1400 mm

up to 25 atmospheres

III

Sewer pipe

-

-

-

-

-

up to 600 mm

-

I

-

-

-

-

-

up to 1500 mm

-

III

Power transmission line

-

-

-

-

-

-

up to 35 kV

I

-

-

-

-

-

-

up to 110 kV

III

-

-

-

-

-

-

up to 220 kV

IV

Communication line

-

-

-

-

-

-

using existing infrastructure

I

-

-

-

-

-

-

by arranging a trench/ditch

II

Land reclamation and irrigation structure

-

-

-

-

-

-

capacity from 1 to 10 m³ per second

IV

Fence

-

-

up to 2.2 m

-

-

-

-

I

-

-

up to 4 m

-

-

-

-

II

-

-

more than 4 m

-

-

-

-

III

Motor road

-

-

-

-

-

-

motor road of local importance

III

-

-

-

-

-

-

motor road of intra-state importance

IV

Street

-

-

-

-

-

-

part of a street which is a dead-end/passage

I

-

-

-

-

-

-

a through street which is not an avenue and/or boulevard and is not a constituent part of a settlement development corridor

III

-

-

-

-

-

-

a through street which is an avenue and/or boulevard and is a constituent part of a settlement development corridor

IV

Railway

-

-

-

-

-

-

dead-ends and intra-production

IV

Tunnel

except for a class V tunnel

IV

Other structures and installations

Electrical substation

-

-

-

-

-

-

35 kV and 110 kV

III

-

-

-

-

-

-

220 kV

IV

Solar and biogas installation

-

-

-

-

-

-

-

I

Hydroelectric power plant

-
-
-
-
-
-
up to 50 kW (Category V)
I
-
-
-
-
-
-
up to 10000 kW (Categories III and IV)
III
-
-
-
-
-
-
from 10 MW to 50 MW (Category II)
IV
wind power plant
-
-
-
-
-
-
-
III
geothermal power plant
-
-
-
-
-
-
-
III
open playground and/or sports grounds
-
-
-
-
-
-
without spectator stands and/or auxiliary buildings/structures
I
open parking lots
-
-
-
-
-
-
without other buildings/structures
I
reservoir
-
up to 1000 m³
-
-
-
-
-
II
-
up to 10 000 m³
-
-
-
-
-
III
-
up to 100 000 m³
-
-
-
-
-
IV
storage/terminal for liquid substances
-
with total tank volume up to 100 m³
-
-
-
-
-
II
-
with total tank volume up to 500 m³
-
-
-
-
-
III
-
with total tank volume up to 1000 m³
-
-
-
-
-
IV
mechanical means of vertical, inclined and/or horizontal movement
-
-
-
-
-
-
-
III
natural and/or liquefied hydrocarbon station
-
-
-
-
-
-
except for a mobile station
IV
auto service stations/auto service complexes
-
-
-
-
-
-
-
IV
gas distribution station of a main gas pipeline
-
-
-
-
-
-
with capacity up to 3000 m³/h
IV
aerodrome
-
-
-
-
-
-
with code designation below 4D (runway length up to 1800 m and aircraft wingspan up to 36 m) and bearing capacity up to PCN 25
IV
types of construction
new construction (including installation)
-
-
-
-
-
-
-
I-IV
reconstruction of a building/structure
-
-
-
-
-
-
-
I-IV
exterior reconstruction
-
-
-
-
-
-
placement/installation of signs and advertisements on buildings/structures
I
-
-
-
-
-
-
except for immovable monuments of cultural heritage
I
reconstruction of load-bearing elements
-
-
-
-
-
-
-
I-IV
reconstruction of networks
-
-
-
-
-
-
-
I-IV
dismantling
-
-
-
-
-
-
-
I-IV
structure provided for by a permit for placement of outdoor advertising
-
-
-
-
-
-
-
I-IV
landscape construction
-
-
-
-
-
-
-
I
earthworks (including change of relief)
30 m³ and more
I
installation of an air conditioner, ATM, awning, water-collecting channels and drainage on a construction land plot, ramps for persons with disabilities, signs, advertisements and/or a ventilation pipe
-
-
-
-
-
-
-
I
arrangement/dismantling of stairs, shop windows, doors, windows and other openings, if the said works affect the load-bearing structures of a building/structure
-
-
-
-
-
-
-
I