On the Rules and Permit Conditions for Issuing Construction Permits for Objects of Special Importance (Including Radiation or Nuclear Facilities)

Machine translation. This text was translated from Georgian automatically and may contain inaccuracies. Only the Georgian text is legally binding: the original on legali.ge · the official publication on matsne.gov.ge. Translation of the consolidated version of 23.02.2026.

This document in other languages: ქართული (original) · Русский · Türkçe

Type of act
Resolution of the Government of Georgia
Number
№257
Date adopted
31.05.2019

Text of the document

📑 Contents (70 articles)

Government of Georgia

Resolution No. 257

31 May 2019

Tbilisi

On the Rules and Permit Conditions for Issuing Construction Permits for Objects of Special Importance (Except for the Construction of Radiation or Nuclear Facilities)

Chapter IGeneral ProvisionsIn accordance with Article 40 of the Law of Georgia "On Licences and Permits" and paragraph 1 of Article 12 of the Organic Law of Georgia "On Normative Acts", the Rules and Permit Conditions for Issuing Construction Permits for Objects of Special Importance (Except for the Construction of Radiation or Nuclear Facilities) shall be approved.

Article 1. Subject matter, purpose and time limits of the Resolution's regulation🔗

1. This Resolution covers the sphere of regulation of public legal relations related to construction permits for objects of special importance (except for the construction of radiation or nuclear facilities) on the territory of Georgia (hereinafter – construction permit). In particular, it regulates the process of issuing construction permits, fulfilment of permit conditions and acceptance of buildings and structures into operation on the territory of Georgia.

2. The process of issuing construction permits, fulfilment of permit conditions and acceptance of buildings and structures into operation shall be carried out by the Legal Entity of Public Law of the Ministry of Economy and Sustainable Development of Georgia – the Technical and Construction Supervision Agency (hereinafter – the Agency).

3. When calculating the time limits specified in the Resolution, public holidays and days of rest established by the labour legislation of Georgia shall not be counted.

Article 2. Principles of the Resolution🔗

The issuance of construction permits and the establishment of permit conditions shall be carried out in accordance with the following principles:

a) safety of life and health;

b) ensuring a safe environment;

c) protection and preservation of cultural heritage;

d) protection and realisation of the right of ownership;

e) publicity;

f) one-window principle;

g) silence is a sign of consent;

h) principle of responsibility.

Article 3. Definition of Terms🔗

1. For the purposes of this Rule, the terms used herein have the following meanings:

a) Mezzanine – a structure arranged in the interior/living space to create a floor surface, which divides part of the interior/living space into two storeys;

b) Incomplete storey – a storey whose average height from the floor surface level to the ceiling surface is from 1.8 metres to 2.3 metres.

c) New construction – construction carried out on the part of a land plot where no building or structure stands or where the existing building or structure is completely replaced; installation/placement of a temporary building or structure;

d) Non-load-bearing structure – a structure that does not affect the rigidity, strength and stability of the main structural system of a building or structure;

e) Landscaping project – a project for arranging the planned landscaping space on a construction site, which may provide for the transplanting of existing green plantings on site and/or compensatory planting, in accordance with the procedure established by legislation.

f) Development regulation plan – an urban planning document which, for the territories of settlements, establishes land use zones (subzones) and/or specifies the architectural-planning and spatial-volumetric characteristics of individual planning units and development, the placement of buildings, and their planning parameters; specifies the urban planning characteristics of the protection and development of immovable monuments of cultural heritage, the organisation of relief, the improvement and landscaping of territories, and the provision of engineering and transport infrastructure;

g) Developed territory – part of the territory of a settlement which may include any zone defined by the Resolution of the Government of Georgia on the approval of the main provisions for the use of territories and regulation of development, except environmental protection, landscape-recreational, agricultural, transport zone 2 and military purpose zone 2.

h) Ground – a generalised designation of all types of rock, including soil, contained in a land plot;

i) Occupancy – a concept determining the expected hazard arising from the functional purpose of a building or structure or its room or space.

j) Concealed works – such construction structural works which, in their completed state, are covered with other materials or ground (e.g.: reinforcement embedded in concrete, waterproofing of the foundation);

k) Declaration on the absence of changes – a document drawn up by the customer confirming the full compliance of the building or structure submitted for acceptance into operation with the permit conditions.

l) Dismantling – demolition/dismantling of existing buildings or structures or their parts;

m) Temporary building and structure – a prefabricated-element, assemblable-disassemblable and/or mobile system which is connected to the ground and/or water by its own weight and/or dry non-monolithic fastening and does not have underground chambers (except water transport);

n) floor – for all types of storey, its lower horizontal surface. The floor level constitutes the level of this horizontal surface;

o) floor surface – the upper level of the load-bearing structure of the floor (including the inter-storey slab);

p) floor covering surface – the level of the upper clad surface of the load-bearing structure of the floor (including the inter-storey slab);

q) infrastructure – the aggregate of engineering-technical and communal services, as well as communication facilities, structures and networks;

r) communication line (network) – a type of linear structure that ensures communication connection between the provider and/or users;

s) landscape construction – construction of a park, garden, boulevard, square and landscape improvement on construction land plots, as well as arrangement of plantings, lawns and other vegetation cover;

t) local engineering-communal networks – the system of engineering networks necessary for the communal servicing of a specific land plot;

u) local engineering-communal networks of common use – local engineering-communal networks existing on a specific land plot and/or in a building/structure, which are used for common use purposes;

v) loggia – a habitable space recessed into the facade of a building, bounded by walls on three sides, covered, open from the facade side and enclosed by a railing;

w) mansard – an attic space used for dwelling/habitation. A mansard is considered a full storey when the average height from 3/4 of the area of the attic floor surface to the mansard ceiling is 2.5 metres or more;

x) land plot – an object of ownership right, bounded by one continuous line, which constitutes a cadastral unit and, in accordance with this Resolution, may be used for the purpose of developing construction activity;

y) land plot area – the area of the orthogonal projection of the territory bounded by the boundaries of the land plot, with an accuracy of 1 m², unless otherwise provided by legislation;

z) conditions for the use of a land plot for construction – conditions the fulfilment of which is necessary for carrying out construction activity on a specific construction land plot. On the basis of these conditions, the documents for carrying out construction are drawn up;

aa) above-ground storey – a storey whose average height of elevation of the floor level from the ground surface is 1.8 metres or more;

bb) underground storey – a storey whose average height of elevation of the ceiling from the ground surface does not exceed 1.8 metres;

cc) installation – assembly, placement of a building/structure or part(s) thereof on a construction site;

dd) Construction permit for objects of special importance – a permit of special hierarchy, as a rule, is divided into three interrelated, but from the standpoint of administrative proceedings independent stages: Stage I – determination of urban planning conditions (approval of the conditions for the use of the land plot for construction); Stage II – agreement of the architectural-construction project (agreement of the architectural project, structural and/or technological scheme); Stage III – issuance of the construction permit;

ee) structure − a structural system created from construction materials and/or products, immovably connected to the ground, for the use of which for its main purpose the existence of premises /dwellings/parking spaces is not necessary;

ff) zero mark – the control mark of a building-structure, which represents the floor level of the ground-level or the first above-ground floor;

gg) picket – a 100-metre section of a motor road;

gg¹) reconstruction – substantial alteration of an existing building-structure and/or its part(s), for the purpose of their physical, qualitative and characteristic renewal;

gg²) stand – a building-structure or part of a building-structure which is used as a shelter for animals;

gg³) engineering-utility networks – the system of main, common and/or local water supply, sewerage, heating, petroleum products and various gas pipelines existing in the territories of settlements, including on a construction land plot and/or outside its boundaries, as well as electricity supply and wireless or cable communication lines/networks;

gg⁴) construction document – documents developed and approved in accordance with the requirements of this Resolution, which contain textual and graphic information and constitute the basis for the issuance of a construction permit and for the carrying out of construction;

gg⁵) violation of a construction document – such a different carrying out (construction) of a building-structure and/or its part(s) from the construction document as requires a new construction permit;

gg⁶) construction land plot – a land plot located in the territory of a functional zone, duly provided with engineering and transport infrastructure, to which at least one access is connected, including by means of a servitude;

gg⁷) construction site – the territory defined by the construction execution documents, which is necessary for the carrying out of construction works and for its servicing;

gg⁸) construction regulation – normative act(s) regulating construction activity, which include construction-technical norms, construction standards and recommendations;

gg⁹) construction work – a set of actions carried out during the preparation of a construction site, the construction, reconstruction, dismantling, conservation and/or repair of building-structures or their parts;

gg¹⁰) construction activity – the entire process of the preparation of documents for the spatial arrangement of the territory and the planning of settlement development, the preparation of architectural projects, the carrying out of construction site, building and structure and other necessary studies, the preparation of documents for the construction of buildings or their parts, the carrying out of construction and the fulfilment of permit conditions;

gg¹¹) habitable space – a part of a building/structure used for the prolonged stay of people;

gg¹²) design works – a set of works as a result of which construction implementation documents are created;

gg¹³) public territory/space – a street, square, bridge, public garden, park, garden, water surface and its coastal strip, natural or artificial landscape, passage between land plots and other spaces of a similar type located within the boundaries of built-up territories, which are accessible to people;

gg¹⁴) storage space – a building/structure or a part thereof used for keeping objects/movable things, for storage, as a depository;

gg¹⁵) attic – a space located above the roof covering of the last floor of a building, between the outer walls and the inner surfaces of the slope(s) of the pitched roof;

gg¹⁶) terrace (bani) – an uncovered area bounded by walls on one, two, three or four sides and, where necessary, enclosed with a railing on the open side(s), as well as such a flat roof or part of a flat roof the surface of which is finished in such a way that it can be used as a habitable space and which is enclosed on the open side(s) by a railing and/or a parapet. A marquise and an awning may be arranged on the terrace;

gg¹⁷) technical floor – a floor intended for the placement of engineering equipment or for the routing of communications, the average height of which from the floor level to the ceiling is less than 1.8 metres;

gg¹⁸) unauthorised construction − construction carried out without the legal grounds established by the legislation of Georgia or with such a violation of construction documentation as a result of which the function of the building/structure changes and/or the development intensity coefficient is exceeded;

gg¹⁹) building − a structural system created from construction materials and products, immovably connected to the ground, for use for its main purpose the existence of storage spaces/habitable spaces/parking spaces is necessary;

gg²⁰) deformation of a building/structure – a change in the shape and dimensions of the object and a reduction of stability (settlement, deviation, creep) as a result of the impact of various loads and of a technogenic nature;

gg²¹) acceptance of a building/structure into operation – the issuance by the Agency of an administrative-legal act on construction completed in accordance with the permit conditions.

gg²²) acceptance of part(s) of a building/structure into (partial) operation – the issuance by the Agency of an administrative-legal act on the part(s) completed in accordance with the permit conditions of the building/structure.

gg²³) main engineering-utility networks – the system of engineering networks necessary for the utility servicing of a settlement or part thereof;

gg²⁴) ceiling – the lower and surface of the floor slab structure;

gg²⁵) linear structure – a communication structure: motor road, railway, pipelines of all types, pipework, aerial cableway, power transmission line, communication line (network), funicular.

gg²⁶) structural stability – the ability of a building/structure to maintain stable equilibrium under the influence of design loads;

gg²⁷) structural strength – the property of a construction product and structure, of their joints, of the foundation of a building/structure, and of the ground to withstand the design values of loads without failure;

gg²⁸) floor slab – a horizontal structural element of a building/structure which vertically separates the floors or rooms/dwellings/stalls of a building/structure;

gg²⁹) topographic plan – a large-scale (scale 1:10000 and less) drawing of the orthogonal projection of a part of a territory onto a horizontal plane, which, using conventional symbols, depicts the physical environment without the horizontal curvature of the earth;

gg³⁰) fire-resistant separating elements – shall be interpreted as a wall, partition and other similar [elements] defined in accordance with the Resolution of the Government of Georgia No. 41 of 28 January 2016 “on the Approval of the Technical Regulation – Rules for the Safety of Buildings/Structures”.

2. The terms used in this Rule that are not defined in this Article shall be subject to the definitions of terms used in the Code of Spatial Planning, Architectural and Construction Activities of Georgia and in the Resolution of the Government of Georgia on the Approval of the Basic Provisions for the Regulation of the Use and Development of Territories.

Chapter IITypes of construction

Article 4. Types of construction🔗

1. The types of construction are:

a) new construction (including installation);

b) reconstruction;

c) repair-fixing, facing/equipping (does not require a permit);

d) dismantling;

e) landscape construction;

f) installation/placement of temporary buildings and structures.

2. New construction of buildings and structures is such construction as is carried out on the part of the land plot where no building or structure stands or where the existing one is fully replaced.

3. Reconstruction may be of the following types:

a) reconstruction of a building/structure – construction of new floor(s) on buildings/structures, or dismantling of existing floor(s), as well as change of the development area of any of its floors by more than 1 m²;

b) exterior reconstruction – change of the dimensions of architectural parts/elements of the exterior (building facade, roof) by more than 2% and 0.1 metre and/or addition/removal of architectural parts/elements, structures, technical means, which substantially changes the exterior of the building;

c) reconstruction of load-bearing elements – replacement of a load-bearing structure with a new and/or another type of structure, as well as reinforcement of a damaged/out-of-order load-bearing structure, removal of a load-bearing structure, cutting an opening in a load-bearing structure in the interior of the building;

d) reconstruction of networks – alteration, replacement, addition or removal of engineering-utility networks of common use of buildings and structures.

e) change of occupancy in buildings and structures;

f) change of fire-resistant separations in buildings and structures.

4. Repair-fixing, facing/equipping is such construction in the course of which defects are eliminated in a manner that does not change the load-bearing structures, namely:

a) movement of partitions in the interior of a building, addition and/or removal of new ones, as well as cutting opening(s) in them;

b) repair of engineering-utility networks of individual use of buildings and structures;

c) repair/renewal is carried out of those parts of engineering-utility systems of common use of buildings and structures which are intended for the servicing of apartments or other dwellings, parking spaces, storerooms (including those parts of engineering-utility systems of common use which are located in apartments or other dwellings, parking spaces, storerooms);

d) repair/renewal is carried out of technological equipment and technological systems, as well as local engineering-utility networks and transport mechanical devices;

e) performance of all types of repair and facing works of a building/structure, including facade and roof, without substantial change of dimensions and appearance (except immovable monuments of cultural heritage);

f) repair-fixing of linear structures without change of their capacity and characteristics, in compliance with technical norms.

5. Dismantling implies demolition/destruction of a building/structure.

6. Landscape construction constitutes construction of a park, garden, boulevard, square and landscape improvement on construction land plots, as well as arrangement of plantings, lawns and other vegetation cover.

7. The installation/placement of temporary buildings and structures is not new construction.

Chapter IIIObjects of Construction Activity

Article 5. Objects of construction activity🔗

1. The object of construction activity is a land plot and the buildings and structures located thereon, including auxiliary and temporary buildings and structures.

2. The creation and use of an object of construction activity is regulated in compliance with the requirements of legislation, including this Resolution and the construction regulation.

3. Land plots, according to the possibilities of their use for construction activity, are divided into the following types:

a) construction land plot;

b) land plot restricted for construction;

c) land plot unsuitable for construction.

4. A change of the type of a land plot determined by paragraph 3 of this Article for construction activity shall be made on the basis of legislation, including the development regulation plan.

Article 6. Placement of buildings and structures, including linear structures, on the territory of more than one land plot adjacent to each other🔗

1. In the event that the owners of adjacent land plots wish to place a building or structure of common ownership (except a linear structure) on the territory of their own land plots, they shall be obliged to merge their land plots and register them with the National Agency of Public Registry. The foregoing shall not apply to the construction, on individual development territories, of a residential house with a shared wall or of utility buildings and structures of common use.

2. In the case of placement of a linear structure, the consent of the owner of every land plot on which the linear structure is to be placed shall be required.

Article 7. Temporary buildings and structures🔗

1. The maximum term of use of a temporary building and structure placed on a public and/or adjacent territory is 1 year, and after the expiry of each term the term may be extended by a maximum of 1 year. After the expiry of the term, when the term is not extended, the temporary building and structure must be dismantled (disassembled/demolished), removed from the territory, and the territory must be improved and/or restored to its original condition.

2. The term of use of a temporary building and structure placed on a public territory shall, in each specific case, be determined by the executive body of local self-government by a relevant administrative-legal act.

3. The term of use of a temporary building and structure required for carrying out construction, determined in accordance with the construction implementation documents at a construction site, shall be determined by the validity term of the construction permit.

4. A temporary building and structure placed on a non-public, private land plot, except for a building or structure having the characteristics set out in paragraph 4 of Article 51 of this Resolution, requires a construction permit in accordance with the Resolution.

Article 8. Parts and Characteristics of a Building🔗

1. Those parts of the roof which extend over parts intended for pedestrians that are public and/or in the ownership of third parties, or which are located above the entrances to the stairwells, shall be equipped with such devices as ensure protection against the falling of snow, ice or parts of the roof, and safe-to-use means shall be used for carrying out repair works related to the roof.

2. The load-bearing structural parts of buildings (walls, columns, girders, etc.) shall be stable and fire-resistant to the extent required by the relevant construction and technical regulations.

3. Determination of the area used for premises (residential house, apartment, office, commercial and household services):

a) The area for premises shall be determined by the area of the surface of the main structure of the floor existing between its enclosing walls, excluding the area of load-bearing walls and columns existing between them (the area of an apartment shall also not include openings in load-bearing walls and in the walls enclosing the apartment, the internal staircase connecting different levels of the floor in the apartment and its landing);

b) If they exist, the areas of loggias and verandas shall be included in the area of premises.

4. The volume of a building consists of the sum of its above-ground and underground volumes.

5. Determination of the above-ground volume of a building:

a) The above-ground volume of a building shall be determined by the sum of the volumes of its ground-level and above-ground full, incomplete and technical floors, including the volumes of the attic and mansard;

b) The volume of a floor shall be determined by multiplying the area of the outer contour of the floor (excluding balconies and terraces) by the height of the floor;

c) Bay windows, verandas, and loggias shall be included in the area of the outer contour of the floor;

d) The volume of a mansard and attic shall be determined by multiplying the area of the horizontal section of its base contour by its average height.

6. The underground volume of a building shall be determined by the sum of the volumes of its underground full, incomplete and technical floors.

7. A floor whose floor is located at one level shall be considered one floor, as well as a floor where the difference between the floor levels does not exceed 1.8 metres.

8. A building that has an independently functioning structural foundation system shall be considered one building.

9. The structural number of storeys of a building shall be determined by the sum of the underground, ground and above-ground full and incomplete floors of one building.

10. The above-ground number of storeys of a building shall be determined by the sum of the ground and above-ground full and incomplete floors of one building.

11. The height of a floor is:

a) when the floor is located at one level – the average vertical distance between the upper level of the main structure of the floor and the upper level(s) of the main structure(s) of the inter-floor ceiling;

b) when the floor is located at different levels – the average height of the floor levels. The average height of each level of the floor shall be determined in accordance with subparagraph „a“ of this paragraph.

12. The height of a mansard is the average distance between the upper elevation of the main floor structure and the lower surface of the ceiling structure.

13. The structural height of a building is measured from the lower elevation of the foundation of one building's main structure (excluding the height of piles, if any).

14. The built-up area of a floor is determined by the area contained within the outer contour of the floor plan, excluding the areas of terraces.

15. The built-up area of a building is the sum of the built-up areas of all floors.

16. The floor area is the area between the walls and columns bounding the floor, excluding the area of the load-bearing walls and columns located therebetween, plus the areas of balconies and terraces.

17. The area of a building is the sum of the areas of all floors.

18. In addition to the requirements defined by this article with respect to parts of a building, other additional requirements and characteristics, as well as other parts and characteristics of a building, are determined by construction regulations.

Article 9. Classes of buildings and structures for the issuance of a construction permit and commissioning🔗

1. The assignment of a building or structure to a class is carried out according to the parameters of the building or structure to be constructed or demolished; in the case of reconstruction, where the class of the building or structure increases, the class is determined according to the final parameters of the building or structure (as provided for by the construction document). Where, in the case of reconstruction, the class of the building or structure decreases, the assignment of the building or structure to a class is carried out according to the parameters of the existing building or structure being reconstructed.

2. If one specific building or structure has characteristics determining different classes, the class of the building or structure is determined by its highest characteristic.

3. The purpose of determining the characteristics of classes of buildings and structures is to establish the class of the building or structure and the authorised body whose competence includes the issuance of the relevant construction permit. The class is assigned to the building or structure and not to any of its parts.

4. If the characteristics defined by this Resolution are insufficient to determine the class of buildings and structures, the relevant authorised state body is entitled to determine other additional characteristics of classes of buildings and structures, whereby it will be possible to assign the relevant class to a specific building or structure.

5. For the purposes of this article, the height of a building or structure is determined from the lowest elevation of the foundation: in the case of a building – to the highest elevation of the building's design surface(s), and in the case of a structure – to the highest elevation of the structure.

Chapter IVSubjects of construction activity

Article 10. Customer. Rights and obligations of the customer🔗

1. At the first and second stages the customer is represented by the applicant, while at the third stage the customer may be the owner, user, or his/their authorized person of the land plot and the buildings located or to be constructed thereon, who has an interest in the development of the object for construction.

2. The customer shall:

a) ensure, in accordance with the requirements of legislation, the preparation of construction implementation documents;

b) ensure the placement of an information board in a visible place on the relevant territory/building in accordance with the requirements of this Resolution;

c) obtain a construction permit in the cases determined by legislation and in the established manner;

d) ensure the fulfilment of the permit conditions;

e) organize, in the established manner, the passing of the relevant procedures for the acceptance into operation of completed buildings;

f) upon suspension of construction works, carry out the conservation of the building under construction in accordance with Article 61 of this Resolution;

g) before the commencement of construction works, have at the construction site a duly certified copy of the construction document and the documentation provided for by paragraph 2 of Article 18 of this Resolution, signed by the responsible person;

h) upon the demand of the authorized administrative body and/or official, ensure familiarization with the documentation provided for by paragraph 2 of Article 18 of this Resolution.

3. The customer has the right to:

a) in accordance with the requirements of legislation, transfer his authority to another person who, in relations of construction activity, will be represented with the authority of the customer;

b) in accordance with the requirements of legislation, organize the implementation of technical supervision of the construction process;

c) carry out other types of activity that are not prohibited by legislation.

4. Other rights and obligations established by legislation apply to the customer.

5. At various stages of the implementation of construction activity, the customer may be a different person, and at any stage it must be possible to determine who is the customer of a specific building. In the event that the identity of the customer cannot be determined, the owner shall be considered the customer.

6. In the event of non-fulfilment or improper fulfilment of the rights and obligations assigned to him, the customer shall bear responsibility in accordance with legislation.

7. The customer is responsible for the correctness of the documents submitted by him.

Article 11. Responsibility of the main specialists participating in construction activity🔗

The main specialists participating in construction activity are responsible for the correctness of the document executed by them and/or the work performed.

Article 12. Principal specialists participating in construction activity🔗

1. Conflict of interest applies to the following principal specialists in construction activity:

a) The architect designing a specific facility shall not be entitled to perform the functions of an expert in construction activity on the same facility;

b) The builder performing the works shall not be entitled to perform the functions of a technical supervisor and expert in construction activity on the same facility;

c) If a principal specialist in construction activity has a commercial or other personal interest in the commissioned work, he/she shall be obliged to notify the customer of this interest immediately after he/she becomes aware thereof; otherwise, he/she shall be liable in accordance with legislation;

d) A principal specialist in construction activity who has commissioned work shall not be entitled to assume any other contractual obligation that is incompatible with the obligations already assumed; otherwise, he/she shall be liable in accordance with legislation.

2. A specialist working in the Agency shall not be entitled, in the event of implementation of construction planned by him/her, to prepare a decision on the issuance of a construction permit; otherwise, he/she shall be liable in accordance with legislation.

3. The conflict of interest defined by this article during the implementation of construction activity shall also apply to interdependent persons defined by Article 19 of the Tax Code of Georgia.

Chapter VExpert assessment in construction activity

Article 13. Purpose, scope and types of expert assessment in construction activity🔗

1. The purpose of expert assessment in construction activity is to assess the documents for the implementation of construction and the stages of implementation of the construction of buildings and structures in order to ensure a safe environment harmless to human health on the territory of Georgia.

2. Expert assessment in construction activity constitutes confirmation of compliance with legislation, including this Resolution and construction regulations.

3. The scope of expert assessment in construction activity includes:

a) expert assessment of draft documents for the implementation of construction;

b) expert assessment of the stages of implementation of the construction of buildings and structures;

c) expert assessment of existing buildings and structures and/or their parts.

4. Mandatory expert assessment in construction activity is of three types:

a) expert assessment of parts of draft documents for the implementation of construction;

b) expert assessment of the stages of performance of the construction of buildings and structures;

c) expert assessment of buildings and structures or their parts built without a permit or in violation of the design.

5. The Agency has the right to conduct a voluntary expert assessment at its own expense only in the event of a substantiated doubt as to the correctness of the submitted expert assessment.

Article 14. Expert in construction activity, his/her rights and obligations🔗

1. The following shall have the right to be an expert in construction activity:

a) a “Type A inspection body” accredited by the LEPL – Unified National Accreditation Body – Accreditation Centre, which ensures expert assessment of performed and/or to-be-performed construction activity. In such case, the expert assessment shall be accompanied by the accreditation certificate and documentation on the scope of accreditation;

b) bodies accredited in the member countries of the European Union and the Organisation for Economic Co-operation and Development (OECD), which register with the Accreditation Centre for the purpose of being an expert in construction activity. In such case, the expert assessment shall be accompanied by a document confirming registration with the Accreditation Centre.

2. An expert in construction activity shall be obliged to ensure that the expert assessment conducted by him/her bears an unambiguously positive or negative character. A negative assessment is a ground for refusal to issue a construction permit.

3. The expert conclusion shall include an assessment of the compliance of the architectural project with the Resolution of the Government of Georgia No. 41 of 28 January 2016 “Technical Regulation – on Approval of the Safety Rules for Buildings and Structures”, indicating at least the following parts:

a) assessment of occupancy(ies) and occupancy loads;

b) assessment of types of structures;

c) assessment of height and area;

d) assessment of exits, approaches to exits, passages and exits from the building;

e) assessment of the capacities of stairways and other means of egress;

f) assessment of accessibility;

g) assessment of requirements for external walls;

h) assessment of roof assemblies;

i) assessment of required fire-resistance-rated separations;

j) assessment of fire protection systems;

k) assessment of fixed devices of the water supply system;

l) if necessary, assessment of other requirements.

Article 15. Parts of construction documentation subject to mandatory expert assessment and the procedure for conducting their expert assessment🔗

1. The following defined by this Resolution shall be subject to mandatory expert assessment for the customer:

a) the following parts of the projects of documents for the implementation of the construction of buildings:

a.a) expert assessment of engineering-geological research;

a.b) expert assessment of bases, foundations and other main structures;

a.c) expert assessment of the technological parts of the projects of documents (if any);

a.d) compliance of the architectural parts with the regulation approved by Resolution No 41 of 28 January 2016 of the Government of Georgia "On approval of the technical regulation – rules of safety of buildings";

b) the requirements of this Article shall not apply to the buildings defined by subparagraph "n" of paragraph 2 of Article 50 of this Resolution with the following characteristics − with the coefficient of development intensity (density) determined by K-2, or in the zone where K-2 is not determined – a total area of development at the floor levels of the storeys of up to 6,000 m2, a height of up to 22 m and a deepening from the ground surface of more than 4 m on average".

2. The expert assessment shall include the method of conducting the expertise and the substantiation of the comments and of the positive assessment.

3. The Agency has the right to receive explanations and additional information from the expert and to hold consultations with him/her.

Article 16. Stages of the production of construction of buildings subject to mandatory expert assessment and the procedure for conducting their expertise🔗

1. All those stages of the production of construction of buildings (except for subparagraph "b" of paragraph 1 of Article 15 of this Resolution) defined by this Resolution that are related to the implementation of the construction of the parts of construction documentation (except for engineering-geological research) defined by subparagraph "a" of paragraph 1 of Article 15 of this Resolution shall be subject to mandatory expert assessment.

2. The Agency verifies the compliance of the implementation of each stage with the construction documentation, about which a record is made in the protocol of completion of the relevant stage and confirmed by signature.

Chapter VIParticipant of the process of issuing a construction permitAdministrative bodies

Article 17. Other administrative bodies participating in the construction permit issuance process🔗

1. In the construction permit issuance process, in accordance with this Resolution, at the first and second stages of the construction permit issuance process, the following other administrative bodies shall participate:

a) for the Gudauri recreational territory – Ministry of Regional Development and Infrastructure of Georgia;

b) in cultural heritage protection zones (except for the territory of the city of Tbilisi and immovable monuments of cultural heritage) – Ministry of Education, Science, Culture and Sport of Georgia;

c) on the territory of the Autonomous Republic of Ajara, in cultural heritage protection zones (except for immovable monuments of cultural heritage) – the Council of Cultural Heritage of the Autonomous Republic of Ajara, whose composition shall be approved in agreement with the Ministry of Education, Science, Culture and Sport of Georgia;

d) for protected areas – Ministry of Environmental Protection and Agriculture of Georgia;

e) in the coastal strip and/or coastal zones – state sub-agency institution – Roads Department of Georgia;

f) in the border strip and/or border zones – state sub-agency institution within the sphere of governance of the Ministry of Internal Affairs of Georgia – Border Police of Georgia;

g) in objects assigned to state fire supervision, in order to ensure compliance with fire safety requirements, state sub-agency institution within the sphere of governance of the Ministry of Internal Affairs of Georgia – Emergency Management Service;

h) for the construction of a tunnel (including a diversion tunnel of a hydroelectric power station) or another underground structure at a depth of not less than 25 metres from the ground surface or from the base of a building-structure (if any), as well as for such buildings-structures as are connected to the unified energy system of Georgia and/or are directly used for electricity generation, including for those energy objects whose placement is envisaged on the following rivers: Enguri, Rioni, Qvirila, Mtkvari, Khrami, Tergi, Ksani, Aragvi, Supsa, Bakhvis Tskali, Khobis Tskali, Tekhuri, Tskhenis Tskali, Dzirula, Nenskra, Kintrishi, Jejora, Kanis Tskali, Gubazeuli, Paravani, Stori, Nakra, Kheledula, Janauli, Sakaura, Chakvis Tskali, Tsablaris Tskali, Samquris Tskali, Magana and Pirikita Alazani – Ministry of Economy and Sustainable Development of Georgia;

i) local self-governing units on whose territory of operation the construction is planned, except for the construction of buildings-structures planned on the Gudauri recreational territory.

Chapter VIIGrounds for carrying out construction

Article 18. Legal basis for carrying out construction🔗

1. The legal basis for carrying out construction is:

a) a construction permit issued in accordance with this Resolution;

b) the documentation established by paragraph 2 of this Article, which unambiguously indicates the possibility of construction;

2. Before the commencement of construction, the customer (orderer) shall obtain the following documents:

a) engineering-geological survey of the construction land plot;

b) where necessary, survey of the buildings and structures and the land plot(s) in accordance with Article 20 of this Resolution;

c) performance of a mandatory expert assessment in accordance with the requirements of this Resolution;

d) construction organisation project in accordance with Article 46 of this Resolution;

e) structural design of the building/structure, a structural design consisting of a detailed design of the main structural system of the building/structure and all its other structural elements.

Article 19. Initial data for design works🔗

1. The initial data (documents/information) for design works include:

a) information confirming ownership and/or use of the land plot(s);

b) topographic map of the land plot(s) in its existing condition (scale 1:500, 1:1000);

c) description/main data of the buildings and structures existing on the land plot(s);

d) in the case of planned construction on the territory of the city of Tbilisi, as well as — description of the green plantings existing on the land plot(s) and their qualitative assessment;

e) the requirements of urban planning documents, including the development regulation plan, where the land plot(s) are located within the area of operation of urban planning documents;

f) other data (documents/information) as necessary, under the requirements of legislation and/or on the basis of a decision of the customer (orderer).

Article 20. Study of a land plot and buildings🔗

1. The study of a land plot and building shall be carried out before the preparation of documents for the construction of buildings, in some cases – during the design, construction and use of buildings (in the event of the occurrence, in the process of construction or during the use of the building, of circumstances necessary for the study).

2. The purpose of the studies is to determine the natural and physical conditions and characteristics of the land plot, the factors of impact on the environment, and to forecast their changes.

3. The necessity of carrying out studies of individual types, their composition, scope and method of conduct depend on:

a) the purpose and type of the buildings;

b) the structural features, technical complexity of the buildings and such potential hazard as may cause deformation of the building;

c) the complexity of topographic, engineering-geological, ecological and climatic conditions, the quality and accessibility of the results of existing studies on the said conditions.

4. During new construction and reconstruction of an existing building, an assessment of the impact on the existing building adjacent to which the construction is planned shall be carried out. In the event that the planned construction works may affect their stability, then a study of the stability of this building shall be carried out.

5. When carrying out construction in conditions limited by established development, the customer, the designer and the builder shall ensure the implementation of all necessary measures so as to exclude the deformation and damage, caused by them, of the structures of the buildings bordering the land plot; otherwise, the customer is obliged, upon confirmation of such a fact:

a) to correct at own expense the deformation and damage of the structures of the buildings bordering the land plot;

b) in the event that the correction of the deformation and damage of the structures of the buildings bordering the land plot is not possible, then to effect appropriate compensation on the basis of an agreement with the owner of the bordering damaged building.

6. Customers of buildings under construction in conditions limited by established development shall, during pre-design works, if necessary, conduct a proper study of the stability of the adjacent buildings in order to record their condition, and determine the degree of the possible impact of the planned construction works on the existing objects.

7. The respective person authorized for design shall, if the results of the studies give grounds for this, take into account in the construction organization project special measures that ensure the preservation of the existing condition of the adjacent buildings.

8. During the execution of construction, the principal specialists, within the scope of their own competence, shall ensure constant monitoring of adjacent buildings/structures. In the event of detection of deformations, they shall urgently notify the owner/user of the building/structure and the Agency thereof.

Chapter VIIIConstruction Permit and Stages; Publicity

Article 21. Types of construction activity for which a construction permit is issued🔗

1. The legal basis for carrying out construction is a construction permit obtained in the prescribed manner in the cases determined by legislation, including this Resolution.

2. A construction permit is issued:

a) for new construction (including installation);

b) for reconstruction of an existing building/structure;

c) for dismantling of an existing building/structure;

d) for an amendment to a construction document that requires a permit.

Article 22. General rule for issuing a permit🔗

1. A construction permit is issued in three stages, except for the cases established by Articles 23 and 24, in each of which independent administrative proceedings are conducted. Only after completion of the administrative proceedings provided for by the previous stage and issuance of a positive administrative-legal act may the permit applicant request the initiation of the administrative proceedings of the next stage. The time limits for the administrative proceedings of the said stages are:

a) Stage I – determination of urban planning conditions (hereinafter – approval of the conditions for the use of the land plot for construction) – 30 days;

b) Stage II – approval of the architectural-construction project (hereinafter – approval of the architectural project, structural and/or technological scheme) – 20 days;

c) Stage III – issuance of a construction permit – 10 days.

2. All three stages of the administrative proceedings related to the permit shall be conducted by the Agency, which issues the following types of administrative-legal acts:

a) Stage I – an administrative-legal act on approval of the conditions for the use of the land plot for construction;

b) Stage II – an administrative-legal act on approval of the architectural project, structural and/or technological scheme;

c) Stage III – an administrative-legal act on issuance of a construction permit.

3. The administrative-legal acts related to the stages of permit issuance shall comply with the requirements established for an administrative act by Chapter IV of the General Administrative Code of Georgia.

Article 23. Issuance of a construction permit on the basis of a development regulation plan🔗

1. In those territories where a development regulation plan exists, for the issuance of a construction permit, the passing of the first stage determined by this Resolution (approval of the conditions for the use of the land plot for construction) is not required, and the conditions for the use of the land plot for construction shall be constituted by the respective development regulation plan. The exception is the case determined by paragraph 2 of this Article.

2. If not all those conditions are determined by the development regulation plan that are determined by this Resolution for the first stage of issuance of a construction permit for the approval of the conditions for the use of the land plot for construction, then it is also necessary to conduct the administrative proceedings established by the first stage procedure, in order to determine those conditions that are not determined by the respective development regulation plan.

Article 24. Issuance of a construction permit under the simplified procedure🔗

1. The client is entitled, in order to obtain a construction permit, unlike the general procedure for issuing a construction permit, to choose a two-stage administrative proceeding. The time limits for the administrative proceedings of the said stages are:

a) Stage I – approval of the conditions for the use of the land plot for construction – 15 days;

b) Stage II – issuance of the construction permit – 20 days (at this stage, the construction document draft must include the projects/schemes required for Stage II as determined in accordance with this Resolution).

2. The client or his/her representative is entitled to submit to the Agency all documents required for obtaining a construction permit together. In this case, the Agency conducts the administrative procedures of the stages defined by paragraph 1 of this Article and issues the relevant administrative-legal acts.

3. For buildings and structures of particular importance and/or significant for the country from a social and/or economic point of view, or their complexes, the construction of which has already been completed and which lack the relevant legal basis (proper documents and documentation for the full implementation of construction), a construction permit shall be issued only on the basis of the relevant decision of the Government of Georgia, upon the petition of the relevant state agency determining state policy in the field, under the simplified procedure, only by Stages II and III (or their combined administrative proceeding). In such a case:

a) The owner of the facility shall submit, with proper justification, an application to the relevant authorized state body determining state policy in the field, attaching the existing design and other documentation, in order to initiate a petition to the Government of Georgia for the commencement of the procedure for issuing a construction permit, with the aim of issuing the relevant ordinance of the Government of Georgia;

b) The owner of the facility shall be obliged to ensure the publicity of the said procedure, in particular, in compliance with the requirements of this Resolution, to post an information board at the construction site regarding the submission of an application to the Agency for obtaining a construction permit;

c) The government institution determining policy in the field, in agreement with the Ministry of Economy and Sustainable Development of Georgia, assigns the applicant (owner) a task to examine the condition of the facility;

d) In accordance with the task, the owner of the facility shall, at his/her own expense, ensure the performance of the examination works of the facility and submit the results of the examination to the relevant authorized state body;

e) The administrative body shall, within 10 days from the submission of the examination results, but not less than 20 days from the receipt of the application, consider the matter and adopt a decision on submitting a petition to the Government of Georgia, taking into account the obtained examination results;

f) The administrative proceeding related to the issuance of a construction permit shall be carried out within the time limits established by legislation.

4. If the construction of the object is related to a large volume of design documentation to be elaborated and to large-scale works to be performed within tight deadlines, and also the clarification and agreement of the circumstances required for designing and/or of individual parts of the design documentation is complicated, as a result of which the permit applicant is unable to submit complete documentation, the Agency is entitled, on the basis of a substantiated petition of the permit applicant, to issue a construction permit subject to the conditions and deadlines for the documentation to be submitted. Documentation submitted under the conditions established by the Agency and within the determined deadline shall be an integral part of the design documentation and shall be added thereto.

5. A construction permit for buildings and structures of representations and embassies of foreign countries shall be issued in accordance with the administrative proceedings procedures established by Stages I and II. After the procedures established by Stage II have been completed and the relevant administrative-legal act has been issued, the construction permit certificate shall be issued.

6. In the case provided for by paragraph 5 of this Article, the draft construction document shall include only: facades, unfolded views, the site layout plan, the schematic plan of buildings and the document confirming payment of the construction permit fee.

Article 25. Ensuring publicity of the issuance of construction permits and compliance with permit conditions within the boundaries of built-up territories🔗

1. During planned construction within the boundaries of built-up territories, the permit applicant, by the time of submitting an application on establishing the conditions for the construction use of the land plot, shall ensure the placement of an information board in a visible place on the relevant object (building/structure), which shall indicate the data of the expected construction, namely:

a) address of the building/structure;

b) functional purpose of the building/structure;

c) the body issuing the construction permit and the time limits for reviewing the application;

d) the estimated number of storeys and/or dimensions of the building/structure.

2. The permit applicant shall, within three days from the submission of the application on the issuance of a construction permit, place on the existing board the information reflected in the conditions for the use of the land plot approved for construction, namely:

a) functional purpose of the building/structure;

b) number and date of the administrative-legal act by which the conditions for the construction use of the land plot were established, if such exists;

c) number of storeys and/or dimensions of the building/structure.

3. The permit holder shall, within ten days after the issuance of the permit in accordance with the established procedure, place on the existing board information reflecting the main aspects and parameters of the construction implementation documents, namely:

a) functional purpose of the building/structure;

b) the body issuing the construction permit, the permit number and its validity period;

c) the time limits for the commencement and completion of construction;

d) number of storeys and/or dimensions of the building;

e) at the customer's (orderer's) request, the architectural appearance of the object.

4. In the case where the construction permit applicant receives a construction permit in three stages in accordance with this Resolution, he/she shall additionally place on the information board information related to the submission of an application on the approval of the architectural project and to the approval of the architectural project.

5. Any change made to the construction document that changes the essence of the information placed on the information board shall be placed on the information board.

6. The dimensions of the information board and the conditions for placing information on it may be specified by the Agency, for the purpose of ensuring publicity and visibility, according to the multiplicity of the minimum dimensions. The minimum dimensions of the information board are A2 size format.

7. By decision of the Agency, the information board may include only mandatory data:

a) address and function of the building/structure;

b) identity and contact information of the customer (orderer);

c) name of the Agency, address and, if available, website address where information on the construction of the object can be reviewed.

8. The information board shall exist throughout the entire period of performance of construction works and shall be removed after the completion of the construction of the building/structure and/or its commissioning.

9. Only the information defined by this Article shall be placed on the information board, and its use for advertising purposes shall be prohibited.

Article 26. Ensuring publicity of the issuance of construction permits outside the boundaries of built-up areas and of the fulfillment of permit conditions🔗

1. In the case of planned construction outside the boundaries of built-up areas, an information board shall be placed near the administrative building of the self-governing unit(s) in whose area of operation the planned construction is located, at a place specially allocated for this purpose.

2. In the case of planned construction outside the boundaries of built-up areas, publicity shall be ensured in accordance with the requirements defined by Article 25 of this Resolution, with the addition of an indication of the location.

Chapter IXApproval of the conditions for the use of a land plot for construction

Article 27. Conditions for the use of a land plot for construction🔗

1. The conditions for the use of a land plot for construction shall reflect the mandatory requirements defined by legislation, including by this Resolution, that are necessary for the development of draft documents for the implementation of construction.

2. It shall be prohibited to include in the conditions for the use of a land plot for construction requirements that are not established by legislation.

3. The conditions for the use of a land plot for construction shall not include a requirement that the customer (orderer) repair or reconstruct existing main engineering-utility networks, as well as existing transport lines, if the intended construction does not cause the necessity of their expansion and/or damage.

4. The participants in the drafting and approval of the conditions for the use of a land plot for construction shall be responsible for the compliance of the documents prepared by them with legislation.

Article 28. Composition of an application on the conditions for the use of a land plot for construction🔗

1. An application on the conditions for the use of a land plot for construction, in accordance with this Resolution, in the process of issuing a construction permit, constitutes the conditions necessary for the first stage of issuing the construction permit and required by the permit applicant.

2. The requirements defined by this Article apply to the composition of the application on the use of a land plot for construction to be submitted to the Agency.

3. An application on the conditions for the use of a land plot for construction includes:

a) information about the land plot;

b) the main requirements of the permit applicant regarding the construction of buildings and structures on the land plot.

4. Information about the land plot:

a) location of the land plot within the administrative boundaries of the territory of settlements;

b) information on the registration of the land plot;

c) if necessary, general characteristics of the soils of the land plot and its adjacent territory;

d) the type of land plot according to its use possibilities in accordance with this Resolution;

e) indication of the location of the land plot in a general and/or specific functional zone (if any);

f) indication of the location of the land plot in a territorial-structural zone (if any);

g) indication of the location of the land plot in a cultural heritage and/or environmental protection zone (if any);

h) in the event of reasonable suspicion, information on the ecological condition of the land plot;

i) improvement of the land plot or part thereof (e.g.: fencing, children's playgrounds, landscaping);

j) on the territory of the city of Tbilisi, as well as information on planned landscaping, with a description of the proposed landscaping project;

k) if necessary, engineering-geological preparation of the territory (e.g.: change of the ground surface, diversion/removal of surface and/or ground water, protective structures);

l) the number of parking spaces for motor vehicles;

m) during the reconstruction of buildings and structures, if necessary, the documents for the implementation of the existing construction or, in the absence thereof, a measurement project, as well as an expert opinion on the condition of the building/structure;

n) if necessary, other information established by legislation.

5. The main requirements of the permit applicant regarding the construction of buildings and structures on the land plot include:

a) the development coefficient of the land plot;

b) the development intensity coefficient of the land plot;

c) the landscaping coefficient of the land plot;

d) the functional purpose of the buildings and structures;

f) the number of storeys and dimensions of the buildings and structures;

g) the arrangement of the construction site in the case of use of public space/territory;

h) if necessary, other data in accordance with this Resolution.

6. In the event that a specific land plot falls within the area of operation of the spatial arrangement and/or urban planning documents of the territories, the application on the conditions for use of the land plot for construction purposes shall be based on such spatial arrangement and/or urban planning documents.

7. In the event that a specific land plot does not fall within the boundaries of the documents of specific legal zoning of land use of settlement territories, the draft of the conditions for use of the land plot for construction purposes shall be based on the requirements of the Resolution of the Government of Georgia on approval of the main provisions for regulation of use and development of territories.

8. The application on the conditions for use of a land plot for construction purposes shall indicate the number of pages and shall be signed/certified by the persons authorised to draw it up.

9. The Agency verifies the compliance of the application on the conditions for use of a land plot for construction purposes with the legislation and, on the basis of the conditions determined by the legislation, upon completion of the administrative proceedings of Stage I of issuance of the construction permit and issuance of the relevant administrative-legal act, approves the conditions for use of the land plot for construction purposes.

Article 29. Application for approval of the conditions for use of a land plot for construction purposes🔗

1. At Stage I of issuance of the construction permit, the customer (orderer) or a person authorised by him/her shall submit to the Agency an application drawn up on the basis of the legislation, including this Resolution, for approval of the conditions for use of the land plot for construction purposes.

2. The types of application on the conditions for use of a land plot for construction purposes are:

a) application for new construction;

b) application for reconstruction;

c) application for a project to be used a second time.

3. The form of the application on the conditions for use of a land plot for construction purposes and of the conditions for use of a land plot for construction purposes shall be established by the Agency in compliance with the requirements of this Resolution.

Article 30. Rule for approving the conditions for the use of a land plot for construction purposes🔗

1. The decision on approving the conditions for the use of a land plot for construction purposes shall be taken by the Agency in accordance with the simple administrative procedure established by Chapter VI of the General Administrative Code of Georgia.

2. The customer or a person authorised by him/her shall submit to the Agency an application which must meet the requirements provided for by Article 78 of the General Administrative Code of Georgia.

3. The following shall be attached to the application:

a) a topographic plan of the land plot as it currently stands (scale 1:500 or 1:1000);

b) copies of the documents established by legislation confirming the identity of the applicant;

c) in the case of submission of the application by a representative – the relevant power of attorney;

d) a situational plan of the land plot with appropriate detailing (location according to city streets and, where necessary, aerial photography);

e) in cases established by legislation – the results of a study of the cultural heritage protection zone;

f) in cases established by legislation – the results of an archaeological study (except for buildings defined by subparagraph „n“ of paragraph 2 of Article 50 of this Resolution, with the following characteristics − determined by the building intensity (density) coefficient K-2, or, in a zone where K-2 is not determined – a total building area of up to 6 000 m² at the floor levels of the storeys, a height of up to 22 m and a deepening of more than 4 m on average from the ground surface);

g) a photograph confirming the placement of an information board in a conspicuous place;

h) a plan of the cadastral boundaries of the land plot (if construction is planned in residential, public-business or resort-recreational zones, together with the plan of the cadastral boundaries of the land plot, the boundaries of the plots/spaces adjacent to the neighbourhood and public boundary of the land plot shall be submitted (a map of the cadastral boundaries). Those points of the boundaries of the construction land plot at which corners are formed shall be marked with a point, indicating its coordinates and absolute elevation, and in the case of the objects specified in paragraph 6 of Article 38 of this Resolution, the coordinates of the land plot(s) required for construction purposes;

i) photographic material reflecting the condition of the land plot;

j) an application on the conditions for the use of the land plot for construction purposes, drawn up in compliance with the requirements of Article 28 of this Resolution;

k) during the transitional period, when specific land plot(s) do not fall within the boundaries of the documents of specific legal zoning of land use of the territories of settlements, then, in addition, for the land plot(s), it is necessary to determine, during the transitional period of the implementation of the specific legal zoning of land use, the conditions for the use and development of individual land plot(s) (in accordance with the main provisions of the regulation of the use and development of the territories of settlements as drawn up).

4. An application submitted for the purpose of approving the conditions for the use of a land plot for construction within the territory of the city of Tbilisi shall, together with the documents provided for by paragraph 3 of this Article, also be accompanied by an expert opinion on the inventory of the green plantings existing on the land plot and their qualitative assessment.

5. The Agency shall, within 3 days, verify the compliance of the application and the attached documents submitted by the customer or his/her authorised person with the requirements defined by this Resolution.

6. The Agency shall be obliged to submit the application and copies of the attached documents to another administrative body no later than 3 days after establishing the compliance of the application with the defined requirements.

7. Another administrative body shall be obliged to adopt a decision on the confirmation of the legally defined factual circumstances no later than 20 days after the submission of the application to the Agency. If the said period is not sufficient for establishing the factual circumstances, another administrative body shall be entitled, no later than 5 days after receipt of the application and copies of the attached documents, to request an extension of the period by a reasoned motion. In the event of adopting a decision, another administrative body shall be obliged to submit the decision to the Agency no later than the 24th day after the submission of the application to the Agency. In the event of failure by another administrative body to submit a decision within the established period, the application shall be deemed agreed with the other administrative body.

8. The Agency shall be obliged to adopt a decision on the approval of the conditions for the use of the land plot for construction or on refusal of approval within the period defined by this Resolution. In the event of refusal, the Agency shall be obliged to immediately notify the customer or the person authorised by him/her in writing of the reasoned refusal.

9. If, in order to establish circumstances of substantial importance for the case, more than the period defined by this Resolution for administrative proceedings is necessary, the Agency shall be entitled, on its own initiative or on the basis of a motion of another administrative body, to adopt a reasoned decision on the extension of the period of administrative proceedings to not more than 3 months. The Agency shall be obliged to adopt the said decision within 15 days after the submission of the application“.

10. If no decision has been adopted within the period established by legislation, the conditions requested by the application shall be deemed approved, taking into account the norms established by legislation for the relevant object.

11. If the applicant for a permit has not, within 5 years from the approval of the conditions for the use of the land plot for construction purposes, continued the relevant administrative proceedings for the purpose of obtaining a construction permit, and during this period there has occurred such a change in the legislation related to spatial-territorial arrangement and/or in the essential characteristics of urban planning conditions (development regulation coefficients, permissible types of buildings, their heights, etc.) as results in a change of the conditions for the use of the land plot for construction purposes, the conditions for the use of the land plot for construction purposes shall be declared invalid by a decision of the body with the relevant authority, and its owner shall be offered to make the appropriate changes.

12. In the event of a change of the conditions for the use of the land plot for construction purposes, the Agency shall be entitled, in accordance with the procedure established by law, to make changes to the administrative-legal act on the approval of the conditions for the use of the land plot for construction purposes.

Chapter XRule for the agreement of an architectural project, structural and/or technological scheme

Article 31. Architectural project, structural and technological scheme🔗

1. The second stage of the issuance of a construction permit, in accordance with this Resolution, is the agreement of the architectural project, structural and/or technological scheme. For the agreement of the architectural-construction project, the applicant for a permit shall submit the architectural project and/or, if necessary, the structural scheme and/or the technological scheme.

2. In the cases determined by the Resolution, as well as at the request of the Agency, the applicant for a permit shall, at the second stage of the issuance of a construction permit, submit the structural scheme and/or the technological scheme for agreement.

Article 32. Composition of the Architectural Project🔗

1. The composition of the architectural project of a building/structure includes:

a) information on the construction permit object, which includes:

a.a) title page, name and address of the object;

a.b) list of pages;

a.c) used conventional designations;

a.d) explanatory note, which includes a description of the planning objectives:

a.d.a) basis and objectives of planning;

a.d.b) written description of the land plot;

a.d.c) substantive description of the project;

a.d.d) description of the main structural system of the building/structure;

a.d.e) description of the legislation used for planning;

a.e) technical indicators of the building/structure:

a.e.a) area of the land plot;

a.e.b) value of the applied K1 and the built-up area;

a.e.c) value of the applied K2 and the built-up density area, showing the built-up area of each floor;

a.e.d) value of the applied K3 and the landscaping area;

a.e.e) area of the building/structure, including, if present: area of the residential house; area(s) of the apartment(s); office area; area(s) of trade and household services; production area; warehouse area; areas of the stairwell and entrances; summer areas (balconies, terraces, verandas and loggias);

b) analysis of compliance of buildings/structures with the "Building/Structure Safety Rules":

b.a) occupancies and description of each use;

b.b) construction type(s);

b.c) height restrictions;

b.d) area restrictions;

b.e) requirements for external wall openings;

b.f) requirements for exits;

b.g) requirements for fire protection systems;

b.h) requirements for fixed fixtures of the water supply system;

b.i) if necessary, other requirements

c) situational plan − scale 1:2000 or 1:1000;

d) photographic material reflecting the existing situation (with distant and close views, indicating the date);

e) land plot plan (indicating coordinates) − scale 1:500 or 1:250:

e.a) land plot plan plotted on the topographic plan of the land plot;

e.b) placement and heights of buildings/structures;

e.c) access and internal vehicular roads to the land plot, parking lots, pedestrian paths, bicycle paths, landscaping, improvement and other;

e.d) if necessary, a scheme for the placement of household waste containers;

e.e) in the event of a change in the land surface, a plan for the change of the land surface;

e.f) scheme for the removal of surface waters;

f) floor plans at all levels and roof plan − scale 1:200, 1:100 and/or 1:50:

f.a) plan of all floors and roof of the building, showing the projection of the cadastral boundary, the elevations of the floor surfaces, the zero elevation of the building/structure in relation to the absolute zero elevation;

f.b) floor plans of the building shall provide information on the main dimensions of the floor, the areas of the room and/or space and their main dimensions, as well as the main dimensions of the means of exit;

f.c) Layout plans for furniture and/or other equipment − in accordance with Resolution No. 41 of 28 January 2016 of the Government of Georgia "On Approval of the Technical Regulation − Building Safety Rules";

g) Cross and/or longitudinal section(s) of the building − at 1:200, 1:100 and/or 1:50:

g.a) the sections of the building shall include, at a minimum, the floor surface elevations and the zero elevation of the building relative to the absolute zero elevation;

g.b) materials used at the discretion of the permit applicant;

g.c) significant parts and/or details at the discretion of the permit applicant − at 1:20, 1:10 and/or 1:5;

h) all facades of the building − at 1:200, 1:100 and/or 1:50:

h.a) materials and colours used on the facade;

h.b) in the case of the existence of adjacent buildings, elevations − at 1:500 and/or 1:200;

h.c) significant parts and/or details of the facade − at 1:20, 1:10 and/or 1:5;

i) plans of occupancies and means of egress for buildings − at 1:200 and/or 1:100:

i.a) occupancy loads;

i.b) capacities of stairways and other means of egress;

i.c) exits, approaches to exits, passages and exits from the building;

i.d) maximum travel distances to an exit;

i.e) accessibility route;

i.f) where necessary, refuge areas;

i.g) where necessary, other requirements;

j) compliance of stairways, ramps, railings and handrails of buildings with the building safety rules in the form of drawings − at 1:50 and/or 1:20;

k) fire protection plans for buildings − at 1:200k.a) required fire-resistance-rated separations;

k.a) fire protection systems used;

k.b) where necessary, other requirements;

l) facades of buildings in zones of special construction regulation and historical protection zones, on which their main overall dimensions, heights, including heights by floors, shall be indicated, showing the levels of intersection with the ground relative to the absolute zero elevation, indicating the dimensions of all openings and architectural details placed on the facade, drawings of facades (accountable surfaces), showing schematic drawings of facades (accountable surfaces) of buildings existing on adjacent land plots (e.g.: street elevation); photo montage and axonometric views defining architectural details, facing and construction materials and colours (both in printed and digital form, with detailed indication of all types of facing materials used on facades, windows, stained-glass windows, railings or other architectural elements (including indication of the location of heating and air-conditioning technical means), as well as the colour of the paints used according to RGB or RAL codes;

m) where necessary, a model and/or three-dimensional view(s) and/or photo montage;

n) on the territory of the city of Tbilisi, as well as − the land plot greening project, which, together with other data, must necessarily include the following information:

n.a) the area of coefficient K-3;

n.b) the species of green plantings to be planted (including characteristics − age, height);

n.c) the completion date of the greening project;

n.d) the person responsible for the care and maintenance of the planted green plantings;

n.e) the duration of the care of the planted green plantings;

o) on the territory of the city of Tbilisi, the road traffic organisation scheme, with the transport/road infrastructure of the project territory applied, showing the connection with the study area.

p) additional material, at the discretion of the permit seeker.

2. The parts of the architectural project defined by paragraph 1 of this Article may be submitted in combined form.

3. In the case of submission in printed form − the architectural project shall be submitted folded in A-4 format, bound in a binder/quick binder.

Article 33. Composition of the structural scheme🔗

1. In the case of construction of buildings (including linear buildings), the structural scheme includes:

a) an explanatory card;

b) the land plot plan (where the placement of buildings on the land plot(s) is shown in physical context);

c) the plan of the change of the ground surface of the territory required for the building(s) (if any);

d) determination of the zero elevation and its relation to the absolute zero elevation;

e) schematic drawings of views/facades;

f) characteristic sections of the building(s);

g) if any, the plan of all floors of the building.

2. By decision of the customer, the structural scheme may additionally include:

a) photographs of the territory;

b) digital visualisation and/or a model.

3. The parts of the structural scheme defined by paragraph 1 of this Article may be submitted in combined form, folded in A-4 format, bound in a binder/quick binder.

Article 34. Composition of the technological scheme🔗

1. The composition of the technological scheme includes:

a) an explanatory card;

b) the land plot plan (where the placement of buildings and structures on the land plot is shown in physical context);

c) the plan of the change of the ground surface of the territory required for the building(s) (if any);

d) determination of the zero elevation and its relation to the absolute zero elevation;

e) schematic drawings of facades (accountable surfaces);

f) characteristic sections of the building(s);

g) the technological scheme of the relevant production process(es);

h) if any, the plan of all floors of the building.

2. By decision of the customer, the technological scheme may additionally include:

a) photographs of the territory;

b) digital visualisation and/or a model.

3. The parts of the technological scheme defined by paragraph 1 of this Article may be submitted folded in A-4 format, bound in a binder/quick binder.

Article 35. Approval of an architectural project, structural and/or technological scheme🔗

1. Approval of an architectural project, structural and/or technological scheme is mandatory:

a) of an architectural project – in cultural heritage protection zones;

b) of a structural and/or technological scheme – in the process of issuing a construction permit, in the case of a request by another administrative body determined by this Resolution, in compliance with the requirements of Article 17 of the Resolution.

Article 36. Application on approval of an architectural project, structural and/or technological scheme🔗

1. The customer shall submit to the Agency an application for approval of an architectural project, structural and/or technological scheme, which must meet the requirements provided for by Article 78 of the General Administrative Code of Georgia.

2. The application shall be accompanied by:

a) an administrative legal act on approval of the conditions for use of the land plot for construction;

b) at least three and at most six copies of the architectural project, structural and/or technological scheme;

c) an environmental decision − if obtaining a construction permit is related to the construction of a facility in which the envisaged activity, in accordance with the Environmental Assessment Code, is subject to environmental impact assessment;

d) in the case of buildings and structures, an expert assessment on compliance with the regulation approved by Resolution No. 41 of 28 January 2016 of the Government of Georgia "Technical Regulation of Architectural Projects – on Approval of Safety Rules for Buildings and Structures".

Article 37. Rule for approval of an architectural project, structural and/or technological scheme🔗

1. The permit applicant shall submit a written application and the attached documents to the Agency. The Agency shall adopt a decision on approval of the architectural project, structural and/or technological scheme in accordance with the procedure established by the Law of Georgia “On Licences and Permits”.

2. The Agency, an administrative body, shall verify the compliance of the application and the attached documents with the requirements of this Resolution and the applicable legislation within 3 days. In the event of a defect, the Agency shall act in accordance with the procedure defined by Article 83 of the General Administrative Code of Georgia.

3. Another administrative body shall, within the scope of its competence, examine the compliance of the architectural project, structural and/or technological scheme with the parameters defined by the conditions of use of the land plot designated for construction and shall adopt a decision on approval of the architectural project, structural and/or technological scheme or on refusal of approval. The said decision shall be adopted by the other administrative body no later than 15 days after the submission of the application to the permit-issuing body. In the event of adoption of a decision, the other administrative body shall submit the decision to the permit issuer no later than 17 days after the submission of the application to the Agency. If the other administrative body fails to submit the decision within the established period, the architectural project, structural and/or technological scheme shall be deemed approved with the other administrative body.

4. The Agency shall, within the period defined by this Resolution, adopt a decision on approval of the architectural project, structural and/or technological scheme or on refusal of approval. In the event of refusal of approval, the Agency shall immediately notify the permit applicant in writing of the substantiated refusal

5. If no decision is adopted within the established period, the architectural project, structural and/or technological scheme shall be deemed approved. The permit applicant shall ensure compliance with the conditions of use of the land plot designated for construction in relation to the given facility.

6. If, according to the approved architectural project, structural and/or technological scheme, no construction permit is issued within ten years, or/and during this time there occurs such a change in the essential characteristics of the legislation related to spatial-territorial arrangement and/or of the conditions of use of the land plot designated for construction (e.g.: development regulation coefficients, maximum permissible heights of buildings, etc.) as results in a change of urban planning conditions, the decision on approval of the architectural project, structural and/or technological scheme shall be deemed invalid.

Chapter XIRule for issuing a construction permit

Article 38. Documents Required for Obtaining a Construction Permit🔗

1. To obtain a construction permit, the customer (orderer) shall submit to the Agency an application, which must meet the requirements provided for by Article 78 of the General Administrative Code of Georgia and contain information on the registration of the land plot.

2. The following shall be attached to the application:

a) information on the land plot and/or building/structure (linear structure);

b) information on the approval of the conditions for use of the land plot for construction, indicating the details of the act;

c) if any, the details of the administrative-legal act on the approval of the architectural project, structural and/or technological scheme;

d) a document confirming payment of the permit fee;

e) the address of the location of the object and the cadastral code;

f) the functional purpose and intended use of the building/structure;

g) the data of the designer of the building/structure: name/legal name, contact information (telephone number and email address), registration data of the Registry of Entrepreneurs and Non-Entrepreneurial (Non-Commercial) Legal Entities, as well as the number of the identity document and personal number;

h) in the case of construction of a temporary building/structure – the requested period of use;

i) the documentation provided for by this Resolution

3. In the case where approval of the facade part of the architectural project is necessary, on the basis of a reasoned application of the applicant for a construction permit, the Agency shall be entitled to issue a construction permit without an approved project for the building facades and to determine, by the permit conditions, the conditions and deadlines for submission of the latter, provided that the facade projects must be submitted before completion of the zero stage of the building.

4. If the construction of objects is associated with a large volume of documents to be processed for the implementation of construction and large-scale works to be performed within tight deadlines, as well as the circumstances necessary for design are specified during the design process, also, if the objects are buildings/structures of special state importance and social purpose or their complexes, due to which it is impossible to submit, by the final stage, a fully completed construction document project complying with the requirements established by legislation, in the case of a properly reasoned application of the permit applicant and by decision of the Agency, a construction permit may be issued for the land plot and/or plots without submitting to the Agency some of the documents confirming ownership or use and the construction document project. In such a case, the deadline for submission of these documents shall be determined in the permit conditions. The permit holder may commence the relevant construction works on the land plot or plots for which he/she submits the document confirming ownership or use and the relevant design documentation.

5. In the case of the construction of a tunnel (including a diversion tunnel of a hydroelectric power plant) or another underground structure at a depth of not less than 25 metres from the ground surface or from the base of a building or structure (if any) (except for construction by the open-cut method), the permit shall be issued without a document confirming ownership/use of the land plot(s).

6. In the case of the construction of a linear structure and/or infrastructure facilities necessary for its operation, a power plant and/or a substation, where the state body determining state policy in the relevant field considers it an object of state importance, a conditional construction permit may be issued, upon application by the permit applicant, if the coordinates of the territory (land plot(s)) to be used for construction purposes are submitted to the Agency in the UTM coordinate system and electronic versions of the files in (*.shp) format, in which case the permit conditions shall determine the time limit for submitting documents confirming ownership or use of the land plot(s). The permit holder may commence the relevant construction works on the land plot or plots for which it submits a document confirming ownership or use.

7. The customer (orderer) shall submit to the Agency a minimum of three and a maximum of six copies of the construction documents and, in addition, one digital copy.

Article 39. Rule for issuing a construction permit🔗

1. The issuance of a construction permit shall be carried out by the simple administrative procedure established by Chapter VI of the General Administrative Code of Georgia and in accordance with the procedure established by the Law of Georgia “On Licences and Permits”.

2. The Agency shall, within 3 days, verify the compliance of the application submitted by the applicant for the permit and the attached documents with the requirements defined by this Resolution. In the event of a defect, the Agency shall act in accordance with the procedure defined by Article 83 of the General Administrative Code of Georgia.

3. The Agency shall be obliged to adopt a decision on the issuance of the permit or on refusal to issue it within the period defined by this Resolution. In the event of refusal, the Agency shall be obliged to immediately notify the applicant for the construction permit in writing of the reasoned refusal.

4. If, in order to establish circumstances of essential importance to the case, more than the period defined for administrative proceedings is necessary, the Agency is entitled to adopt a reasoned decision on the extension of the administrative proceedings period by not more than 3 months. The Agency shall be obliged to adopt the said decision within 7 days of the submission of the application.

5. The Agency, on the basis of a negative expert opinion on an object subject to mandatory expert opinion, shall be obliged to adopt a decision on refusal to issue the permit.

6. In the process of issuing a permit for an object subject to mandatory expert opinion, the Agency, in the event of reasonable doubt, has the right to subject the project to expert assessment again. If the repeated expert opinion is also positive, as is the expert opinion carried out by the customer, then the fee for conducting the expert assessment shall be paid by the Agency, otherwise – by the customer. In the event of an incorrect expert opinion, the issue of the expert's liability shall be raised in accordance with the contract and legislation.

7. If no decision on the issuance of a construction permit was adopted within the period established by legislation, the construction permit shall be considered issued. In this case, the applicant for the construction permit is entitled, after the expiry of the period established for the issuance of the permit, to request the permit certificate. The Agency shall be obliged to immediately issue the permit certificate.

8. If the construction permit has expired without the construction having been carried out and during this time there has occurred such a change in the legislation related to spatial-territorial arrangement and/or in the essential characteristics of the conditions of use of the land plot for construction (e.g.: building regulation coefficients, maximum permissible heights of buildings, etc.) as causes a change of the urban planning conditions, the architectural project, the structural and/or technological scheme, in such case, the conditions of use of the land plot for construction and the approval of the architectural project, the structural and/or technological scheme shall be declared invalid.

9. The administrative-legal act on the issuance of a construction permit and the permit certificate issued on its basis shall set out those stages of construction the completion of which requires the drawing up of an appropriate record.

Article 40. Obligations of the Agency upon issuance of a construction permit🔗

1. The Agency shall, immediately upon adoption of a positive decision on the issuance of a construction permit, and in the event of the time limit of the administrative proceedings being missed – immediately upon the request of the permit applicant, in the manner established by the Law of Georgia on Licences and Permits:

a) hand over to the permit applicant the construction permit certificate and at least three copies of the certified construction document, and, at the request of the customer, a maximum of six copies;

b) retain 2 certified control copies for the performance of archival and supervisory functions;

c) retain the digital copy, if any, for the archive.

Article 41. Term of validity of a construction permit🔗

1. A construction permit shall be issued for a reasonable term specified in the construction implementation documents.

2. The term of the construction permit shall begin to run on the day of commencement of the construction works provided for by the construction organisation project.

Article 42. Extension of the validity period of a construction permit; construction permit🔗

1. Extension of the validity period of a construction permit is possible if no such construction works have been carried out on the construction site which, in accordance with this Resolution, require a construction permit.

2. For extension of the validity period of a construction permit, the customer (orderer) or his/her representative shall, before expiry of the validity period of the construction permit, apply in writing to the Agency regarding extension of the validity period of the construction permit; the application shall be accompanied by the construction organisation project for the remaining works and the reasonable period requested for completion of the construction.

3. When extending the validity period of the construction permit, the Agency, in accordance with the requirements of Article 63 of the General Administrative Code of Georgia, adopts a decision on the issuance of the construction permit, in the administrative-legal act, on changing the date of completion of the construction, for which purpose amendments are made to the permit certificate.

4. If the customer (orderer) or his/her representative applies to the Agency with an application after expiry of the validity period of the construction permit, extension of the validity period of the construction permit is inadmissible. In such a case, obtaining a new construction permit is required.

5. The customer (orderer) or his/her representative is obliged to attach to the application provided for by paragraph 4 of this Article the construction organisation project for the remaining works, the reasonable period requested for completion of the construction and a new receipt of the fee paid for obtaining the construction permit.

6. In the cases provided for by this Article, the Agency issues the construction permit in accordance with the General Administrative Code of Georgia and in the manner determined by this Resolution.

7. In the case of violation of the construction document, the construction permit is issued in accordance with Article 48 of the Resolution.

Article 43. Information to be entered in the permit certificate🔗

The following information shall be entered in the permit certificate:

a) the address of the location of the building-structure and/or, in the case of absence or incompleteness of the address, a description of the location specified as far as possible;

b) registration data of the land plot, cadastral code;

c) date of issuance of the construction permit;

d) number of the construction permit;

e) validity period of the construction permit;

f) date of commencement of the running of the term of the construction permit;

g) functional designation and purpose of use of the building-structure;

h) stages of implementation (supervision) of the construction process;

i) identification data of the holder of the permit;

j) permit conditions;

k) position and signature of the person issuing the construction permit.

Article 44. Making amendments to an administrative-legal act on the issuance of a construction permit🔗

1. In the event of a change in the information determined by Article 43 of this Resolution, the Agency is entitled to make amendments to the administrative-legal act on the issuance of a construction permit. Amendments to the administrative-legal act shall be made in accordance with the procedure established by the General Administrative Code of Georgia.

2. On the basis of paragraph 4 of Article 24 and paragraphs 4 and 6 of Article 38 of this Resolution, if, within the time limits determined by the administrative-legal act on the construction permit, the respective documentation is not submitted to the Agency, the Agency is entitled to make an amendment to the respective administrative-legal act on the extension of the time limit for the submission of the said documentation. The said time limit may be extended only if the holder of the construction permit or his/her authorised representative applies to the Agency for the extension of the said time limit before the expiry of the said time limit, not earlier than the period required by the General Administrative Code of Georgia for the issuance of the respective administrative-legal act.

Chapter XIIConstruction document project; construction document and construction organisation project

Article 45. Draft construction document; construction document🔗

1. A draft construction document is documents/projects developed and/or approved in accordance with the requirements of this Resolution, which contain textual and graphic information and, in accordance with this Resolution, constitute the basis for issuing a construction permit.

2. A draft construction document shall be prepared on the basis of the conditions for the use of the land plot(s) for construction and/or the relevant development regulation plan, the agreed architectural project, the structural and/or technological scheme and/or, in accordance with this Resolution, where necessary, other information/documents.

3. In the cases defined by Articles 23 and 24 of this Resolution, a draft construction document shall be prepared on the basis of the conditions for the use of the land plot(s) for construction or the agreed architectural project, the structural and/or technological scheme and, in accordance with this Resolution, where necessary, other information/documents.

4. The number of sheets shall be indicated in the draft construction document, and each sheet shall be certified in such a way as to enable identification of the main persons implementing the relevant construction activity and, among them, the responsible specialists.

5. The constituent parts of the draft construction document may be presented in a combined form (combined in one format or distributed across different formats).

6. By decision of the customer, the draft construction document may additionally include:

a) photographs of the territory;

b) digital visualisation and/or a model.

7. A construction document is the set of the draft construction document signed/certified by the appropriate person(s) and the construction permit issued on its basis.

Article 46. Construction organisation project🔗

1. The construction organisation project is a document mandatory for the construction works producer to perform. The „e“ subparagraph of the construction organisation project defined by paragraph 2 of this Article is an integral part of the construction document project.

2. The construction organisation project shall reflect in detail the conditions for carrying out the construction, including:

a) the day of commencement of the construction works;

b) the construction stages and duration defined by this Resolution, namely – minimum 10 stages;

c) the plan for the demarcation of the construction site – scale 1:200 or 1:100;

d) where necessary, the place designated on the construction site for construction machinery and building materials;

e) the schedule for carrying out the construction, taking into account the construction stages;

f) the locations for the placement of temporary buildings and structures;

g) the methods and measures for ensuring safety;

h) the list of acts of concealed works, inspection and testing, which shall be drawn up during the construction process.

3. In the case of restriction of public space during the carrying out of construction, the construction organisation project shall reflect the optimal term and time for carrying out such works (e.g.: delivery of concrete by construction machinery).

4. The construction organisation project shall, where necessary, reflect special measures that ensure the stability/strength of adjacent buildings and structures and will not cause the deterioration of their stability/strength.

Chapter XIIIPermissible amendment of the construction document and violationof the construction document

Article 47. Permissible amendments to a construction document that do not require a construction permit🔗

1. The following amendments to a construction document do not require a construction permit:

a) insignificant change of the main overall dimensions of the load-bearing structural elements of buildings, but not more than 0.1 metre (except for changes in the horizontal cross-section of columns, the width of a supporting wall, the vertical cross-section of girders, the cross-section heights of inter-floor slabs and cantilevers), which must not cause the weakening of the stability of the structural system determined, in accordance with the construction regulation, by the construction implementation documents of buildings.

b) change in the height of a floor by a maximum of 0.2 metres, which must not cause the weakening of the stability of the structural system determined, in accordance with the construction regulation, by the construction document of buildings, the conversion of a technical floor into an incomplete floor and the conversion of an incomplete floor into a complete floor;

c) change in the exterior overall dimensions by not more than 0.4 metres;

d) displacement/change and/or addition/removal of non-load-bearing and self-supporting structural elements of the interior;

e) change, addition or removal of individual local engineering and utility systems of buildings;

f) replacement of construction materials and products with other construction materials and products having the corresponding technical characteristics;

g) displacement/change of such parts of buildings which, in accordance with this Resolution, do not require a construction permit;

h) horizontal displacement of the surface and/or underground part of a building in relation to the ground surface by not more than 1.0 metre;

i) vertical change of the zero level of a building in relation to absolute zero by not more than 0.4 metres, which must not cause the conversion of an underground floor into a surface or above-ground floor;

j) depending on the properties of the ground, additional deepening of the foundation of a building (in the case of point, strip and monolithic slab foundations) by not more than 0.5 metres;

k) depending on the properties of the ground, additional or lesser deepening of the pile foundation of a building to the solid part of the ground.

l) replacement of individual structural elements, materials, products, as well as engineering systems of a structure, which does not cause (notwithstanding changes in the overall dimensions of the structure) a change in the design loads and/or the structural solution.

2. The amendments made to the construction implementation documents as defined by this Article must not violate other permit conditions and must not infringe the rights of third parties.

3. In the event of the introduction into the construction document of the changes defined by subparagraph „l“ of paragraph 1 of this Article, the customer (orderer) shall be obliged to submit the amended design documentation and the relevant expert opinion to the Agency for the purpose of confirming/agreeing the change. Confirmation by the Agency of a change introduced into the construction document shall be effected in written form. The corrected design, the expert opinion and the letter of agreement are an integral part of the construction permit and shall be attached to every copy of the construction document defined by this Resolution;

4. The changes defined in the construction document by paragraph 1 of this Article (except for the case provided for by paragraph 3 of this Article) during the procedure of acceptance of the building/structure into operation constitute permissible changes and their confirmation shall be effected in accordance with the procedure provided for by paragraph 6 of Article 66 of this Resolution.

Article 48. Changes to the construction document requiring a construction permit; violation of the construction document🔗

1. Except for the cases defined in Article 47, the introduction of changes into the construction document requires the obtaining of a construction permit anew.

2. Such a change to the construction document as provides for the construction of new floor(s) on the agreed facility, a change of the development area of the facility by more than 20% or a change of the function of that facility is prohibited. In such a case, the procedure for obtaining a construction permit shall be started anew, in accordance with the applicable legislation.

3. Where, on the basis of the amended construction document design, it is necessary to obtain a construction permit, the procedure for obtaining it shall concern only those parts which had not been defined by the construction document.

4. If, as a result of the construction carried out, such changes were made to the construction document as require a construction permit, and/or unauthorised construction has been carried out, the Agency is entitled to consider the issuance of a construction permit after the offender submits the act issued for the relevant violation and the receipt for payment of the imposed fine, except for other cases provided for by the Code of Product Safety and Free Movement and by legislation.

5. In the case of unauthorised construction and/or construction carried out in violation of the construction document as provided for by this Article, the permit applicant shall be obliged, in order to obtain a construction permit or a new permit, to take into account in the construction document design the construction works carried out (the construction organisation design, the stages of completion of construction, etc.) and to obtain the relevant expert opinion on the construction carried out without a permit and/or in violation of the construction document. A new construction permit shall be issued taking into account the construction already carried out.

Article 49. Authority to make changes to construction documentation🔗

1. Changes to construction documentation by the customer shall be made in compliance with copyright.

2. The authority to make changes to construction documentation upon the customer's instruction shall be held by the implementer of the design of construction implementation documents, in compliance with copyright, or by another principal specialist of construction activity (designer) defined by this Resolution, in compliance with copyright.

Chapter XIVObjects of Special Importance

Article 50. Defining characteristics of objects of special importance🔗

1. Objects of special importance are characterized by an increased risk factor.

2. Objects of special importance include:

a) enterprises manufacturing explosives for industrial purposes;

b) compressor and/or gas distribution station of a main gas pipeline with a capacity of 3000 m³/h and more;

c) enterprises producing mineral fertilizer with a productivity of more than 100 t per day;

d) oil and gas processing enterprises with a productivity of more than 500 t per day;

e) enterprises producing air separation products (oxygen, nitrogen, argon, krypton, xenon and neon-helium mixture);

f) enterprises producing chemical fibre and/or polymer materials;

g) enterprises producing paint materials in which processes are carried out using chemical technologies;

h) enterprises producing cellulose paper;

i) enterprises producing rubber technical products;

j) spirit enterprises with a productivity of more than 10 t per day;

k) enterprises producing cold and/or hot rolled products;

l) enterprises for casting ferrous and/or non-ferrous metals;

m) monolithic structure with a volume of 1000 m³ and more without seismic joints;

n) buildings and structures to be constructed in the Gudauri recreational area, as determined by the relevant legal act;

o) a structure with a height of 50 m and/or more and with an average depth of 30 m and more from the ground surface;

p) a structure whose span and/or truss and/or other structural element length is more than 24 m;

q) metro;

r) storage facilities for oil and oil products, as well as liquid gas – terminals, with a total volume of tanks of 1000 m³ and more;

s) transport tunnel;

t) aerial cableway;

u) funicular;

v) reservoir with a volume of 100,000 m³ and more;

w) towers of the radio-relay system of Georgia;

x) hotels to be constructed as determined by the Law of Georgia “On Promoting the Development of Free Tourist Zones”;

y) aerodrome with code designation 4D (runway length 1800 m and more and aircraft wingspan 36 m and more) and load-bearing capacity PCN 25 and more;

z) electrical substation 330 kV and more;

aa) hazardous waste landfill structure;

bb) non-hazardous waste landfill structure;

cc) power plants (thermal power plant, hydroelectric power plant 50 MW and more);

dd) main oil pipeline;

ee) main gas pipeline;

ff) power transmission lines from 154 kV to 330 kV and more;

gg) motor road of international importance;

gg¹) main railway;

gg²) amelioration and irrigation systems (water intake structure and main canals);

gg³) sewer pipe with a diameter of 1,500 mm and/or treatment facilities with a capacity of 5,000 m³ and more per day;

gg⁴) water pipeline with 25 and more atmospheres and a diameter of 1,400 mm and more and/or water supply head structures with a capacity of 5,000 m³ and more per day.

Article 51. Issuance of a construction permit🔗

1. A construction permit shall be issued in accordance with Chapters VIII–XIII of the Resolution and taking into account the requirements of this Article.

2. For new construction, a construction permit shall be issued on the basis of the conditions for the use of the land plot for construction purposes, the construction document project and the relevant expert opinion.

3. A construction permit for the dismantling of a building/structure and for the reconstruction of the load-bearing elements and networks of a building/structure shall be issued on the basis of the construction document project and the relevant expert opinion.

4. On those buildings/structures defined by subparagraph „n“ of paragraph 2 of Article 50 of this Resolution which have the following characteristics, construction shall be carried out in accordance with the procedure established by paragraph 5 of this Article. The said characteristics are:

a) a building with a total built-up area at floor levels of up to 60 m², a height of up to 5 m and an average depth from the ground surface of up to 2 m;

b) a structure with a volume of up to 20 m², a height of up to 10 m and an average depth from the ground surface of up to 10 m;

c) a fence with a height of up to 4 m from the ground surface;

d) a building/structure the span, truss or other structural element of which has a length less than or equal to 5 m;

e) power plants (a hydroelectric power plant of up to 50 kW, a solar and biogas installation);

f) laying/installation of a communication line (network) using existing infrastructure, or arrangement of a trench/ditch for the laying/installation of a communication line (network) (except where the laying/installation of the communication line (network) additionally requires the construction/installation of a building/structure subject to a permit);

g) a structure provided for by an outdoor advertising placement permit;

h) temporary buildings/structures and/or installations intended for outdoor trade in public areas, with a height of up to 2.5 m and an area of up to 6 m²;

i) a gas pipeline of gas supply (gas distribution) systems (low pressure);

j) a water supply pipe of up to 10 atmospheres, with a diameter of up to 500 mm;

k) a sewer pipe with a diameter of up to 600 mm;

l) a part of a street that is a dead end/passage.

m) an electric transmission line of 1–20 kV;

n) an electric transmission line of up to 1 kV;

o) landscape construction;

p) installation of an air conditioner and a ventilation pipe;

q) placement of an ATM;

r) installation of a canopy;

s) such repair and cladding works on the facade and roof of a building/structure during which the colour or the cladding material of the building/structure is changed;

t) arrangement of open playgrounds and sports grounds (without spectator stands and their infrastructure or other buildings) and open parking lots;

u) arrangement of temporary buildings/structures required for fairs-exhibitions, public and entertainment events to be held in public areas, which have no foundation and in respect of the arrangement of which a decision has been taken by the Government of Georgia or a local self-governing unit;

v) arrangement of sewerage channels and drains on a construction land plot;

w) the arrangement, on a construction land plot, of a pool with a volume of up to 25 m³ and a depth of not more than 2.2 m, of an open swimming pool, as well as of wells and springs;

x) the construction, on construction land plots, of masts up to 8 m in height to be placed thereon, of poles for wiring and lighting, of antennas, and of water pressure towers with reservoirs of up to 2 m³;

y) the arrangement of ramps for persons with limited abilities;

z) the temporary reinforcement of a building/structure in case of emergency;

aa) the placement of signs and advertisements;

bb) the arrangement/dismantling of a mezzanine, staircase, shop window, door, window and other openings. If the said works affect the load-bearing structures of a building/structure, in addition to the documentation provided for by paragraph 5 of this Article, the customer (orderer) shall, before the commencement of the construction works, obtain the relevant conclusion on the safety of the works to be carried out;

dd) the addition/removal of small architectural parts/elements, structures, technical means on the exterior of a building/structure.

5. The construction of a building/structure having the characteristics set out in paragraph 4 of this Article shall be carried out in the following manner:

a) the construction shall be carried out without obtaining a permit, on the basis of a written confirmation. The person carrying out the construction shall comply with the requirements provided for by legislation, including construction regulations.

b) the person carrying out the construction/customer (orderer) shall notify the Agency by application of the intended construction.

c) in the cases defined by subparagraphs „a“–„d“ and „f“–„o“ of paragraph 4 of this Article, the owner and/or user of the respective land plot shall:

c.a) reflect in the application information on the registration of the land plot;

c.b) in the case defined by subparagraph „e“, attach to the application a document confirming ownership or use of the land plot.

c.c) the following shall also be attached to the application:

c.c.a) a topographic map of the location of the building/structure showing the location;

c.c.b) a sketch drawing of the building/structure.

d) in the case of laying/installation of communication lines (networks) in existing engineering-communication channels, shafts and tunnels, as well as on existing poles and masts, and also on other buildings/structures, and in the case of laying a trench, the following shall be attached to the application:

d.a) the consent of the owners of the installation area, the land plot and/or the existing engineering-communication structure(s) and/or the chairperson of the association of apartment owners, and in the case of use of public space _ also the consent of local self-government bodies;

d.b) a route design for the laying/installation of communication lines (networks), drawn up in electronic format;

d.c) a topographic map showing the existing infrastructure.

e). in the case of construction/installation of a structure provided for by an outdoor advertising placement permit, the holder of the outdoor advertising placement permit shall attach to the application:

e.a) the outdoor advertising placement permit;

e.b) a topographic map of the outdoor advertising placement location showing the location;

e.c) sketch drawing of the building.

f) In case of construction/installation of temporary buildings/structures and/or installations up to 3 m in height and up to 6 m² in area designated for outdoor trade in public places, the following shall be attached to the application:

f.a) topographic map of the location of the temporary buildings/structures and/or installation designated for outdoor trade, showing the location;

f.b) sketch drawing of the building/structure.

g) In case of construction/installation of linear structures, the following shall be attached to the application:

g.a) in case of construction/installation of underground linear structures: schematic drawing of the linear structures, its electronic version in the UTM program, recorded on a CD;

g.b) in case of construction/installation of above-ground linear structures: plan of the linear structures, its electronic version in the UTM program, recorded on a CD, design of above-ground constructions;

g.c) consent of the owners of the installation territory, land plot and/or existing linear structure(s) and/or of the condominium owners' association; in case of use of public space – also the consent of the local self-government body.

h) In case of landscape construction, the following shall be attached to the application:

h.a) document confirming ownership or use of the land plot;

h.b) tree-planting inventory plan (with an explanatory letter and a data table of the tree-planting description);

h.c) dendroproject;

h.d) landscape improvement plan plotted on the topographic plan (scale 1:2000).

i) The Agency shall, within 5 days, on the basis of the complete document(s) submitted, confirm in writing the compliance of the planned construction/installation with the urban planning documents and the possibility of carrying out the construction.

j) If within five days the Agency does not notify the applicant of a response, the owner and/or user shall be entitled to start construction.

k) Carrying out construction in violation of the requirements of this Resolution shall be considered as unauthorised construction.

l) Carrying out construction/installation in violation of the document provided for by subparagraph „i“ of this paragraph shall not be considered unauthorised construction, if the Agency confirms in writing the possibility of the construction carried out in violation.

6. On those buildings/structures defined by subparagraph „n“ of paragraph 2 of Article 50 of this Resolution, which have the following characteristics, construction shall be carried out in accordance with the procedure established by paragraph 7 of this Article. The said characteristics are:

a) a building with a total area of up to 300 m² at the floor levels of the development (for individual residential houses – a total area of up to 500 m² at the floor levels of the development) determined by the development intensity (density) coefficient K-2, or in the zone where K-2 is not determined, with a height from 5 m to 12 m and an average deepening from the ground surface from 2 m to 4 m;

b) a structure with a volume of up to 60 m³, a height from 10 m to 15 m and an average deepening from the ground surface from 10 m to 15 m;

c) a fence with a height of more than 4 m from the ground surface;

d) a building/structure the span, truss or other structural element of which has a length less than or equal to 7 m;

e) a reservoir with a volume of up to 1000 m³;

f) a storage facility/terminal for liquid substances with a total tank volume of up to 100 m³;

g) exterior reconstruction;

h) a temporary building and/or structure subject to a construction permit.

7. The construction of a building/structure with the characteristics given in paragraph 6 of this Article shall be carried out in accordance with the following procedure:

a) A construction permit for the construction of a building/structure shall be issued in accordance with Chapters VIII–XIII of the Resolution and taking into account the requirements of this Article.

b) For the new construction of a building/structure, a construction permit shall be issued on the basis of the conditions for the use of the land plot for construction purposes and the construction document design.

c) A construction permit for the reconstruction of a building/structure shall be issued on the basis of the construction document design, the architectural design agreed in the cases determined by this Resolution, the structural and/or technological scheme, and the additional conditions for the use of the land plot for construction purposes, in the case where the reconstruction causes a change in the conditions for the use of the land plot for construction purposes.

d) A construction permit for the reconstruction of the load-bearing elements of a building/structure and local common-use networks shall be issued on the basis of the construction document design.

e) A construction permit for exterior reconstruction shall be issued on the basis of the agreed architectural design and the structural and/or technological scheme.

f) A construction permit for dismantling works of a building/structure shall be issued on the basis of the construction document design.

Article 52. Construction document draft🔗

1. The construction document draft includes:

a) a title page – the name and address of the facility;

b) the conditions for the use of the land plot for construction (in the cases determined by this Resolution);

c) the engineering-geological survey/report of the land plot;

d) an explanatory note;

e) the technical indicators of the building/structure:

e.a) the area of the land plot;

e.b) the value of the applied K1 and the built-up area;

e.c) the value of the applied K2 and the development density area, showing the built-up area of each floor;

e.d) the value of the applied K3 and the landscaping area;

e.e) the zero elevation of the building/structure in relation to the absolute zero elevation;

e.f) the structural height of the building/structure;

e.g) the area of the building/structure, including, if present: the area of the residential house; the area(s) of the apartment(s); the office area; the area(s) of commercial and household services; the production area; the warehouse area; the areas of the stairwell and entrances; the summer (balconies, terraces, verandas and loggias) areas;

f) a situational plan with appropriate detailing;

g) the topographic plan of the land plot showing its cadastral boundaries and existing engineering-utility networks;

h) the land plot plan placed on the topographic plan of the land plot (e.g., showing the cadastral boundaries of the land plot, existing engineering-utility networks, the placement of the building/structure on the land plot, the depiction of access roads, parking lots, fences, landscaping and other parts); scale 1:500 or 1:1000;

i) the plans of all floors of the building (showing the projection of the cadastral boundary, the elevations of the floor surfaces, and the zero elevation of the building/structure in relation to the absolute zero elevation);

j) the roof plan of the building (showing the projection of the cadastral boundary);

k) the characteristic sections of the building (showing the projection of the cadastral boundary, the elevations of the floor surface, the elevations of the floor covering surface, and the zero elevation of the building/structure in relation to the absolute zero elevation);

l) the drawings of all facades of the building, determining its facing material, the architectural details on the facade and the colors of the facade;

m) if necessary, the drawings of the facades (design surfaces), showing schematic drawings of the facades (design surfaces) of the building existing on adjacent land plots (e.g., street elevation);

n) if necessary, schematic drawings of the elevations of the facades (design surfaces), showing the intersection of the building and the ground surface;

o) if necessary, a plan of the change of the ground surface of the land plot;

p) if necessary, a project for the improvement of the territory of the land plot;

q) as necessary, project(s) for connection to the main engineering-utility networks;

r) projects of the local common-use engineering-utility networks of the building/structure;

s) if necessary, a technological scheme of the relevant production process(es);

t) the construction organisation project, in accordance with this Resolution.

2. In the case of construction of linear structures, the construction document draft includes:

a) a title page – the name of the object and its address;

b) the conditions for use of the land plot for construction (in the cases determined by this Resolution);

c) engineering-geological survey/conclusion of the territory required for the linear structure(s);

d) an explanatory note;

e) technical indicators of the linear structure;

f) a situation plan with appropriate detailing;

g) a topographic plan of the territory required for the linear structure(s), showing the existing engineering communications;

h) on the topographic plan of the territory required for the linear structure(s), a plan of placement of the linear structure(s) on the land plot(s);

i) plans of the linear structure(s);

j) characteristic sections of the linear structure(s);

k) where necessary, schematic drawings of the views/facades of the linear structure(s);

l) where necessary, a plan of changes to the ground surface and underground engineering communications of the territory required for the linear structure(s);

m) a structural design of the linear structure, which consists of a detailed design of the main structural system of the linear structure;

n) where necessary, a technological scheme of the relevant production process(es);

o) the construction organisation project, in accordance with this Resolution.

3. The requirements determined by subparagraphs „e“, „f“, „g“, „h“, „i“, „j“, „k“, „l“, „m“, „n“, „o“, „q“, „r“ and „s“ of the first paragraph of this Article shall be presented in the form of drawings:

a) for the main drawings – at a scale of 1:50; 1:100 or 1:200;

b) for the detailed drawings – at a scale of 1:1; 1:2; 1:5; 1:10 or 1:20.

4. The construction document draft of a building/structure may additionally include an electronic version.

5. By decision of the customer, the construction document draft may additionally include:

a) photographs of the territory;

b) digital visualisation, an electronic version of the design and/or a model.

6. The parts of the construction document draft of a building/structure determined by the first paragraph of this Article may be presented in a combined form.

7. The draft document of the construction document of a building/structure having the characteristics given in paragraph 6 of Article 51 of this Resolution includes the documentation given in the first and 2nd paragraphs of this Article, except for the documentation given in subparagraph „c“ of the first paragraph and subparagraph „c“ of the 2nd paragraph.

Article 53. Permit conditions🔗

1. The holder of a construction permit shall fulfil the following permit conditions:

a) conduct the construction without violation of the construction document;

b) conduct the construction in compliance with the requirements of construction regulations;

c) after the completion of each stage of construction envisaged by the construction document, draw up a protocol on the completion of the construction stage in the manner determined by this Resolution;

d) perform all construction works determined by the construction implementation documents;

e) within one year from the expiry of the construction permit, carry out the commissioning of the object;

f) other requirements established by legislation.

Chapter XVProcess of fulfilment of the permit conditions determined by the construction permit

Article 54. Commencement of construction🔗

Before the commencement of construction works, the permit holder shall have on the construction site a duly certified copy of the construction document and the documentation envisaged by paragraph 2 of Article 18 of this Resolution, signed by the responsible person.

Article 55. Construction site and safety of the construction process🔗

1. Before the commencement of main construction works, the construction site and its adjacent territory shall be arranged in accordance with this Resolution.

2. The territory of the construction site and its boundaries shall be determined by the construction implementation documents.

3. The boundaries of the construction site shall, as a rule, fall within the boundaries of the land plot.

4. In cases where the boundaries of the construction site are not sufficient for carrying out construction activity and there is a justified necessity for this, the use of the adjacent land plots and/or public territory/space not owned by the holder of the construction permit shall be determined by a contract concluded between the holder of the construction permit and the owners of these land plots and/or public spaces/territories. Local self-government bodies shall establish the rules for temporary use of public territory/space.

5. In case of justified necessity, the owners of adjacent land plots shall not be entitled to restrict the holder of the construction permit in carrying out construction activity.

6. In case of justified necessity, when using public spaces/territories, the possibility of minimal restrictions of public spaces/territories and the conditions for avoiding damage, as well as the interests of third parties, shall be taken into account.

7. The arrangement of the construction site shall be carried out in compliance with the requirements of the construction regulations of construction activity.

8. On the construction site, all places where third parties may be injured by construction activity shall be delimited and marked with warning signs.

9. Before the commencement of construction works, the construction site shall be delimited with a safety protective fence and equipped with appropriate lighting. The fence shall be arranged so as to protect third party(ies) from falling objects.

10. The measures carried out on the construction site shall ensure the requirements of the construction regulations of the respective construction activity, including:

a) its cleanliness and shall not allow pollution of adjacent land plots and streets, as well as damage to the road surface of these streets;

b) protection of main and public utility engineering communications/buildings located on the construction site;

c) fire safety;

d) compliance with appropriate working hygiene conditions;

e) safety of the performance of works;

f) avoidance of pollution of the adjacent environment, including streets and public spaces, by production waste, wastewater and air dust;

g) performance of works within permissible levels of noise and vibration.

11. Before the dismantling of the buildings and structures existing on the construction site, their disconnection from the main engineering-utility networks of electricity supply, natural gas supply, water supply and drainage shall be ensured, but the customer (orderer) shall notify the companies owning the respective main engineering-utility networks of the disconnection at least ten days before the disconnection. The companies owning the main engineering-utility networks have the right to exercise technical supervision over the disconnection process.

12. After the arrangement of the foundation of a building/structure, the data of the setting-out on the ground of the building/structure placed on the construction site shall be transferred to the foundation and shall be preserved until the completion of the foundations.

13. An information board perceptible from public spaces shall be fixed on the construction site in accordance with the requirements of this Resolution.

Article 56. Measures to be implemented on land plots adjacent to the construction site🔗

1. If the construction site is damaged, or may be damaged by water leakage, ground sliding and other natural or artificial impacts caused from adjacent land plots, in this case the owner(s)/user(s) of such adjacent land plot(s) shall not have the right to hinder the implementation of the necessary respective measures on the land plot(s) in their ownership/use, and at the same time, after the implementation of the respective necessary measures, such adjacent land plot(s) shall be brought to the condition existing before the damage.

2. During the construction on the construction site, the measures implemented on adjacent land plots shall not create a threat to the construction. If this nevertheless occurred, in this case the owners/users of the land plots adjacent to the construction site shall themselves correct it.

Article 57. Sequence and stages of the construction implementation process🔗

1. The construction implementation process is divided into sequences, and the sequences – into stages.

2. The sequence and stages of the construction implementation process are determined by the construction implementation documents.

3. The construction implementation documents of a building/structure shall determine at least two sequences of the construction implementation process:

a) Sequence I – preparatory works for the construction implementation;

b) Sequence II – main works for the construction implementation.

Article 58. Preparatory Works and Stages for the Implementation of Construction🔗

1. Preparatory works for the implementation of construction consist of two stages, and in the case of a change in the ground surface, of three stages:

a) preparatory works related to the arrangement of the construction site, including the demolition of depreciated or other existing structures and the removal of construction waste, the protection of green plantings to be preserved, and the relocation of underground engineering communications;

b) staking out of the building/structure on the ground and fixing of the main axes;

c) in the case of a change in the ground surface of the land plot, staking out of the building/structure on the ground and fixing of the main axes after the changed surface of the ground.

2. Preparatory works include both organizational measures and external and internal works of the construction site, which shall be performed in accordance with the construction implementation documents.

Article 59. Main sequence works and stages of construction implementation🔗

1. Main sequence works for the construction implementation of a building/structure are divided into the following stages:

a) Earthworks for buildings/structures;

b) Works for the arrangement of the base of buildings/structures;

c) Works for the arrangement of the foundation of buildings/structures;

d) Arrangement of the main structural system up to the zero level of the building/structure;

e) Arrangement of the main structural system (excluding non-load-bearing structures) from the zero level of the building/structure at a height of at most every 7.0 metres (in the case of floors, in multiples of floors);

f) Arrangement of the roof and roofing of buildings/structures;

g) Arrangement of non-load-bearing structures;

h) Arrangement of local common-use engineering and utility networks of buildings/structures;

i) Installation of technological equipment;

j) External facing works of buildings/structures;

k) Improvement works.

2. Main sequence works for the construction implementation of a linear structure are divided into the following stages:

a) Earthworks (e.g.: arrangement of earth embankments, trenches, channels, pits);

b) Works for the arrangement of the base of linear structures;

c) Works for the arrangement of the grillage;

d) Works for the arrangement of pipelines, cable or ropeway lines and other conduits;

e) Works for the arrangement of piers and supports;

f) Works for the arrangement of spans;

g) Construction/installation works of buildings/structures necessary for the functioning of the linear structure provided for by the construction document (e.g.: towers, stations, substations, distribution points, storage facilities, terminals and/or other buildings/structures);

h) Works for the arrangement of pavement, paving or track;

i) Testing works of the linear structure;

j) Improvement works.

3. The construction implementation documents may provide for the combination and division of the main sequence stages of construction implementation.

4. In the cases provided for by Article 48 of this Resolution, if all works provided for by this Article have already been carried out at the construction site, the drawing up of a construction stage completion protocol is not mandatory; accordingly, the permit holder shall be under an obligation to submit the facility for commissioning.

Article 60. Completion of Construction Stage🔗

1. Upon completion of each stage of construction provided for by the permit conditions, the permit holder shall draw up a record on the completion of the construction stage on the basis of an inspection of the works carried out at the construction site and determination of compliance with the permit conditions.

2. The record on the completion of the construction stage shall be signed by the customer, the contractor and/or their duly authorised representative, and the expert in construction activity.

3. The record drawn up on the completion of the construction stage shall be submitted in written form to the Agency after completion of the relevant stage, where, after registration, it is a document having legal force.

4. Responsibility for the correctness of drawing up the record on the completion of the construction stage shall be borne by the person drawing up the record. Failure to draw up the record or entry of incorrect data in the record shall entail the liability provided for by the Law of Georgia – the Code of Product Safety and Free Movement.

5. This article shall not apply to the construction of facilities that are carried out on the basis of an international treaty and/or with the participation of foreign financing (attracted international funds, investment, credit), and for the construction of which technical supervision is carried out on the basis of an international treaty and/or a tender, as well as by supervisory (expert) companies selected in accordance with the special procedure established by the Government of Georgia for the procurement of goods or services as determined by the Law of Georgia "On Public Procurement" and/or provided for by Article 3 of this Law, or by services staffed with special professional personnel existing within the customer's structure.

6. Upon final completion of the construction of the facilities referred to in paragraph 5 of this article, the holder of the construction permit shall submit to the Agency a final document confirming the full compliance of the facility with the norms and standards of the design documentation. The said document shall also contain information on the acts of completion of construction works performed in accordance with the established procedure during the entire construction period, other necessary documentation, and certificates of conformity of the materials used, and their storage location.

Chapter XVIConservation of Construction

Article 61. Conservation of Construction🔗

1. In the event of suspension of the construction process by the customer for more than 6 months, the conservation of the construction object shall be carried out, of which the Agency shall be notified.

2. Conservation implies protection of the stability, safety and sanitary norms of the object, preservation of its structural elements without damage, which ensures the possibility of subsequent continuation of construction activities, as well as the safety of adjacent buildings and territories.

3. The process of conservation of the construction object includes:

a) suspension of the performance of construction works provided for by the permit conditions;

b) determination of the conservation conditions and implementation of the measures necessary for conservation;

c) periodic inspection of the object by the customer for safety purposes.

4. The conditions for conservation of the construction object shall be determined in compliance with the requirements of the relevant construction regulations.

5. The conservation of the object shall be carried out in such a way that its physical wear and tear does not occur, in particular:

a) garbage and construction waste shall be removed from the object;

b) the object shall be arranged in such a way that corrosion of metal structures, products and elements does not occur; reinforced concrete joints shall be covered with concrete;

c) the foundation and the pit shall be protected from sliding of slopes, as well as from atmospheric precipitation and water accumulation;

d) safety requirements shall be observed at the object and the construction site;

e) all materials (boards, formwork, cement, gypsum, etc.) shall be stored in such a way that their falling, dropping, spilling, pollution or damage to the adjacent territory does not occur, and no other unforeseen consequences ensue;

f) the inaccessibility of the construction site to unauthorized persons shall be ensured (safety fence, locked gate);

g) the construction object shall not be used as a warehouse, storage, temporary dwelling, or for other purposes;

h) the safety of persons admitted to the construction site shall be ensured;

i) crane mechanisms shall be brought into such a condition as ensures the avoidance of negative consequences under any weather conditions;

j) a visible marking on the conservation of the object shall be made on the information board;

k) in places and cases determined by legislation, the object shall be wrapped with a protective net. Depending on wear, the protective net shall be periodically renewed and replaced, as well as the safety fence shall be renewed and repainted;

l) the permit holder/customer shall regularly, at the frequency necessary to ensure compliance with established requirements, inspect the conserved object.

6. In the decision taken by the customer on the conservation of the construction object and in the notification to the Agency, the required period for the conservation of the construction object and the conditions for conservation of the object determined in compliance with the requirements of the relevant construction regulations shall be determined.

7. When a building or structure is transferred to the conservation regime, a conservation act shall be drawn up, signed by the permit holder/customer and the Agency's authorised responsible person(s) for the specific object. In the event of the non-appearance of the Agency's representatives, the conservation record shall be drawn up by the customer and shall be valid immediately upon its submission to the Agency.

8. From the day of submission to the Agency of the act provided for by paragraph 7 of this Article, the running of the term of the construction permit shall be considered suspended. The running of the term of the construction permit shall resume after the completion of the conservation regime.

9. The conservation of a building or structure may be effected for a period of not more than three years, and in a special construction regulation zone — for a period of not more than one year.

10. After the expiry of the term determined by paragraph 9 of this Article, the customer shall be obliged to resume the construction of the conserved building or structure or to carry out its demolition.

11. In the event of the elimination of the reasons that gave rise to the conservation of the object, a decision on the resumption of construction shall be taken, which shall be communicated to the Agency.

12. The resumption of the construction process shall be carried out in compliance with the requirements of the legislation, in particular, of this Resolution and of the construction regulations.

13. The requirements of this Article shall apply, inter alia, to such dilapidated, burnt and buildings or structures unfit for acceptance into operation whose demolition is not provided for.

14. The conservation regime determined by this Article shall not apply to demolition works to be carried out on the basis of a relevant decision of the Agency or of a court.

Chapter XVIISupervision of Construction Activity and Liability

Article 62. State supervision of construction🔗

1. State supervision of construction is the control exercised by the Agency over the fulfilment of permit conditions and the acceptance of a building or structure into operation, as well as the detection of unauthorised construction or construction carried out in violation of legislation and responding thereto in accordance with legislation.

2. Works to be carried out for the purpose of remedying a violation by the construction customer on the basis of an instruction/assignment of the Agency or a court judgment shall not require a construction permit.

Article 63. Responsibility for the safety of construction activity and the correctness of documentation🔗

1. Responsibility for the correctness of the documentation submitted by the customer (orderer) shall be borne by the customer and the person executing the document, who confirms by signature the correctness of the drawn-up document.

2. Responsibility for the correctness of the documentation defined by paragraph 2 of Article 18 of this Resolution shall be borne by the customer and the person executing the document, who confirms by signature the correctness of the drawn-up document.

3. The Agency verifies the compliance of the documents submitted by the customer with the legislation in force and is responsible only for the compliance with legislation of the documents certified by it.

4. Responsibility for construction safety shall be borne by the customer, the author (executor) of the relevant document and the person responsible for construction safety (if any).

Chapter XVIIIAcceptance of a building/structure into operation

Article 64. Building/structure prepared for acceptance into operation🔗

1. Acceptance into operation of the construction carried out means the final determination of the compliance of the completed construction with the permit conditions.

2. The obligation to accept a building/structure into operation shall not be borne by the customer in the case of reconstruction of the exterior and networks.

3. Acceptance of a building/structure into operation is possible if, as a result of the construction carried out, the obligations defined by the permit conditions have been fulfilled and are not violated.

4. Independently functioning object(s) of a complex of buildings/structures, the construction of which has been completed in accordance with the permit conditions, may be accepted into operation.

5. Partial acceptance into operation of a motor road/section(s) of a motor road is possible after the submission of a document confirming the completion of the construction works provided for by the construction document for ensuring traffic safety, which shall be confirmed by the state body that is the customer of the construction in accordance with the documentation provided for by subparagraph „b“ of paragraph 5 of Article 65 of this Resolution. Acceptance into operation of a motor road/section(s) of a motor road shall be carried out in accordance with the procedure defined by this Resolution.

Article 65. Submission for acceptance of a building/structure into operation🔗

1. It shall be inadmissible to establish other requirements for the acceptance of a building/structure into operation, except for those determined by the permit conditions.

2. For acceptance of a building/structure into operation, the customer (orderer) shall apply with an application within the period determined by the Agency for acceptance into operation.

3. The application shall be accompanied by:

a) drawings reflecting the final condition of the building/structure, prepared taking into account the changes made, in 3 copies; in the absence of changes, a declaration on the absence of changes. In such a case, submission of the drawings shall not be mandatory;

b) in the city of Tbilisi, a cadastral survey drawing of the land plot and the buildings/structures located thereon (except for construction provided for by paragraph 3 of Article 4 of this Resolution);

c) in the event of the presence in buildings/structures of mechanical and technological devices, including elevators and escalators, and in the case of industrial and production facilities – acts of testing of additionally installed technological devices and/or lines, certified by the relevant body. In the absence of such bodies, the results of the test carried out in accordance with the installation documentation of the devices, certified by the installation organization and the customer (orderer), shall be submitted;

4. During acceptance into operation of part(s) of a building/structure (except for a motor road/motor road section(s) of international importance), the application shall be accompanied by:

a) a new construction organization project prepared taking into account the methods and measures for ensuring construction safety. In such a case, agreement of the new construction organization project with the Agency shall not be mandatory;

b) drawings reflecting the final condition of the part(s) of the building/structure (including plans of the respective floor(s) prepared taking into account the changes made and indicating technical-economic indicators) in 3 copies and an explanatory card;

c) in the part(s) of buildings/structures submitted for acceptance into operation, in the event of the presence of mechanical and technological devices, including elevators and escalators, and in the case of industrial and production facilities – acts of testing of additionally installed technological devices and/or lines, certified by the relevant body. In the absence of such bodies, the results of the test carried out in accordance with the installation documentation of the devices, certified by the installation organization and the customer (orderer), shall be submitted;

d) expert opinion on the compliance of the new construction organization project with the construction norms and rules in force, on the compliance of the methods established for ensuring construction safety and the measures implemented with the conditions provided for by the new construction organization project, and on the readiness of the part(s) of the building/structure for further safe operation (functioning);

e) cadastral survey drawing of the land plot with the buildings and structures located thereon.

5. When a motor road of international importance/a section(s) of a motor road is partially put into operation, the application shall be accompanied by:

a) information on the picket(s) of the motor road/section(s) of the motor road;

b) a document confirming the completion of the construction works provided for by the construction document for ensuring road traffic safety:

b.a) a positive opinion of the advisory body – the Technical Council – of the Roads Department of Georgia, a state sub-agency institution under the governance of the Ministry of Regional Development and Infrastructure of Georgia;

b.b) a document agreed by the relevant structural subdivision or territorial bodies of the Ministry of Internal Affairs of Georgia, confirming the conditions for organising road traffic on the motor road/section(s) of the motor road.

6. If the holder of a construction permit submits a building/structure for acceptance into operation in violation of the time limit established for acceptance into operation for the relevant class, the application shall additionally be accompanied by a receipt for payment of the fine imposed for violation of the relevant permit condition.

7. If, at the time of completion of a construction stage of a building/structure submitted for acceptance into operation, the records were not drawn up or were not drawn up in the prescribed manner, the customer (orderer) shall attach to the application an expert opinion on the compliance of the works provided for by the construction stages defined by the permit conditions with the permit conditions.

Article 66. Acceptance of a building/structure into operation🔗

1. The decision on acceptance of a building/structure into operation or on refusal of acceptance shall be made by the Agency. Acceptance into operation shall be carried out in accordance with the simplified administrative proceedings procedure.

2. The Agency shall carry out the final inspection/check and acceptance into operation of the building/structure within the framework of one administrative proceeding, during which the customer shall be obliged to ensure unimpeded and unconditional access of the Agency's representative to the site. The administrative proceeding shall commence from the moment of registration with the Agency of the application of the authorised person regarding the request for acceptance into operation. In the process of the administrative proceeding on acceptance into operation, the construction supervision body:

a) checks the compliance of the application and the documentation attached thereto with the legislation and, in the event of establishing a defect, acts in accordance with the legislation;

b) carries out the final inspection/check;

c) carries out an examination of the building/structure and/or, if necessary, measurement in order to establish its compliance with the documents for its construction;

d) in the event of detection of a violation in the building/structure, carries out the relevant response in accordance with the legislation;

e) issues an administrative-legal act on acceptance of the building/structure into operation or on refusal thereof.

3. After the elimination, in accordance with the established procedure, of the violations recorded in the process of the final inspection, in the event of a repeated application by the customer, the relevant body shall be entitled to conduct a repeated inspection/check of the building/structure.

4. The decision on acceptance into operation of the buildings/structures defined by this Resolution shall be made within 30 days from the submission of the application;

5. If, within the period provided for by paragraph 4 of this Article, the relevant administrative-legal act on acceptance into operation or refusal of acceptance of the buildings/structures is not issued, after the expiry of the said period the building/structure shall be considered accepted into operation and, upon the request of the permit holder, the Agency shall be obliged to immediately issue an administrative-legal act on acceptance of the buildings/structures into operation.

6. By the decision on acceptance into operation of the building/structure or part(s) thereof, the fulfilment of the permit conditions and/or permissible changes shall be confirmed. The act shall be issued in 3 copies and shall be accompanied by drawings reflecting the final condition of the building/structure accepted into operation, duly certified by the body issuing the act.

7. If, after acceptance of the building/structure into operation, it is found that it has structural defect(s), liability for the said shall, on the basis of the relevant expert opinion, be borne by the architect (architectural company); the structural engineer, construction company or the Agency.

8. The grounds for refusal of acceptance of a building/structure into operation are:

a) failure to submit the documents provided for by Article 65 of this Resolution or submission of incorrect documents;

b) in the case provided for by paragraph 2 of this Article – refusal by the customer (orderer) or his/her authorized representative to allow the Agency's representative to inspect the building/structure, obstruction, or failure to create proper conditions for the inspection;

c) violation and/or non-fulfilment of permit conditions.

9. The grounds for refusal to accept into operation the part(s) of a building/structure (except for the part(s) of a motor road/motor road section of international importance) are:

a) failure to submit the documents provided for by Article 65;

b) in the case provided for by paragraph 2 of this Article, refusal by the customer (orderer) or his/her authorized representative to allow the Agency's representative to inspect the building/structure, or obstruction;

c) violation and/or non-fulfilment of permit conditions;

d) non-fulfilment of the methods and measures established to ensure construction safety, or non-compliance of the implemented measures with the submitted final construction organization project, negative expert assessment and/or violation of construction safety rules.

10. The ground for refusal to accept into partial operation the part(s) of a motor road/motor road section of international importance is failure to submit the documentation provided for by paragraph 5 of Article 65 of this Resolution.

11. The Agency adopts the decision on acceptance into operation of the part(s) of a building/structure within the scope of its discretionary authority.

12. Responsibility for the correctness of the documents submitted for acceptance into operation of a building/structure or its part(s) shall be borne by the customer (orderer).

Chapter XIXPossibility and ensuring of the supply of a construction site and building/structure with water, sewerage, electricity and natural gas

Article 67. Possibility and provision of supplying a construction site and building with water, sewerage, electricity and natural gas🔗

1. At the request of the customer and/or the owner/user, the possibility of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas implies receipt of information from the company owning the respective main engineering-utility networks on the possibility of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas.

2. Companies owning the respective main engineering-utility networks shall, in accordance with the requirements of the General Administrative Code of Georgia, submit to administrative bodies, in the exercise of public legal powers, information respectively on the possibility of supplying the construction site and building with water, sewerage, electricity and natural gas. The said information is public.

3. Companies owning the respective main engineering-utility networks are obliged to issue information on the possibility of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas, and in the absence of such possibility – on a reasoned/substantiated refusal.

4. In the case where the companies owning the main engineering-utility networks do not have the possibility of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas, but there is a possibility of their development, in such case the respective companies have no right to refuse the possibility of providing and connecting the main engineering-utility networks.

5. The provision of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas shall be determined in accordance with contracts concluded between the companies owning the main engineering-utility networks and the owner(s) of local engineering-utility networks, taking into account the conditions determined by paragraphs 6, 7 and 8 of this article.

6. Under the contract on the provision of supplying the construction site and building with water, sewerage, the sewage network, electricity and natural gas concluded between the companies owning the main engineering-utility networks and the owner of local engineering-utility networks, enrolment as a subscriber is effected in respect of the object (building and/or land plot) and not its owner. Accordingly, in the case of alienation of the said building and/or land plot, the conditions/capacities determined by the contract shall be automatically transferred to the new owner.

7. The holder of a construction permit that has concluded a contract with the companies owning the main engineering-utility networks on the connection of local engineering-utility networks to the main engineering-utility networks shall, at least 10 days before the commencement of the connection works, provide written notification to the owner of the respective main engineering-utility networks about the performance of the works of connection of the local engineering-utility networks to the main engineering-utility networks.

8. The works of connection of local engineering-utility networks to the main engineering-utility networks, to be carried out in accordance with the respective normative-technical documents of construction activity, shall be performed on the basis of a contract concluded between the holder of the construction permit and any construction organisation or installation engineer performing the works. The owner of the respective main engineering-utility networks is entitled to exercise technical supervision over the connection works.

9. After the completion of the works provided for by paragraph 8 of this Article, an act on the connection shall be drawn up between the holder of the construction permit and any construction organisation or installation engineer performing the works.

Chapter XXTransitional and Final Provisions

Article 68. Proceedings commenced before the entry into force of the Resolution🔗

1. For those objects in respect of which the procedure for issuing a construction permit was commenced before the entry into force of this Resolution or a construction permit was issued, but the building/structure has not been put into operation, the legislation in force at the moment of submission of the application shall apply.

2. Payment of the construction permit fee for the objects defined by paragraph 1 of this Article shall be made in accordance with the legislation in force at the time of the entry into force of this Resolution.

3. If buildings have been constructed before the entry into force of this Resolution in non-compliance with the requirements of this Resolution, during their reconstruction it shall be inadmissible to increase the degree of the existing non-compliance with the requirements of the Resolution any further. All possibilities must be used to reduce it.

Article 69. Administrative proceedings commenced before the entry into force of the Environmental Assessment Code🔗

The legislation in force at the moment of submission of the application shall apply to administrative proceedings commenced before 1 January 2018.

Article 70. The Resolution shall enter into force on 3 June 2019.🔗

Prime Minister Mamuka Bakhtadze