On the Approval of the Criteria and Rule Necessary for the Preparation of a Decision/Conclusion in Connection with the Approval of the Conditions for the Use of a Land Plot for Construction and/or the Agreement of an Architectural Project by the Ministry of Internal Affairs of Georgia in Administrative Proceedings Related to the Issuance of a Construction Permit for Objects of Special Importance (Including Radiation or Nuclear Objects) and the Issuance of a Construction Permit for Buildings/Structures of Class II-IV
Text of the document
📑 Contents (7 articles)
On the Approval of the Criteria and Rule Necessary for the Preparation of a Decision/Conclusion in Connection with the Approval of the Conditions for the Use of a Land Plot for Construction and/or the Agreement of an Architectural Project by the Ministry of Internal Affairs of Georgia in Administrative Proceedings Related to the Issuance of a Construction Permit for Objects of Special Importance (Including Radiation or Nuclear Objects) and the Issuance of a Construction Permit for Buildings/Structures of Class II-IV
Joint Order No. 81–No. 1-1/381 of the Minister of Internal Affairs of Georgia and the Minister of Economy and Sustainable Development of Georgia
29 October 2024
Tbilisi
On the Approval of the Criteria and Rule Necessary for the Preparation of a Decision/Conclusion in Connection with the Approval of the Conditions for the Use of a Land Plot for Construction and/or the Agreement of an Architectural Project by the Ministry of Internal Affairs of Georgia in Administrative Proceedings Related to the Issuance of a Construction Permit for Objects of Special Importance (Including Radiation or Nuclear Objects) and the Issuance of a Construction Permit for Buildings/Structures of Class II-IV
Pursuant to subparagraph „i1“ of paragraph 2 of Article 3 of the Rules and Conditions for the Issuance of a Construction Permit and the Commissioning of a Building/Structure approved by Resolution No. 255 of 31 May 2019 of the Government of Georgia „On the Rules and Conditions for the Issuance of a Construction Permit and the Commissioning of a Building/Structure“, subparagraph „e1“ of paragraph 1 of Article 17 of Resolution No. 257 of 31 May 2019 of the Government of Georgia „On the Rules for the Issuance of a Construction Permit for Objects of Special Importance (Including Radiation or Nuclear Objects) and Permit Conditions“, and Article 9 of the Organic Law of Georgia „On Normative Acts“, we order:
Article 1🔗
The criteria and rule necessary for the preparation of a decision/conclusion in connection with the approval of the conditions for the use of a land plot for construction and/or the agreement of an architectural project by the Ministry of Internal Affairs of Georgia in administrative proceedings related to the issuance of a construction permit for objects of special importance (including radiation or nuclear objects) and the issuance of a construction permit for buildings/structures of Class II-IV shall be approved.
Article 2🔗
The Ministry of Internal Affairs of Georgia shall be tasked with:
a) before this Order enters into force, ensure the provision of the relevant information on the objects of the system of the Ministry of Internal Affairs of Georgia provided for by this Order to the administrative bodies issuing construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures;
b) in the event of a change in the data provided for by subparagraph „a“ of this Article, provide information to the administrative bodies issuing construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures within 10 working days from the implementation of the change.
Article 3🔗
1. This Order, except for Article 2 of this Order, shall enter into force from 31 October 2024.
2. Article 2 of this Order shall enter into force upon publication. Minister of Internal Affairs of Georgia Vakhtang Gomelauri Minister of Economy and Sustainable Development of Georgia Levan Davitashvili
Criteria and procedure required for the preparation by the Ministry of Internal Affairs of Georgia of a decision/conclusion in administrative proceedings related to the issuance of construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures, in connection with the approval of the conditions for the use of a land plot for construction and/or the approval of an architectural project
Article 1. General provisions🔗
This Rule determines, in accordance with Article 109 of the Code of Spatial Planning, Architectural and Construction Activities of Georgia, as well as subparagraph „i1“ of paragraph 2 of Article 3 of the rules and conditions for issuing a construction permit and commissioning a building-structure approved by Resolution No. 255 of the Government of Georgia of 31 May 2019 „On the rules and conditions for issuing a construction permit and commissioning a building-structure“, and subparagraph „e1“ of paragraph 1 of Article 17 of Resolution No. 257 of the Government of Georgia of 31 May 2019 „On the rules for issuing a construction permit for objects of special importance (including radiation or nuclear facilities) and permit conditions“, the criteria necessary for the preparation of a decision/conclusion by the Ministry of Internal Affairs of Georgia (hereinafter – the Ministry) in administrative proceedings related to the issuance of a construction permit for objects of special importance (including radiation or nuclear facilities) and a construction permit for Class II-IV buildings and structures, in connection with the approval of the conditions for the use of a land plot for construction and/or the approval of an architectural project, if the administrative proceedings on the issuance of a construction permit for objects of special importance (including radiation or nuclear facilities) and a construction permit for Class II-IV buildings and structures are conducted within a radius of 100 or 300 metres from an object in the possession of the Ministry's system.
Article 2. Categories of objects of the Ministry's system🔗
The objects of the Ministry's system are divided into the following categories:
a) Category I – administrative buildings, which includes such buildings as:
a.a) administrative buildings of the Ministry;
a.b) locations of territorial bodies or structural units;
a.c) coast guard stations;
a.d) examination grounds of the Ministry's service agency;
a.e) locations for the placement of archival documents;
a.f) warehouse buildings;
a.g) service centres for the provision of services;
a.h) penalty parking lots;
b) Category II – places of detention, which includes such buildings as:
b.a) temporary placement isolators;
b.b) receiving department (centre) for asylum seekers;
b.c) reception and temporary accommodation centre;
c) Category III – bases intended for special purpose squads;
d) Category IV – shooting range;
e) Category V – locations of fire-rescue units;
f) Category VI – ports;
g) Category VII – border sectors/border posts located in the border zone and border strip;
h) Category VIII – aerodrome, heliport.
Article 3. Criteria to be taken into account before the commencement of construction around the objects of the Ministry's system🔗
1. If construction is planned within a radius of 100 metres from category I buildings, the following circumstances shall be taken into account when planning construction:
a) construction shall be planned in such a way that it does not hinder the operational movement of units and rapid response to an incident;
b) construction shall be planned in such a way that the location and design of the object to be built do not hinder the functioning of the maritime monitoring means (radar and video surveillance systems) existing in the units;
c) during construction works, the possibility of blocking the access motor road to the object shall be minimised;
d) during construction works and as a result of the completion of construction, the number of existing access motor roads to the Ministry's object shall not be reduced.
2. If construction is planned within a radius of 100 metres from category II buildings in populated areas, and within a radius of 300 metres in unpopulated areas, the following circumstances shall be taken into account when planning construction:
a) construction shall be planned in such a way that it does not hinder the operational movement of employees of the Temporary Detention Isolator and the Migration Department and rapid response to an incident;
b) during construction works, the possibility of blocking the access motor road to the object shall be minimised;
c) during construction works and as a result of the completion of construction, the number of existing access motor roads to the Ministry's object shall not be reduced;
d) the territory of the object shall not fall within the field of view of the object to be built;
e) it shall not be possible to supply items from the building to detained persons in an unlawful manner;
f) it shall be impossible to establish direct communication from the building with detained persons;
g) no conditions shall be created that facilitate the possibility of escape by detained persons.
3. If construction is planned within a radius of 300 metres from category III buildings, the following circumstances shall be taken into account when planning construction:
a) construction shall be planned in such a way that it does not hinder the operational movement of units and rapid response to an incident;
b) during construction works, the possibility of blocking the access motor road to the object shall be minimised;
c) during construction works and as a result of the completion of construction, the number of existing access motor roads to the Ministry's object shall not be reduced;
d) the territory of the object, including the training ground, shall not fall within the field of view of the object to be built;
e) the safety norms established by Georgian legislation shall be observed (especially around the shooting range on the territory of the object).
4. If construction is planned within a radius of 300 metres from category IV buildings, the following circumstances shall be taken into account when planning construction:
a) construction shall be planned in such a way that it does not hinder the operational movement of units;
b) during the course of construction works, the possibility of blocking the motor road providing access to the facility shall be reduced to a minimum;
c) during the course of construction works and as a result of the completion of construction, the number of existing motor roads providing access to the Ministry's facility shall not be reduced;
d) the territory of the facility shall not fall within the field of view of the facility to be constructed;
e) the safety norms established by the legislation of Georgia shall be observed.
5. If construction is planned within a radius of 100 metres from category V buildings in populated areas, and within a radius of 300 metres in unpopulated areas, the following circumstances shall be taken into account when planning the construction:
a) the construction shall be planned in such a way that it does not impede the prompt movement of the personnel of fire-rescue units and rapid response to an incident;
b) during the course of construction works, the possibility of blocking the motor road providing access to the facility shall be reduced to a minimum;
c) during the course of construction works and as a result of the completion of construction, the number of existing motor roads providing access to the Ministry's facility shall not be reduced, including that the width of the existing road shall not be reduced.
6. If construction is planned within a radius of 100 metres from category VI buildings, the following circumstances shall be taken into account when planning the construction:
a) the construction shall be planned in such a way that it does not impede the prompt movement of the personnel of the relevant units and rapid response to an incident;
b) during the course of construction works, the possibility of blocking the motor road providing access to the facility shall be reduced to a minimum;
c) during the course of construction works and as a result of the completion of construction, the number of existing motor roads providing access to the Ministry's facility shall not be reduced, including that the width of the existing road shall not be reduced.
7. When constructing around category VII and VIII buildings, the relevant requirements established by the legislation of Georgia shall be observed.
Article 4. Preparation of a decision/conclusion by the Ministry🔗
1. In administrative proceedings related to the issuance of construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures, in connection with the approval by the Ministry of the conditions for the use of a land plot for construction and/or the coordination of the architectural project, a decision/conclusion shall be prepared by a commission created in the Ministry (hereinafter – the Commission). The composition and rules of activity of the Commission shall be determined by order of the Minister of Internal Affairs of Georgia.
2. The Commission shall adopt a decision on the issue raised in connection with the approval of the conditions for the use of a land plot for construction no later than 20 working days from the submission of the relevant application and shall submit this decision to the administrative body issuing construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures.
3. Within 10 working days, the Commission shall examine the compliance of the architectural project with the conditions for the use of the land plot for construction and shall prepare the relevant conclusion, which shall be submitted to the administrative body issuing construction permits for objects of special importance (including radiation or nuclear objects) and construction permits for Class II-IV buildings and structures.