On approval of the special rule for the procurement of goods and services by LLC Georgian Airports Association
Text of the document
📑 Contents (21 articles)
On approval of the special rule for the procurement of goods and services by LLC Georgian Airports Association
Government of Georgia
Resolution No. 612
29 December 2025
Tbilisi
On approval of the special rule for the procurement of goods and services by LLC Georgian Airports Association
Article 1🔗
Pursuant to subparagraph „a.h“ of paragraph 1 of Article 3 of the Law of Georgia „On State Procurement“, the attached „Special Rule for the Procurement of Goods and Services by LLC – Georgian Airports Association“ shall be approved.
Article 2🔗
The term of validity of the Resolution shall be determined up to and including 31 December 2026.
Article 3🔗
The Resolution shall enter into force from 1 January 2026. Prime Minister Irakli Kobakhidze Special Rule for the Procurements of Goods and Services by LLC – Georgian Airports Association
Article 1. General Provisions🔗
1. The Special Rule for the Procurements of Goods and Services by LLC – Georgian Airports Association (hereinafter – the Rule) has been developed in accordance with subparagraph „a.h“ of paragraph 1 of Article 3 of the Law of Georgia „On State Procurement“ and establishes the rule for the procurement of goods and services determined by this Rule.
2. The purpose of this Rule is to simplify the procedures for the procurement of services to be performed and goods and to ensure the uninterrupted achievement of the purchaser's objectives.
Article 2. Definition of Terms🔗
The terms used in this Rule have the following meanings:
a) procuring entity – an enterprise which, when procuring goods or services related to the specifics of its activity, is guided by this special rule established by the Government of Georgia for the procurement of goods or services;
b) procurement – procurement by the procuring entity of goods and services defined by the Annex to this Rule;
c) direct procurement – a procurement method used in the cases provided for by Article 4 of this Rule;
d) Unified Electronic System of Public Procurement (hereinafter – the System) – the official public procurement portal provided for by the legislation of Georgia, https://tenders.procurement.gov.ge;
e) electronic procurement procedure – a procurement method for goods and services provided for by the Annex to this Rule, the procedure and conditions for the implementation of which are determined by this Rule (for the purposes of the guarantee of performance of a contract determined by this Rule, the term “tender” may be used);
f) conditions of the electronic procurement procedure (hereinafter – the conditions of the procedure) – information on the procurement provided for by the announcement and documentation on the electronic procurement procedure, as well as the set of conditions/requirements established by the commission in respect of the procurement object and the tenderer;
g) tenderer – a person participating in the electronic procurement procedure;
h) supplier – a person with whom a contract on procurement has been concluded;
i) bid security guarantee – a guarantee mechanism submitted by the tenderer to the procuring entity for the purpose of securing the bid, in the amount of 1% of the estimated value of the procurement object, and in the case of procurement on the basis of a pre-invoice, in the amount of 1% of the contractual value;
j) bid price – the bid price fixed as a result of electronic trading, which the tenderer indicates in the relevant field of the System;
k) bid price reduction step – the amount indicated by the procuring entity in the announcement on the conduct of the electronic procurement procedure, in the amount of 0.4% to 2% of the estimated value of the procurement object (hereinafter – the step);
l) bid – technical documentation submitted by the tenderer in compliance with the requirements of this Rule and in accordance with the conditions determined by the procuring entity in the electronic procurement procedure, for the purpose of participating in the electronic procurement procedure, and the bid price offered by the tenderer through the System, as well as, if available, a sample of the procurement object, an expert opinion, document(s) confirming the adequacy of pricing and/or document(s) reflecting registration/legal data;
m) technical documentation – information on the procurement object and the tenderer uploaded by the tenderer to the System, which is required by the procuring entity in the announcement and documentation;
n) Electronic auction – a component procedure of electronic procurement, during which the tenderer is able, through the system, to reduce the price of the bid submitted by him, for the purpose of winning in the electronic procurement procedure. The electronic auction includes the main time and additional rounds, in accordance with the conditions determined by the system. By decision of the contracting authority, the electronic procedure may be conducted without including additional rounds of the electronic auction;
o) Document reflecting registration/legal data – a document to be submitted from an administrative body, which contains the information required by the conditions of the electronic procurement procedure regarding the legal aspect of the tenderer's status/activity (registration data, legal restrictions, existing financial and other types of obligations, etc.);
p) Commission – a commission staffed, by decision of the contracting authority, from employees of the contracting authority, which carries out the electronic procurement procedure, and is also authorized to adopt a decision on carrying out procurement by direct procurement, in accordance with this rule and the procedure established by the legislation of Georgia;
q) Electronic procurement procedure completed with a negative result – the electronic procurement procedure is considered completed with a negative result when all tenderers participating in the electronic procurement procedure are disqualified;
r) Electronic procurement procedure did not take place – the electronic procurement procedure is considered not to have taken place when no tenderer participated in the electronic procurement procedure;
s) Electronic procurement procedure is terminated – the electronic procurement procedure is considered terminated when the relevant reasoned minutes of the commission's meeting are uploaded by the authorized representative of the contracting authority;
t) Contractual value of the procurement object – in accordance with this rule, the value of the contract to be concluded with the winning tenderer;
u) Black list – the register of unscrupulous persons participating in procurement provided for by the Law of Georgia “On State Procurement”;
v) “CMR” module of the system – the module defined in the system for submitting a report on the progress of contract performance (hereinafter – CMR).
Article 3. Rights and obligations of the purchaser🔗
1. The purchaser is entitled to:
a) in compliance with this rule, select a supplier and conclude a procurement contract with it (hereinafter – the contract);
b) in accordance with this rule, disqualify tenderers;
c) at any time before the conclusion of the contract, by a reasoned decision, terminate the electronic procurement procedure, if this becomes necessary due to objective reasons independent of it and/or unforeseeable in advance, as well as proceeding from the objectives and/or interests of the purchaser's activity;
d) exercise control and supervision over the supplier's performance of the terms of the contract;
e) in accordance with the legislation of Georgia, terminate the contract at any time, if the registration/legal data submitted by the supplier prove to be false, as well as in the presence of other circumstances provided for by the legislation of Georgia and the contract existing between the parties.
2. The purchaser is obliged to:
a) carry out procurement rationally, including economically, productively and efficiently, in compliance with the conditions established by this rule;
b) in accordance with the terms provided for by the contract, reimburse the supplier for the value of the delivered goods and/or services;
c) in the event of termination of the electronic procurement procedure, upload to the system the reasoned minutes of the relevant decision-making meeting. In the event of termination of the electronic procurement procedure, the purchaser is not obliged to reimburse the tenderers for the expenses related to participation in the procurement and/or preparation of the contract;
d) not conclude a contract with a supplier registered in the blacklist.
Article 4. Procurement means🔗
1. The procurement of goods and/or services defined by the annex to this rule shall be carried out by means of the electronic procurement procedure and/or by means of direct procurement.
2. Procurement by the purchaser by means of direct procurement may be carried out if the value of a contract to be concluded at one time for the procurement does not exceed the limits indicated in the annex, excluding value added tax (hereinafter – VAT). The said regulation shall not apply to the relations regulated by Article 6 of this rule.
3. The purchaser is entitled to purchase services related to the transportation of goods together with the goods or independently of them, in the manner established for the procurement of the goods to be transported.
4. The electronic procurement procedure shall be carried out by the purchaser's commission.
Article 5. Conditions for the prevention of a conflict of interest🔗
1. The conditions for the prevention of a conflict of interest apply to the following activities related to procurement:
a) consideration, selection and evaluation of a bid in the electronic procurement procedure;
b) control and supervision over the performance of the contract;
c) selection of a supplier in the case of direct procurement.
2. A person carrying out the activities defined by paragraph 1 of this Article shall have a conflict of interest with a tenderer or supplier if there is a relationship between them provided for by Article 19 of the Tax Code of Georgia.
Article 6. Incentive contract🔗
1. The incentive contract is concluded within the framework of the airport incentive programme and the business plan, between the purchaser and the supplier, which at the same time must be an airline.
2. For the incentivisation of airline basing, the value of the contract shall be determined for each based aircraft in an amount not exceeding 4,000,000 (four million) euros, excluding VAT, in accordance with the number of passengers carried, within the framework of the incentive programme.
3. The purchaser is entitled to conclude a contract in the direction of incentivisation of airline basing with not more than three airlines.
4. Within the framework of the airline basing incentive contract, the supplier, in exchange for the value determined in accordance with paragraph 2 of this Article, shall ensure:
a) in total, the carriage of at least 150,000 (one hundred and fifty thousand) departing passengers by the respective based aircraft, within the next 3 years from the date of performance of the first flight;
b) the addition of at least 1 new destination which has not been served regularly at the respective airport for at least the last 6 months.
5. The value of the new priority destination incentive contract for each priority destination within the framework of the incentive programme shall be determined as follows:
a) for each priority destination of category I, within the next 3 years from the date of performance of the first flight – not more than 600,000 (six hundred thousand) euros, excluding VAT;
b) for each priority destination of category II, within the next 3 years from the date of performance of the first flight – not more than 500,000 (five hundred thousand) euros, excluding VAT;
c) for each priority destination of category III, within the next 3 years from the date of performance of the first flight – not more than 400,000 (four hundred thousand) euros, excluding VAT;
d) for each priority destination of category IV, within the next 3 years from the date of performance of the first flight – not more than 300,000 (three hundred thousand) euros, excluding VAT.
6. Within the framework of the new priority destination incentive contract, the supplier shall ensure:
a) at least 2 frequencies per week on each new priority destination which has not been served regularly at the respective airport for at least the last 6 months;
b) at least 2 frequencies per week on each priority destination within the next 3 years from the date of performance of the first flight.
7. Within the framework of the new priority destination incentive programme, one or several destinations may be determined as a priority destination of each category.
8. The value of the new strategic destination incentive contract for each strategic destination shall be determined in an amount not exceeding 90 (ninety) euros, excluding VAT, per each passenger brought in, within the framework of the incentive programme.
9. Within the framework of the contract for the stimulation of a new strategic direction, the airline shall ensure the operation of at least 2 frequencies per week on the new strategic direction that has not been operated regularly at the relevant airport for at least the last 6 months.
10. Within the framework of the new strategic direction stimulation program, it is possible that several strategic directions exist and/or that such strategic directions be divided into categories and the relevant remuneration be determined for each category, within the limits established by these rules.
11. The contracting authority is entitled to conclude a contract for the stimulation of a new strategic direction for each strategic direction with no more than three airlines for a term of no more than 3 (three) years.
12. The stimulation program shall be public and accessible to all airlines.
13. Stimulation programs shall operate in parallel with the discount concept approved by the contracting authority. Also, a stimulation contract concluded by a decision of the Government of Georgia may be entered into within the framework of the discount concept.
14. The contracting authority shall be obliged to observe the principles of fairness and non-discrimination in the process of relations with suppliers.
15. Proceeding from the content and purpose of the stimulation contract, when concluding such a contract, the submission of a guarantee is not mandatory, notwithstanding the requirement established by paragraphs 6 and 7 of Article 17 of these rules.
16. By ordinance of the Government of Georgia, in certain cases, a stimulation contract may be entered into under rules and conditions different from these rules.
Article 7. Procurement planning🔗
1. The procurement of goods and services determined by the annex to these rules shall be carried out in accordance with these rules, in accordance with a pre-defined plan approved by a decision of the head of the contracting authority.
2. The plan provided for by paragraph 1 of this Article shall be registered in the system and shall contain:
a) the name of the procurement object;
b) the estimated value of the procurement;
c) the procurement method;
d) the period of procurement implementation (indication of the relevant quarter);
e) the source of funding.
3. Before the implementation of each procurement, it is mandatory to conduct market research, which, in turn, shall be carried out in accordance with the legislation in force in the field of public procurement, recommendations and methodological instructions.
Article 8. Rules for the establishment and operation of the Commission🔗
1. The electronic procurement procedure is determined and conducted by the Commission, which is established with a composition of no fewer than three members by the head of the procuring entity.
2. The Commission acts on behalf of the procuring entity.
3. The Commission is chaired by the head of the procuring entity or a person appointed by the head.
4. On the basis of a decision of the Commission, specialists in the relevant field may be invited as experts and consultants.
5. The Commission adopts a decision by a majority of the total number of members. In the event of an equal division of votes, the vote of the chairperson of the Commission shall be decisive. The decision of the Commission shall be reflected in the minutes of the meeting, which shall be signed by all members of the Commission present at the meeting. A member of the Commission who does not agree with the decision of the Commission has the right to submit his/her opinion in writing, which must be attached to the decision of the Commission.
6. Any decision of the Commission shall be reflected in the minutes of the relevant meeting of the Commission. The minutes shall be uploaded to the system immediately upon signature. The minutes uploaded to the system may be changed only by cancelling the minutes already uploaded to the system and uploading the changed minutes to the system.
7. Any correspondence/written notification between the procuring entity and the tenderer shall be sent through the relevant module of the system.
Article 9. Commission's Apparatus🔗
1. For the purpose of technical and organizational support of the Commission's activity, by a decision of the head of the procuring entity, the Commission's apparatus (hereinafter – the apparatus) is established with the composition of the procuring entity's employees, which is headed by the chairperson of the Commission.
2. The function of the apparatus is to ensure the announcement on the conduct of the electronic procurement procedure, the documentation and any organizational matter related to the course of the procurement.
3. The apparatus has the right to provide tenderers with information and explanations related to the electronic procurement procedure.
4. The apparatus shall ensure the storage of any document and information material related to the conduct of each electronic procurement procedure for not less than 10 years from the conclusion of the contract.
Article 10. Notice on conducting the electronic procurement procedure🔗
1. The completion and posting of the notice on conducting the electronic procurement procedure (hereinafter – the notice) shall be carried out through the system.
2. The period for reviewing the notice and documentation shall be not less than 3 (three) working days from the moment of posting the notice and documentation in the system. Within not less than 3 (three) days after the expiry of this period, the tenderer may submit a bid through the system and, by way of electronic auction, change the price of the submitted bid according to the descending principle and taking into account the step.
3. The notice shall indicate the following information:
a) notice number;
b) name of the procuring entity;
c) date of announcement, indicating the exact time;
d) date of commencement and completion of receipt of bids, indicating the exact time;
e) estimated value of the procurement object (if the electronic procurement procedure is conducted on the basis of a pre-contract – indication of the estimated value of the pre-contract and the contractual value of the procurement object);
f) indication as to whether the bid shall be submitted with or without VAT;
g) quantity or volume of the procurement object;
h) delivery period of the procurement object;
i) amount of the step.
4. The notice has an additional information field, which may be used by the authorized representative of the procuring entity for the purpose of providing an additional description of the procurement object or additional information related to the electronic procurement procedure.
5. For posting the notice in the system, it is necessary to upload the documentation in the system.
Article 11. Placement of the documentation of the electronic procurement procedure in the system and amendment of the documentation🔗
1. The documentation of the electronic procurement procedure shall contain:
a) the list of documents reflecting the registration/rights data that the tenderer must satisfy (if any);
b) the quantity of the goods to be purchased, the volume of the service, the term, place and form of delivery of the goods or provision of the service;
c) a full description of the technical, performance and/or functional specifications of the procurement object, including plans, drawings, sketches (if any), information on quality, functioning, safety, dimensions, packaging, marking and labelling, production method and process, symbols, terms, compliance requirements established by the purchaser, and others;
d) the methods by which the value of the bid shall be calculated, indicating whether, in addition to the value of the goods or service, it shall also include other expenses (transportation, insurance, taxes and others);
e) an indication on the submission of a sample, an expert opinion and/or document(s) confirming the adequacy of pricing (if any);
f) information on the warranty period and conditions of the procurement object (if necessary);
g) an indication on the 1% guarantee of the bid (if any);
h) the identity and contact information of the member of the commission's staff who is entitled to provide information and explanations regarding the electronic procurement procedure.
2. The commission is entitled, before the start of the bid acceptance time, to amend the data indicated in the notice and the documentation. Amendment of the documentation may be made by cancelling the documentation and uploading the amended documentation into the system. Amendment of the procurement object shall be inadmissible.
Article 12. Technical requirements for the tenderer and rules for describing the procurement object🔗
1. The procuring entity is entitled, in each specific case, to determine the requirements that the tenderer and the procurement object must meet.
2. Requirements for tenderers may be established for the purpose of assessing their knowledge, experience, reliability, financial and technical capabilities.
3. The procuring entity is entitled to require the submission of document(s) reflecting registration/legal data if the estimated value of the procurement is equal to or exceeds GEL 200,000. If the estimated value of the procurement is less than GEL 200,000, the requirement to submit document(s) reflecting registration/legal data shall be permissible only in exceptional cases, which must be substantiated under the conditions of the electronic procurement procedure. In such a case, the number of documents reflecting registration/legal data must be minimal, based on the specifics of the specific procurement.
4. The commission shall, when describing the technical, performance and/or functional specifications of the procurement object, match the textual materials and other indicators used to international or Georgian standards. The commission shall indicate the relevant standard used (if any). It is inadmissible to indicate a trademark, patent, model, source of origin or manufacturer, except in the case where no other means of precise description of the procurement object exists. In such a case, the term "similar" or "equivalent" and others must necessarily be used in the description.
5. The procuring entity shall determine in the documentation the obligation and deadline for submitting a sample of the procurement object. Failure by the tenderer to submit a sample or its non-compliance with the requirements of the application and/or documentation or with the technical documentation submitted by the tenderer through the system shall result in his/her disqualification, on the basis of subparagraph "c" of paragraph 1 of Article 16 of these Rules. A sample of the procurement object submitted by the tenderer shall not be subject to clarification. The sample of the procurement object shall be returned to the tenderer within a reasonable time, except in cases where the sample is a perishable thing and/or its return is impossible due to its nature.
Article 13. Submission of a bid🔗
1. In order to participate in the electronic procurement procedure, the tenderer may submit a bid from the stage of commencement of the bid acceptance period until the end of the bid acceptance period.
2. Before submitting a bid, any person has the right to review the notice and the documentation in the system.
3. A bid may be submitted only through the system. All documents determined by the conditions of the electronic procurement procedures shall be uploaded by the tenderer.
4. After uploading the documents provided for by paragraph 3 of this Article, the tenderer shall indicate in the relevant field of the system the bid price, which shall not exceed the estimated value of the procurement object and/or shall be less than the estimated value of the procurement object by at least one step. After uploading the technical documentation and indicating the bid price, it shall be inadmissible to change, add to, cancel or delete the uploaded technical documentation.
5. In the event that the notice provides for submission of the bid price without VAT, the tenderer shall not take VAT into account in the bid price, regardless of whether or not it is a VAT payer, in accordance with the legislation of Georgia. In such case, the selection-evaluation shall be carried out according to the prices of the submitted bids. The purchaser shall be obliged to take into account in the contract value the amount corresponding to the VAT of the bid price, if at the moment of conclusion of the contract the tenderer is a VAT payer, in accordance with the requirements of the legislation of Georgia.
Article 14. Bid security guarantee🔗
1. The tenderer shall be obliged, together with the technical documentation, to submit a bid security guarantee, in one of the manners and forms indicated below:
a) by payment of the amount to the bank account determined by the conditions of the procedure and submission of the receipt confirming the same together with the technical documentation;
b) by a bank guarantee, which shall be submitted from a banking/insurance institution licensed in accordance with the legislation of Georgia.
2. The beneficiary of the bid security guarantee is the purchaser.
3. If the estimated value of the procurement is less than GEL 50,000, the purchaser is entitled not to require a bid security guarantee.
4. The bid security guarantee shall be subject to return in the case of conclusion of the relevant contract, completion of the electronic procurement procedure with a negative result, or termination, within no later than 10 (ten) working days from the occurrence of any of the results.
5. The bid security guarantee submitted by the tenderer shall not be subject to return if the disqualification of the relevant tenderer was carried out on the basis of subparagraphs „b“, „f“ or „g“ of paragraph 1 of Article 16 of these Rules.
Article 15. Selection/Evaluation🔗
1. The tenderer's bid shall be evaluated after completion of the electronic trading stage.
2. If two or more tenderers have indicated in the system the same lowest bid price, preference shall be given to the tenderer that was the first to indicate the lowest bid price.
3. The commission shall consider whether the technical documentation of the tenderer with the lowest bid price complies with the conditions of the procedure. If the technical documentation uploaded in the system by the tenderer does not comply with the requirements specified in the tender notice and documentation, by decision of the commission, the tenderer shall be disqualified, except for the cases provided for by paragraph 4 of this Article.
4. The commission shall not disqualify the tenderer if its technical documentation does not contain such data and/or contains such inaccuracy/inaccuracies, the submission and/or clarification of which will not cause a material change to the technical documentation and/or will not increase the bid price.
5. If the entire technical documentation is uploaded in the system as a defective file (which cannot be read), the commission shall not be entitled to address the tenderer with a request for clarification of the technical documentation, except for the case where such part of the technical documentation is defective, the submission and/or clarification of which will not cause a material change to the technical documentation and/or will not increase the bid price.
6. In the cases provided for by paragraphs 4 and 5 of this Article, the contracting authority shall address the tenderer with a request for clarification of the technical documentation submitted by it, for which it shall set a reasonable period, but not more than three working days. If the submitted documentation is not clarified within the said period, the commission shall disqualify the tenderer.
7. If the technical documentation uploaded in the system by the tenderer with the lowest bid price, as well as, in the case of a request, the document reflecting registration/legal data, complies with the requirements specified in the tender notice and documentation, the request by the contracting authority for clarification of the cost estimate and/or price table shall be made together with the request for submission of the performance guarantee for the contract (if any) and the invitation to conclude the contract.
8. The submission by the tenderer to the contracting authority of both the tender bid and the clarified technical documentation and documents confirming registration/legal data shall be made through the system.
Article 16. Disqualification of a tenderer🔗
1. A tenderer shall be subject to disqualification if:
a) it is registered in the blacklist;
b) it refuses the bid or otherwise expresses refusal to enter into the contract;
c) its technical documentation does not comply with the conditions defined by the notice and documentation of the electronic procedure;
d) it does not clarify the technical documentation within the established time limit, clarifies it incompletely and/or as a result of the clarification substantially changes it;
e) it does not submit a sample, expert opinion and/or document(s) confirming the adequacy of pricing within the established time limit, or the sample, expert opinion and/or document(s) confirming the adequacy of pricing submitted by it do not comply with the conditions of the procedure;
f) it does not submit document(s) reflecting registration/legal data within the established time limit and/or the registration/legal data and/or document(s) reflecting registration/legal data do not comply with the conditions of the procedure;
g) for the purpose of obtaining the right to enter into the contract, commits an unfair act.
2. If, by the time of expiry of the bid deadline, a tenderer does not have a bid security guarantee submitted in full compliance with the requirements, the tenderer's offer shall not be considered and the Commission may apply to the next tenderer with the lowest bid price.
3. In the event of disqualification of the tenderer with the lowest bid price, the Commission, in accordance with the established procedure, shall evaluate the next tenderer with the lowest bid price (if any) or is entitled to adopt a decision on termination of the electronic procurement procedure, if the bid price of the next tenderer, as a result of changed circumstances on the market, significantly exceeds the market value of the object of this procurement.
Article 17. Contract and documentation to be uploaded in the system🔗
1. In accordance with this rule, purchases carried out as a result of both the electronic procedure and direct procurement, concluded contracts and information and/or documents on related actual payments and the progress of contract performance shall be uploaded in the system no later than 10 days from their preparation.
2. A contract concluded on the basis of direct procurement, documents related to the conclusion of the contract, document(s) reflecting the amendment of this contract, as well as documentation confirming the performance/non-performance of the contract shall be uploaded in the relevant field of the CMR module of the system.
3. In accordance with this rule, on the basis of the conditions and documentation determined by the bid of the winning tenderer in the electronic procurement procedure, a contract shall be concluded between the winning tenderer and the purchaser, which shall be uploaded in the system.
4. The value of the contract may not exceed the final price of the bid fixed by the winning tenderer as a result of electronic trading, except for the case provided for by paragraph 5 of Article 13 of this rule, when the purchaser includes in the value of the contract the amount of the corresponding VAT on the price of the bid.
5. The contract may be concluded in both Georgian and a foreign language. In the case of concluding the contract in a foreign language, it shall, in accordance with the procedure established by the legislation of Georgia, be translated into Georgian. The contract does not need translation if it is concluded as a single document in parallel in Georgian and a foreign language.
6. If the value of the contract amounts to or exceeds GEL 200,000, the purchaser is entitled to require a guarantee of performance of the contract, in the amount of 2% to 10% of the value of the contract.
7. If the final price of the bid fixed by the winning tenderer as a result of electronic trading in the electronic procurement procedure or the value of the contract to be concluded in direct procurement is less than GEL 200,000, it shall be inadmissible to require the tenderer/supplier to submit a guarantee of performance of the contract, except for the case when the purchaser has substantiated what particularity of the procurement object gave rise to the requirement of the guarantee.
8. The guarantee of performance of the contract concluded as a result of the electronic procurement procedure shall be submitted before the conclusion of the contract, while in direct procurement the guarantee of performance of the contract may be submitted to the purchaser after the conclusion of the contract, no later than 10 days. In the case of failure to submit the guarantee, the purchaser is entitled to terminate the contract.
9. In the case of advance settlement, if within the framework of a single procurement the amount of the advance payment exceeds GEL 20,000 including VAT, the supplier is obliged to submit to the purchaser a guarantee in an amount identical to the advance payment, under the conditions provided for by the contract.
10. The rule for reviewing the terms of a contract concluded with a supplier shall be determined by the legislation of Georgia.
11. The conclusion of a contract shall not be mandatory in the case of direct procurement effected by means of online ordering, in which case the contract may be replaced by a document confirming payment by means of the internet.
Article 18. Conducting an electronic procedure on the basis of a pre-invoice🔗
1. Procurement through an electronic procedure may be carried out on the basis of a pre-invoice.
2. In the case provided for by paragraph 1 of this Article, the purchaser shall indicate, in the field for the estimated value of the pre-invoice of the electronic procedure notice, the estimated value of the pre-invoice, and in the field for the contractual value of the procurement object — the contractual value of the procurement object, which may differ from the value of the pre-invoice.
3. The price of a bid submitted by a tenderer through the system shall not exceed the estimated value of the pre-invoice, and, as a result of electronic trading, a reduction in the bid price may be effected only in relation to the estimated value of the pre-invoice.
4. When conducting an electronic procedure on the basis of a pre-invoice, the commission shall itself determine, in the documentation of the electronic procedure, the rule for determining the value of the units of the procurement object given in the pre-invoice in relation to the final price of the bid submitted by the winning tenderer through the system.
5. In the case provided for by this Article, if, after the conclusion of the contract, any unit of the procurement object is absent from the pre-invoice, the price of that unit, where its procurement is necessary, shall be determined by agreement between the purchaser and the supplier, taking into account the market price. In such a case, the share of the procurement caused by the absence of the relevant unit from the pre-invoice may not exceed 10% of the final total value of the pre-invoice recorded by the supplier as a result of the electronic trading.
Annex
List of goods and services to be procured by LLC – Georgian Airports Association in accordance with these rules
No.
Software/proper functioning of systems
the total value of a contract to be concluded as a one-off by direct procurement of licences/software for individual programmes, systems and web services introduced in the company (including: licences/software for accounting, financial, training, airport operation-related systems, licences/software for computer programmes, programmes required for aerodrome communication, including discrete communication and the proper functioning of closed and open networks) shall not exceed GEL 200,000.00. By direct procurement, a contract may be concluded only with non-resident legal and natural persons 1 support) updates, licences, additional modules, physical devices, training related to their use and certification of the relevant personnel, programme operation management and technical support services. Also, licences for information exchange related to airport development and operation (API PNR systems, personal information about the passenger and a.y.), analytical systems (statistical, commercial) and access to modules/databases.
No.
Training and professional development of personnel
1
Trainings (theoretical and practical) for improving the professional skills of the company's employees and raising aviation professional qualifications, the necessary training materials, including specialised professional training and retraining related to airport operations and the implementation of aviation security.
The total value of a contract to be concluded on a one-off basis by means of direct procurement shall not exceed 50000.00
2
Specialised literature and international and local normative materials or their collections, in both printed and electronic form.
GEL. A contract may be concluded by means of direct procurement only with non-resident legal entities and natural persons
№
Consulting services
1
Aviation audit services (ISAGO, ACI, IATA, ICAO, FAA, TSA and other international specialised audit services) for the purpose of maintaining and developing airport quality, the periodic conduct of which is necessary for the functioning of LLC Georgian Airports Association and the airports within its ownership in accordance with international standards.
The total value of a contract to be concluded on a one-off basis by means of direct procurement shall not exceed GEL 200000.00. A contract may be concluded by means of direct procurement only with non-resident legal entities and natural persons
2
Consulting services in the field of aviation, airport planning, development, design, operation, aviation security, airport management, technical, economic and commercial research and optimisation, flight safety and other types of intellectual activity.
№
Airport operations
1
Second-hand special machinery necessary for ensuring aviation security and fire-rescue safety; second-hand special machinery for aircraft ground handling, servicing of aerodromes and infrastructure; as well as units, devices and tools necessary for the servicing and/or maintenance of special machinery available at airports.
The total value of a contract to be concluded on a one-off basis by means of direct procurement shall not exceed 200000.00
2
Servicing, repair, spare parts, consumables of special equipment (including special machinery) necessary for passenger check-in, transportation and servicing, baggage management, aircraft servicing, aerodrome operation, flight operations, fire-rescue, operation quality management and safety, airport operation monitoring, implementation of aviation security.
GEL.
№
Maintenance of airport infrastructure
1
For the proper and uninterrupted functioning of the airports included in LLC Georgian Airports Association, repair of existing systems (fire safety, power supply, water supply, heating and cooling, low-voltage, aviation security and other similar critical systems), goods and services necessary for technical servicing.
The total value of a contract to be concluded on a one-off basis by direct procurement shall not exceed GEL 20,000.00.
2
Services and goods necessary for the proper and uninterrupted functioning of the baggage handling system existing at Kutaisi International Airport named after David the Builder, included in the Airports Union of Georgia.
The total value of a contract to be concluded on a one-off basis by direct procurement shall not exceed GEL 100,000.00. A contract may be concluded by direct procurement only with non-resident legal and natural persons
№
Development of airports and air routes
Direct
procurement
by means of
1
Marketing services for ensuring the growth of air routes, frequencies and/or passenger traffic at Georgian airports.
Total of a contract to be concluded on a one-off basis
value
not exceeding 200,000.00
GEL.