On Approval of the Procedure for Acceptance of Completed Road Works (Except Construction, Modernization and Reconstruction) on Motor Roads of International and Domestic Importance
Text of the document
📑 Contents (16 articles)
Minister of Infrastructure of Georgia
Order No. 22/n
11 March 2026
Tbilisi
On Approval of the Procedure for Acceptance of Completed Road Works (Except Construction, Modernization and Reconstruction) on Motor Roads of International and Domestic Importance
Pursuant to Article 26 of the Law of Georgia “On Motor Roads” and subparagraph “t” of paragraph 3 of Article 7 of the Regulation approved by Resolution No. 133 of the Government of Georgia of 30 April 2025 “On Approval of the Regulation of the Ministry of Infrastructure of Georgia”, I order:
Article 1🔗
The Procedure for Acceptance of Completed Road Works (Except Construction, Modernization and Reconstruction) on Motor Roads of International and Domestic Importance shall be approved.
Article 2🔗
The Order shall enter into force upon publication. Minister of Infrastructure of Georgia Revaz Sokhadze
Procedure for Acceptance of Completed Road Works (Except Construction, Modernization and Reconstruction) on Motor Roads of International and Domestic Importance
Article 1. General Provisions🔗
1. The Procedure for Acceptance of Completed Road Works (Except Construction, Modernization and Reconstruction) on Motor Roads of International and Domestic Importance (hereinafter – the Procedure) regulates the procedure for acceptance of completed road (except construction, modernization and reconstruction) and bank protection/bank restoration works on motor roads of international and domestic importance.
2. The Procedure shall not apply to the acceptance of those road works whose acceptance procedure is determined by Resolution No. 257 of the Government of Georgia of 31 May 2019 “On the Procedure for Issuing a Construction Permit and Permit Conditions for Objects of Special Importance (Including Radiation or Nuclear Objects)”.
3. In accordance with this Procedure, the works included in the concept of a motor road and carried out for the purpose of arranging its constituent parts, bank protection/bank restoration works, and works for the elimination and prevention of the consequences of natural and other force majeure events shall be accepted.
Article 2. Definitions of terms🔗
For the purposes of this Rule, the terms defined therein have the following meaning:
a) motor road – the concept of a motor road is defined in accordance with the Law of Georgia on Motor Roads;
b) journal of laying of asphalt-concrete mixture – a document reflecting the name of the road work, volumes, pavement structure, laying and compaction technology, climatic conditions and periodic description of the condition;
c) laboratory conclusion on asphalt-concrete and cement-concrete mixtures, as well as samples taken from the pavement – a document reflecting the physical-mechanical and chemical indicators of asphalt-concrete and cement-concrete mixtures, as well as samples taken from the pavement, and their compliance with the requirements of construction norms and rules;
d) protocol of laboratory tests of used construction materials – compliance of the physical-mechanical and chemical characteristics of materials used in road works with the requirements of standards;
e) acceptance of completed works – issuance by the supervisor of a certificate of acceptance of completed works;
f) completed work – completed work of the first, second or third category;
g) Department – the state sub-agency institution under the authority of the Ministry of Infrastructure of Georgia – the Roads Department of Georgia;
h) laboratory – an organization accredited in accordance with the legislation of Georgia by the Legal Entity of Public Law – the Unified National Accreditation Body – the Accreditation Centre, which, in the cases established by this Rule, carries out laboratory tests, examinations and measurements;
i) control journal of earth embankment compaction – a document reflecting the technological description of the construction of the earth embankment – indicating design elevations, location, layer height, thickness of the layer to be compacted, physical-mechanical properties of the soil, and types of compaction machines and mechanisms;
j) object – a specific motor road / section of a motor road / component part of a motor road included in the concept of a motor road, or the shore of the sea/water reservoir or the riverbed, on which road or shore protection/shore restoration work is carried out;
k) mix design for the preparation of asphalt-concrete and cement-concrete – the designed composition of the asphalt-concrete mixture used in road and shore protection/shore restoration works, the components required for preparing 1 t/1 m3 of the mixture and their physical-mechanical indicators, which must comply with the relevant construction norms and rules;
l) supervisor – a natural or legal person of Georgia or a foreign country which, in accordance with the legislation of Georgia, has concluded a contract with the Department and on its basis provides supervisory services for the performance of the relevant work;
m) design organization – a natural or legal person of Georgia or a foreign country, which, in accordance with the legislation of Georgia, has concluded a contract with the Department and on its basis carries out/carried out the preparation of design documentation necessary for the relevant work;
n) road work – road works provided for by the technical regulation approved by Resolution No. 172 of the Government of Georgia of 10 April 2013 “On approval of the technical regulation on classification of road works on motor roads of Georgia”, except for construction, reconstruction and modernization;
o) work production log – a systematic description of the methods of performance of the relevant work, the commencement and completion of the relevant types of work of the first, second or third category, their volumes, production conditions, the supervisor’s remarks and their correction, quality and their general condition;
p) force majeure – natural disaster, landslide, flood, epidemic, war, uprising, quarantine, imposition of an embargo on the supply of goods, sharp reduction of budget allocations, public disorder, changes in legislation and irresistible force or such an event, the prior determination or avoidance of which exceeded the capabilities of the parties. Irresistible force is events on the origin and development of which the parties cannot exert influence;
q) contractor – a natural or legal person of Georgia or a foreign country, which, in accordance with legislation, has concluded a contract with the Department on the performance of work of the first, second or third category;
r) certificate of conformity (passport) for a factory-manufactured structure – a document issued by the manufacturing plant confirming the characteristics of the structure;
s) payment card for completed works – a document for payment for road or coast protection/coast restoration work performed by the contractor, provided for by the terms of the contract concluded between the Department and the contractor, which is drawn up and confirmed by signature jointly by the contractor and the supervisor. The said document constitutes, for the Department (on the basis of other attached documentation), one of the grounds for settlement with the contractor;
t) act of acceptance of completed works – a document which includes a list of completed works (names), volume, indicating the unit and total value of the works;
u) act of hidden works – confirmation of hidden works performed in accordance with the current construction norms and rules, as well as design requirements, for road or coast protection/coast restoration work, with the requirement to continue the performance of works of the next stage of the technological cycle.
Article 3. Categories of works🔗
For the purposes of this Rule, works, according to their complexity and purpose, are divided into the following categories:
a) First category – works carried out for the purpose of rehabilitation of the motor road, periodic repair, and arrangement of its constituent parts included in the concept of the motor road;
b) Second category – works of current repair of the motor road;
c) Third category – shore protection/shore restoration works and works for the liquidation and prevention of the consequences of natural and other force majeure events.
Article 4. Mandatory documentation to be submitted for acceptance of completed first category works and acceptance of works🔗
1. Within no later than 2 working days from the day of completion of first category works, the contractor shall provide the supervisor and the department with written information on the completion of the works.
2. Within one calendar month from the completion of the works, the contractor shall apply to the supervisor requesting the issuance of a certificate of acceptance of completed works and shall submit a report on the completed works.
3. The report on completed first category works shall include:
a) information on the full name of the facility, with a general overview of the facility and indication of the main characteristic indicators;
b) the final act of acceptance of performed works;
c) the work execution log;
d) the act of hidden works;
e) the mix design for preparation of asphalt concrete and cement concrete;
f) the laboratory test conclusion of used construction materials;
g) the log of laying of asphalt concrete mixture;
h) the laboratory conclusion of asphalt concrete and cement concrete mixture, as well as samples taken from the pavement;
i) certificate(s) of conformity (passport(s)r) for factory-made structures;
j) the laboratory conclusion on the compaction coefficient of the earth embankment;
k) the list of returnable and actually existing construction materials and structures provided for by the design documentation.
4. The supervisor shall be entitled, in addition to the documents provided for by paragraph 3 of this article, to additionally request from the contractor other documents, if necessary.
5. The supervisor, after studying the report on completed first category works submitted by the contractor, shall study on site the compliance of the submitted document (report) with the performed first category works and the design documentation/defect list.
6. Except for the case provided for by paragraph 9 of this article, the supervisor, within no later than 10 working days from the submission of the request by the contractor in accordance with paragraph 2 of this article, shall issue a certificate of acceptance of completed works and shall confirm the final act of acceptance of performed works, which shall be submitted to the department within 5 working days. The certificate confirms the acceptance of completed works and its compliance with the design documentation/defect list.
7. The contractor and the supervisor shall be responsible for the correctness of the certificate of acceptance of completed works.
8. The certificate of acceptance of completed works shall be considered issued immediately upon signature by the authorized person. The certificate of acceptance of completed works shall reflect the dates of completion of the works and its entry into force (signature by the authorized person).
9. The deadline for issuing the certificate provided for by paragraph 6 of this article may be extended by the supervisor, of which the department shall be notified within the 10-day period provided for by paragraph 6 of this article.
10. In accordance with the rule established by paragraph 6 of this article, together with the certificate, the supervisor shall submit to the department the documentation provided for by paragraph 3 of this article, including the act of inventory and storage of materials.
Article 5. Acceptance of second category works🔗
1. For the purpose of acceptance of second category works, the supervisor shall submit to the department the act of acceptance of completed works issued by the supervisor and the remuneration card for completed works.
2. After the submission by the supervisor of the act of acceptance of completed works and the remuneration card for completed works, the structural subdivision of the department that monitors current repair works shall submit to the relevant structural subdivision the act of acceptance of completed works and the remuneration card for completed works for the purpose of remuneration.
Article 6. Acceptance of completed works of the third category🔗
1. Acceptance of third category works shall be carried out in accordance with Article 4 of these Rules, taking into account the exception established by this article.
2. For the purpose of acceptance of third category works, the report defined by paragraph 3 of Article 4 of these Rules shall include:
a) information on the full name of the object, with a general overview of the object and indication of the main characteristic indicators;
b) the latest act of acceptance of completed works;
c) the work execution log;
d) the act of hidden works;
e) the recipe for preparation of asphalt concrete and cement concrete (if necessary, if provided for by the project);
f) the laboratory conclusion on samples taken from the used concrete mixture (if available);
g) the log of asphalt concrete laying (if necessary, if provided for by the project);
h) the laboratory conclusion on the asphalt concrete and cement concrete mixture, as well as on samples taken from the pavement (if necessary, if provided for by the project);
i) conformity certificates (passports) for factory-made structures (if available);
j) the laboratory conclusion on the compaction coefficient of the earth embankment (if there are works of a similar type);
k) the act of acceptance and transfer of actually existing materials to be returned as provided for by the project.
Article 7. Confirmation of performed works of the first and third categories in the event of termination of a contract concluded between the Department and the contractor🔗
1. In the event that a contract concluded between the Department and the contractor is terminated, confirmation of works of the first or third category shall be carried out in accordance with the actually performed works.
2. In the event of termination of a contract concluded between the Department and the contractor, the supervisor shall, within 10 working days from the termination of the contract, apply to the Department and submit the act of confirmation of the actually performed works concluded with the contractor, the inventory list and the payment card for the performed works.
3. In the case provided for by paragraph 1 of this article, if the contract provides for withholding of funds for the purpose of ensuring quality protection, in the absence of defect(s) in the performed works of the first or third category in accordance with the act of confirmation of actually performed works, the inventory list and the payment card submitted by the supervisor to the Department, half of the amount withheld for the purpose of ensuring quality protection shall be returned in full to the contractor, and the second half of the amount withheld for the purpose of ensuring quality protection shall be returned to the contractor after the expiry of the warranty period from the issuance of the act of confirmation of actually performed works concluded with the contractor, the inventory list and the payment card for the performed works, in the absence of defect(s) in the works performed by the contractor.
4. In the case provided for by paragraph 1 of this article, in the presence of defects in the performed works of the first or third category, the amount withheld for the purpose of quality protection shall not be returned to the contractor at all.
5. In the event that defects are found in the performed works and the amount of funds provided for by paragraph 3 of this article is insufficient for the elimination of the defect(s), for the purpose of reimbursement of additionally incurred expenses, the Department is entitled to withhold the additionally incurred expenses from other amounts receivable by the contractor from the Department (if any).
Article 8. Special conditions to be taken into account for the purpose of acceptance of works carried out for the purpose of liquidation and prevention of the consequences of natural phenomena🔗
1. The acceptance of works carried out for the purpose of liquidation and prevention of the consequences of natural phenomena shall be carried out in accordance with Article 4 of this Rule, taking into account the exception(s) established by this Article.
2. When accepting works carried out for the purpose of liquidation and prevention of the consequences of natural phenomena, the amount withheld for the purpose of ensuring quality compliance shall not be withheld from the contractor, except where, given the type of work, the foregoing is not determined by the relevant contract.
3. In the event that, before the acceptance of works carried out for the purpose of liquidation and prevention of the consequences of natural phenomena, force majeure events developed at the site, the remuneration of the works performed by the contractor who perished as a result of the force majeure events shall be effected in accordance with the works actually performed, on the basis of the act of acceptance of completed works (Form No. 2) and the card of remuneration for completed works submitted by the supervisor to the Department before the development of the force majeure events.
4. Regarding the force majeure event defined in paragraph 3 of this Article, there shall be a certificate issued by the relevant administrative body/institution.
Article 9. Acceptance of road and coast protection/coast restoration works in the event of the development of force majeure events🔗
1. In the event of the development of force majeure events in the course of road and/or coast protection/coast restoration works, the remuneration of the works performed by the contractor who perished as a result of the force majeure events shall be effected according to the works actually performed, on the basis of the confirmed act of acceptance of completed works (Form No. 2), the inventory record and the card of remuneration for completed works submitted by the supervisor to the Department before the development of the force majeure events.
2. In the case provided for by paragraph 1 of this Article, the amount withheld for the purpose of ensuring quality compliance shall be fully reimbursed to the contractor.
3. Regarding the force majeure event defined in paragraph 1 of this Article, there shall be a certificate issued by the relevant administrative body/institution.
Article 10. Additional conditions for the acceptance of works🔗
1. Conditions different from this Rule for the acceptance of works may be established, taking into account the specifics of the work, by a contract concluded between the Department and the contractor.
2. The supervisor shall, on the instruction of the Department, submit an act of inventory of the works in accordance with the annex to this Rule.
Article 11. Acceptance of works carried out on motor roads of local importance🔗
In accordance with the instruction of the Government of Georgia, in the case of the performance by the Department of works of the first, second or third category defined by this Rule on motor roads of local importance, their acceptance shall be carried out in accordance with this Rule.
Article 12. Acceptance of works performed within the framework of projects financed by international financial institutions and donor organizations🔗
Within the framework of projects financed by international financial institutions and donor organizations, in the case of performance of works of the first, second or third category, their acceptance shall be carried out in accordance with the procedure defined by the respective contract, and the operation of this procedure shall not extend to them.
Article 13. Forms of documents🔗
The forms of certain documents defined in this procedure shall be determined in accordance with the annex to this procedure:
a) form of the work execution log (Annex No. 1);
b) form of the concealed works report (Annex No. 2);
c) form of the asphalt-concrete mixture laying log (Annex No. 3);
d) log of sampling and testing of specimens cut from the asphalt-concrete pavement (Annex No. 4);
e) card of remuneration for performed works (Annex No. 5);
f) certificate of acceptance of completed works (Annex No. 6);
g) report of acceptance of performed works (Annex No. 7);
h) report of inventory of works (Annex No. 8);
i) report of inventory and storage of materials (Annex No. 9).
Article 14. Transitional provisions🔗
1. With respect to those works performed/ongoing within the framework of contracts existing before the entry into force of this procedure, which have not been accepted by the commission procedure defined by the respective contract, the operation of the procedure shall extend, in the case of mutual agreement with the respective persons within the framework of the contractual relationship.
2. With respect to those works performed within the framework of contracts existing before the entry into force of this procedure, which are completed and have not been accepted by the commission procedure defined by the respective contract, due to defects at the site, in the case of mutual agreement with the supervisor within the framework of the contractual relationship, the supervisor shall issue a certificate of completion of works, taking into account the actual satisfactory operational condition existing at the site. In this case, the date of entry into force of the certificate shall be indicated in the certificate as the date of completion of works. The aforementioned shall be considered as acceptance of the performed works.