Government of Georgia

Resolution No. 239

29 May 2026

Tbilisi

On Approval of the Rules and Conditions for the Implementation of Centralised Procurement

Article 1🔗

Pursuant to paragraph 1 of Article 6 of the Law of Georgia „On the Structure, Powers and Rules of Activity of the Government of Georgia“ and subparagraph „b“ of paragraph 1 of Article 2 of the Law of Georgia No. 1056-IVms-XImp of 12 November 2025 „On Amending the Law of Georgia „On State Procurement““, the following shall be approved:

1. „The Rules and Conditions for the Implementation of Centralised Procurement“.

2. The form and conditions of the affidavit (Annex).

Article 2🔗

The Resolution shall enter into force from 1 June 2026.

Prime Minister Irakli Kobakhidze

The Rules and Conditions for the Implementation of Centralised Procurement

Article 1. Scope of Application🔗

1. The “Rules and Conditions for the Implementation of Centralized Procurement” (hereinafter – the Rule) has been developed on the basis of the Law of Georgia on Public Procurement (hereinafter – the Law), and its purpose is the regulation, inspection and control of activities related to the conduct of centralized procurement.

2. Within the framework of centralized procurement, the LEPL – Central Purchasing Body (hereinafter – the Central Purchasing Body) shall ensure the conduct of a consolidated tender for the procurement of homogeneous procurement objects determined by the Government of Georgia and/or for the implementation of the procurement whose value equals or exceeds the monetary thresholds established by the Government of Georgia.

3. The range of procuring organizations for which the operation of the consolidated tender is mandatory shall be determined by a legal act of the Government of Georgia and/or the tender documentation of the relevant consolidated tender.

4. The procuring organizations provided for by paragraph 3 of this Article shall be obliged to carry out the public procurement determined in accordance with paragraph 2 of this Article only through a consolidated tender, from the winning tenderer(s) in the consolidated tender, except for cases of urgent necessity provided for by the legislation of Georgia and the implementation in a foreign country of the procurement determined by paragraph 2 of this Article by representatives of the Ministry of Internal Affairs of Georgia, the Ministry of Defence of Georgia and the State Security Service of Georgia, as well as by a defence attaché, a diplomatic mission and a consular post of Georgia, as well as a case provided for by the tender documentation.

5. Procuring organizations to which the operation of the consolidated tender does not mandatorily extend under a legal act of the Government of Georgia and the tender documentation of the relevant consolidated tender may, for the purpose of carrying out the procurement determined in accordance with paragraph 2 of this Article, and for the purpose of concluding a public procurement contract (hereinafter – the Contract), on the basis of the consent of the tender commission, apply to the winning tenderer(s) in the consolidated tender. In the event of conclusion of the Contract, the requirements established by this Rule and the tender documentation shall fully apply to them.

Article 2. Definition of Terms🔗

1. For the purposes of this Rule, the terms used herein have the following meanings:

a) Unified Electronic System of State Procurement (hereinafter – the System) – the official portal of state procurement https://tenders.procurement.gov.ge, which ensures the conduct of activities related to the implementation of centralized procurement, including the holding of a consolidated tender, in an open, transparent and competitive environment;

b) implementation of centralized procurement – implementation by the central purchasing body of activities related to centralized procurement determined by law, including the holding of a consolidated tender and the implementation of activities related to centralized procurement on the basis of an application by a purchasing organization;

c) holding of a consolidated tender – for the purpose of implementing state procurement by means of a consolidated tender, a set of decisions of the tender commission, as well as actions of the tender commission and its authorized representative(s), which includes the conduct of tender procedures, ensuring the process of concluding contracts between purchasing organizations and the supplier/suppliers, regulation of activities related to the performance of concluded contracts and administration of activities subsequent to the holding of the consolidated tender, including inspection and control;

d) tender procedures – a set of procedures which includes the relevant stages of a consolidated tender from the announcement of the consolidated tender until the commencement of the process of concluding the contract(s) within the framework of this tender;

e) authorized representative of the tender commission (hereinafter – authorized representative) – a natural person registered (added) and acting in the System in accordance with the established procedure, who acts on behalf of the tender commission;

f) tender conditions – information on the procurement provided for by the tender notice and tender documentation, as well as a set of conditions/requirements established by the tender commission in respect of the procurement object and the tenderer;

g) tender notice – a notice placed in the System by the authorized representative on the holding of a consolidated tender, which contains the information determined by this Rule and is part of the tender conditions;

h) tender documentation – documentation attached to the tender notice, which contains the information determined by this Rule and is part of the tender conditions;

i) tender bid – technical documentation submitted by the tenderer in compliance with the requirements of this Rule and in accordance with the tender conditions, for the purpose of participating in the consolidated tender, as well as, if any, the price of the tender bid, a sample of the procurement object and/or a document confirming the adequacy of pricing;

j) Technical documentation – documentation containing the information required by the tender conditions about the tenderer and the procurement object, including, where available, the expert opinion and the document reflecting registration/legal data. The technical documentation shall be uploaded in the relevant field of the system;

k) Tender bid price (hereinafter – bid price) – the tender bid price fixed as a result of electronic trading, which the tenderer indicates in the relevant field of the system;

l) Value of the contract to be concluded – if a consolidated tender is announced by the method provided for by subparagraph "a" or "b" of paragraph 1 of Article 3 of these Rules, the value of the contract to be concluded shall be the bid price fixed by the tenderer, unless otherwise determined by the tender documentation, and if the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these Rules – the estimated price determined by the tender documentation;

m) Expert opinion – an opinion issued by an expert or an expert institution, which shall confirm the compliance of the information indicated in the technical documentation about the procurement object, as well as, where available, of the sample, with the tender conditions and the technical documentation;

n) Document reflecting registration/legal data – a document to be submitted from an administrative body, which contains the information required by the tender conditions relating to the legal aspect of the tenderer's status/activity (registration data, legal restrictions, existing financial and other types of obligations, etc.);

o) Sample of the procurement object (hereinafter – sample) – a sample which, in compliance with the requirements of these Rules and in accordance with the tender conditions, is submitted to the tender commission in material form, for the purpose of establishing the compliance of the description of the procurement object or its component indicated in the technical documentation, as well as of the goods to be supplied or their component (including goods constituting part of a service), with the tender conditions and the technical documentation;

p) Document confirming the adequacy of pricing – a document determined by the tender documentation, in compliance with the requirements of these Rules, which shall confirm the ability to perform the obligations assumed within the framework of the consolidated tender at the bid price fixed by the tenderer;

q) Status of the progress of the consolidated tender (hereinafter – tender status) – a status existing in the system, assigned to the consolidated tender as a result of an action of the authorised representative or by means of the system, which reflects a specific stage of the progress of the consolidated tender;

r) Electronic trading – a constituent procedure of a consolidated tender, during which the tenderer may reduce the bid price in order to obtain victory in the consolidated tender. Electronic trading includes the main time and additional rounds. In the cases determined by this rule, a consolidated tender may not include electronic trading or the additional rounds of electronic trading;

s) the main time of electronic trading (hereinafter – the main time) – a constituent period of electronic trading from the commencement of the receipt of bids in the consolidated tender until the expiry of the deadline intended for the receipt of tender bids indicated in the tender notice;

t) the additional rounds of electronic trading (hereinafter – the additional rounds) – a constituent period of electronic trading – three additional rounds, which begin five minutes after the expiry of the main time. A two-minute break is held between the additional rounds. In each additional round, the tenderer has the right to reduce the bid price only once, for which two minutes are allocated to each tenderer;

u) the validity period of the winner's bid – the period established by the tender documentation, during which a contract may be concluded between the purchasing organisations and the winning tenderer(s);

v) the validity period of the consolidated tender – the period which begins from the announcement of the consolidated tender and the end date of which exceeds the final deadline for the delivery of the procurement object by not less than 30 (thirty) calendar days;

w) the electronic guarantee of tender bid security (hereinafter – the electronic guarantee) – for the purpose of securing the tender bid, a guarantee mechanism submitted by the tenderer to the State Procurement Agency through the system, in the amount of 1% of the estimated value of the procurement object;

x) the register of electronic guarantees – a database of electronic guarantees issued by a banking institution and/or an insurance organisation;

y) the consolidated tenders management system – the portal https://ctd.spa.ge created for consolidated tenders, which ensures the search, exchange, processing and reporting of the information necessary for conducting consolidated tenders, the obtaining of permission for a certain procurement and the management of consolidated tenders. The purchasing organisation shall be obliged to conclude a contract for the quantity submitted through the said portal within the framework of the relevant consolidated tender, unless, when requesting information, it was indicated by the central purchasing body that the quantity to be indicated by the purchasing organisation is indicative;

z) reporting – the submission, for reporting purposes, by the central purchasing body or the purchasing organisation to the State Procurement Agency of the information provided for by this rule;

aa) contract – a contract on state procurement concluded with a supplier within the framework of centralised procurement/a document equated thereto;

bb) report on the progress of contract performance – information submitted, in accordance with the law and this rule, by the procuring organisation to the State Procurement Agency on the progress of contract performance, in the established manner;

cc) contract status – a status existing in the system assigned to the contract as a result of an action of the authorised representative of the procuring organisation or through the system, which reflects a specific stage of the progress of the contract;

dd) documentation confirming the performance/non-performance of the contract – any document related to the performance/non-performance of the obligation undertaken under the contract (including an acceptance-handover act, a consignment note, an invoice, the opinion of the person responsible for monitoring the contract, an expert opinion, correspondence, a photograph, etc.);

ee) Agency – Legal Entity of Public Law – State Procurement Agency.

2. Other terms used in this rule have the same meaning as in the law, and also, taking into account the specificities of this rule, in other subordinate normative acts regulating state procurement adopted/issued on the basis of the law.

Article 3. Methods of conducting a consolidated tender🔗

1. A consolidated tender may be conducted:

a) by a method that provides for additional rounds of electronic trading;

b) by a method that does not provide for additional rounds of electronic trading;

c) by a method that does not provide for the holding of electronic trading.

2. The decision on conducting a consolidated tender by the relevant method shall be taken by the tender commission.

Article 4. Principles of conducting a consolidated tender🔗

When conducting a consolidated tender, the following principles shall be observed:

a) rational spending of the funds allocated for state procurement;

b) healthy competition among the participants in the procurement;

c) non-discriminatory approach and equal treatment towards the participants in the procurement;

d) establishment of proportionate requirements towards the participants in the procurement;

e) publicity and transparency.

Article 5. Conditions for the prevention of conflict of interest🔗

1. When conducting a consolidated tender, the conditions for the prevention of conflict of interest provided for by Article 8 of the Law shall be observed.

2. A natural person carrying out the activity defined by the first paragraph of Article 8 of the Law shall have a conflict of interest with a tenderer or supplier if there are relations between them as provided for by Article 19 of the Tax Code of Georgia.

3. The written declaration on the absence of conflict of interest shall be signed by the persons carrying out the activity defined by the first paragraph of Article 8 of the Law, as well as by the members of the staff of the tender commission who are involved in the process of conducting a specific consolidated tender.

4. During the consolidated tender, the written declaration on the absence of conflict of interest shall be uploaded to the system together with the minutes of the very first meeting of the tender commission to be uploaded after completion of receipt of bids in the consolidated tender. At the same time, if during the consolidated tender the identities of the tenderers become public in stages, the written declaration on the absence of conflict of interest shall be uploaded to the system individually, in relation to each tenderer, together with the minutes of the very first meeting of the tender commission to be uploaded after public disclosure of the identity of that tenderer.

5. The written declaration on the absence of conflict of interest of a natural person administering the activities following the conduct of the consolidated tender, including inspection and control, shall be uploaded to the system together with documentation confirming the conduct of inspection and control. At the same time, the said person shall not be obliged to confirm the absence of conflict of interest if he/she, as a member of the tender commission or of the staff of the tender commission, has already confirmed the same in relation to the same supplier (tenderer) during the consolidated tender.

6. The written declaration on the absence of conflict of interest of a natural person exercising control and supervision over the performance of a contract concluded within the consolidated tender shall be uploaded to the system by an authorized representative of the procuring organization, together with documentation confirming performance/non-performance of the contract.

Article 6. Tender Commission🔗

1. A consolidated tender shall be conducted by the tender commission provided for by paragraph 4 of Article 206 of the Law.

2. The tender commission shall act on behalf of the central purchasing body.

3. The tender commission shall be chaired by the chairperson of the tender commission. In the absence of the chairperson, his/her duties shall be performed, upon the instruction of the chairperson, by one of the deputies, and in the absence of the deputy, upon the instruction of the chairperson, by one of the members of the tender commission.

4. A meeting of the tender commission shall be convened by the chairperson of the tender commission or the person performing his/her duties.

5. Any decision taken at a meeting of the tender commission shall be reflected in the minutes of the respective meeting of the tender commission. The minutes of the tender commission meeting shall indicate:

a) the name of the tender commission;

b) the time and place of the meeting;

c) the identity of the chairperson and members of the tender commission (including a note on the member who does not attend the meeting);

d) the subject of consideration;

e) the deliberations of the tender commission;

f) the opinion of experts and consultants invited with an advisory vote (if any);

g) the legislative or subordinate normative act or its relevant norm on which the tender commission relies;

h) the results of the voting;

i) the decision taken.

6. For the purpose of technical and organizational support of the activities of the tender commission, by decision of the head of the central purchasing body, a staff of the tender commission shall be established from among the employees of this body, which shall be headed by the chairperson of the tender commission.

7. The tender commission shall adopt a decision by a majority of the total membership of the commission. In the event of an equal distribution of votes, the vote of the chairperson of the tender commission shall be decisive. A member of the tender commission who does not agree with the decision of the commission shall have the right to submit in writing his/her opinion, which shall be attached to the minutes of the tender commission meeting. A decision shall be considered adopted only after the minutes have been signed by all attending members of the tender commission.

8. The minutes of the tender commission meeting shall also be signed by a member of the staff of the tender commission who is involved in the process of conducting the specific consolidated tender.

9. The minutes of any meeting of the tender commission, except for the minutes of the meeting on approval of the tender conditions, shall be uploaded to the system immediately upon signing.

10. Any correspondence with the tender commission may be conducted through the Consolidated Tenders Management System or email. A notification shall be considered officially received, accordingly, from the moment of its upload to the system or sending to the email address.

Article 7. Right to receive clarification🔗

1. From the announcement of the consolidated tender until the commencement of receipt of bids in the consolidated tender, any user registered as a "supplier" in the system shall have the right to request from the tender commission, through the "question-answer" module existing in the system, clarification of a specific entry of the tender conditions. The tender commission shall be obliged, within a reasonable time after the question is posed, to provide the relevant clarification, by which any interested person may be guided.

2. After the completion of receipt of bids and before the identification of the winning tenderer, the right to request clarification regarding a decision/action of the tender commission shall be held by:

a) the tenderer with the lowest bid price – if the consolidated tender is announced by the method provided for by subparagraph "a" or "b" of paragraph 1 of Article 3 of these Rules;

b) all tenderers – if the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these Rules.

3. In the case provided for by paragraph 2 of this Article, the tender commission shall be obliged to provide the relevant clarification within a reasonable time.

Article 8. Termination of the consolidated tender🔗

The tender commission shall be entitled, at any time before the commencement of the process of concluding the contract(s), to terminate the consolidated tender, if this becomes necessary due to objective reasons independent of it and unforeseen in advance, as well as proceeding from the state interests of Georgia and/or public interests, and/or in the case provided for by paragraph 14 of Article 18 of these Rules.

Article 9. System malfunction🔗

1. If, due to a technical defect existing in the system, a tenderer is unable to submit a tender bid in a consolidated tender, the Agency shall be entitled to adopt a decision on extending the deadline for the completion of receipt of tender bids in the relevant consolidated tender(s) by an appropriate period.

2. The Agency may adopt the decision provided for by paragraph 1 of this Article only in relation to the consolidated tender(s) in which the deadline for the completion of receipt of tender bids coincides with the existence of the technical defect in the system.

3. The decision provided for by paragraph 1 of this Article shall determine the matters related to the additional rounds held before the adoption of this decision and/or the statuses conferred on the consolidated tender(s).

4. The central purchasing body shall be obliged to terminate the consolidated tender if the decision provided for by paragraph 1 of this Article contains such an instruction.

5. The decision provided for by paragraph 1 of this Article shall enter into force upon publication on the Agency's website www.procurement.gov.ge.

Article 10. Tender Conditions🔗

1. The tender commission shall adopt the decision on holding the consolidated tender and approve the tender conditions.

2. The minutes of the tender commission meeting shall be placed in the system together with the tender conditions.

3. The tender notice shall contain the following information:

a) the type of procurement (by which method the consolidated tender is conducted);

b) the number of the tender notice;

c) the status of the tender;

d) the procuring entity;

e) the date of announcement of the consolidated tender, indicating the exact time;

f) the date of commencement of acceptance of tender bids, indicating the exact time;

g) the date of completion of acceptance of tender bids, indicating the exact time;

h) the financing of the procurement (first year of procurement);

i) the estimated value of the procurement object;

j) an indication whether the tender bid shall be submitted without VAT or including it;

k) the classifier division and its corresponding CPV codes;

l) the most detailed possible procurement object and its corresponding CPV code (classifier category, class, group or division. If it is impossible to indicate a lower hierarchical level of the classifier, its next higher hierarchical level shall be indicated);

m) the indicative quantity/volume of the procurement object;

n) the delivery period of the procurement object;

o) the amount of the step (if any);

p) the first and last name of the authorized representative who placed the tender notice in the system, indicating the date and exact time of placement.

4. The information provided for by subparagraphs "b"–"f" of paragraph 3 of this Article shall be automatically generated in the tender notice by means of the system.

5. The tender notice has an additional information field, which the authorized representative may use for the purpose of additional description of the tender conditions.

6. In the tender notice, the estimated value of the procurement object and the amount of the step may be indicated only in the national currency.

7. Together with the tender notice, the tender documentation must be placed in the system.

8. The tender documentation shall contain:

a) the range of procuring organizations for which the operation of the consolidated tender is mandatory;

b) the qualification requirements that the tenderer must satisfy;

c) the method(s) and/or condition(s) by which the value of the tender bid shall be calculated;

d) the indicative quantity of the goods to be purchased or the indicative volume of the services, the period, place and form of delivery of the goods or provision of the services;

e) a full description of the technical, performance and/or functional specifications of the procurement object;

f) the amount of the electronic guarantee;

g) the time limit for payment of the value of the contract to be concluded, and if the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of this Rule, also the value of the contract to be concluded, the rules and conditions for payment of the value of the contract to be concluded;

h) the procedure for submitting a sample, as well as the document(s) accompanying the sample (if any);

i) the procedure for submitting a document confirming the adequacy of pricing (if any);

j) the procedure for submitting an expert opinion (if any);

k) the procedure for submitting a document reflecting registration/rights data (if any);

l) the procedure for selection-evaluation and identification of the winning tenderer(s);

m) the draft contract;

n) the procedure for concluding the contract;

o) an indication of the guarantee for securing the performance of the contract;

p) the means and procedure for requesting additional information and clarifications regarding the tender documentation;

q) other information provided for by this procedure.

9. The tender documentation may also provide for the amount within which it is permissible to increase the value of the contract initially concluded within the framework of a consolidated tender in the event of the occurrence of the conditions provided for by Article 398 of the Civil Code of Georgia.

10. The tender commission has the right, before the commencement of the receipt of bids, to amend the tender conditions. It is inadmissible to change the method of conducting a consolidated tender and the object of procurement.

11. Amendments to the tender conditions shall be made in compliance with the requirements established by this procedure for the approval of the tender conditions.

Article 11. Submission of a Tender Bid🔗

1. A person wishing to participate in procurement may submit a tender bid in a consolidated tender at the stage of submission of bids. A tender bid may be submitted only through the system, after agreeing to the terms of the affidavit, submitting an electronic guarantee and paying the fee, in the sequence provided for in this paragraph.

2. Before submitting a tender bid, any interested person has the right to review the tender conditions. By submitting a tender bid, the tenderer agrees to the tender conditions.

3. When submitting a tender bid, the tenderer shall, first of all, upload the technical documentation to the system (except for the expert opinion, which may be submitted in material form if this is provided for by the tender documentation). Thereafter, if the consolidated tender is announced by the method provided for by subparagraphs “a” or “b” of paragraph 1 of Article 3 of these Rules, the tenderer shall indicate in the relevant field of the system the bid price (in national currency), which shall not exceed the estimated value of the procurement object or shall be lower than the estimated value of the procurement object by at least one step.

4. If the consolidated tender is announced by the method provided for by subparagraphs “a” or “b” of paragraph 1 of Article 3 of these Rules, a tenderer who is a VAT payer shall submit the tender bid excluding VAT or including it, depending on what indication the tender notice contains regarding VAT. A tenderer who is not a VAT payer shall submit the tender bid excluding VAT, regardless of what indication the tender notice contains regarding VAT. If the tender notice provides for submission of the tender bid excluding VAT, the tenderer shall submit the tender bid excluding VAT, regardless of whether or not it is a VAT payer. In such a case, if the winning tenderer, at the moment of conclusion of the contract, in accordance with Georgian legislation, is a VAT payer, the procuring organization shall take into account in the contract value the amount of VAT corresponding to the bid price. Information on the registration of the tenderer as a VAT payer is automatically generated through the system.

5. If the consolidated tender is announced by the method provided for by subparagraphs “a” or “b” of paragraph 1 of Article 3 of these Rules, after indicating the bid price, the tenderer shall not have the right to change, add to or delete the technical documentation.

6. If the consolidated tender is announced by the method provided for by subparagraphs “a” or “b” of paragraph 1 of Article 3 of these Rules, immediately upon submission of the tender bid, the tenderer is given the opportunity, through the system, to participate in electronic trading.

7. Submission of a tender bid or its constituent document may be made in both Georgian and foreign languages. If a document is submitted in a foreign language, it shall be accompanied by a translation into Georgian executed in accordance with the procedure established by Georgian legislation. When resolving disputed issue(s) related to the document, the issue of granting priority between the foreign-language document and its translation into Georgian shall be decided by the tender commission.

8. Before being declared the winner, a tenderer has the right to withdraw the tender bid. During the main time or additional rounds, the tenderer withdraws the tender bid through the system. If the tenderer withdraws the tender bid after the end of the main time or additional rounds, the tenderer shall be subject to disqualification. Withdrawal of a tender bid entails the consequence provided for by paragraph 5 of Article 14 of this rule.

Article 12. Participation of a partnership in a consolidated tender🔗

1. For the purpose of joint participation in a consolidated tender, two or more suppliers shall be entitled to unite by a joint activity (partnership) contract. By agreement of the parties, a joint activity (partnership) contract may be concluded for the purpose of participating in one or several electronic tenders.

2. Suppliers shall conclude the joint activity (partnership) contract in written form, which must be signed by all its participants. By agreement of the participants, the contract or the authenticity of their signatures must be certified by a notary or another person provided by law. The contract must contain the conditions defined by paragraph 2 of Article 931 of the Civil Code of Georgia. At the same time, when agreeing on the terms of the contract, suppliers are obliged to take into account that:

a) the term of the joint activity (partnership) contract may not be less than the term of the consolidated tender;

b) before the fulfilment of the obligations undertaken within the framework of the consolidated tender, it is inadmissible to replace or add a participant of the partnership;

c) before the fulfilment of the obligations undertaken within the framework of the consolidated tender, the withdrawal of one of its participants from the partnership causes the termination of the joint activity;

d) the partnership must be represented before the central purchasing body/purchasing organisation by a natural person authorised to manage and represent it, who shall be selected from among the participants of the partnership.

3. After the conclusion of the joint activity (partnership) contract, the partnership is obliged, in accordance with the established procedure, to be registered for tax accounting and to register in the system. For registration in the system, it is necessary that all suppliers participating in the partnership be registered in the system. The profile of the partnership shall indicate the details of its participating suppliers and the joint activity (partnership) contract shall be uploaded (if it exists, subsequent amendments to this contract shall also be subject to uploading).

4. In a consolidated tender, the partnership participates and submits a tender bid as an independent tenderer. The partnership and its participants are prohibited from participating individually in the same consolidated tender. In such a case, the partnership and its participant/participants shall be subject to disqualification on the basis of paragraph 12 of Article 18 of this rule.

5. The participants of the partnership are authorised to perform different parts of the obligations provided by the state procurement contract, if it is possible to separate them from the whole obligation and perform them independently, in such a way that the aforementioned, with a high degree of probability, should not cause the destruction, damage and/or impossibility of enjoying the result. The participants of the partnership must clearly define in the technical documentation which specific obligation each participant will perform within the framework of the state procurement contract.

6. The issue of compliance with the tender conditions by a consortium shall be considered as follows:

a) the compliance of the technical documentation of the consortium members with the tender conditions shall be determined in relation to the requirement established for the obligation to be performed by the member, taking into account the requirements of paragraph 5 of this Article. At the same time, the aggregation of the financial and material-technical capabilities of the consortium members shall be permissible, while the aggregation of experience shall not be permissible;

b) documents reflecting registration/legal data (if any) shall be submitted to the tender commission both in respect of the consortium and in respect of its members.

7. If the contract of joint activity (consortium) has not been concluded in accordance with paragraph 2 of this Article, the consortium has not acted in accordance with paragraph 3 of this Article, or the technical documentation of the consortium has not been drawn up taking into account the requirements of paragraph 5 of this Article, the consortium shall be subject to disqualification on the basis of paragraph 4 of Article 18 of these Rules.

8. Participation in a consolidated tender shall be prohibited for a consortium a member of which is registered in the black list.

9. The members of joint activity (consortium) shall be liable to the central purchasing body/purchasing organisation jointly and severally.

10. Termination of joint activity shall result in the termination of the consolidated tender in its entirety, and if the consolidated tender is announced by the method provided for by subparagraph „c“ of paragraph 1 of Article 3 of these Rules — in part, in relation to a specific supplier. At the same time, the members of joint activity (consortium) shall be liable for the consequence arising from the termination of the consolidated tender.

11. Legal relations related to the contract of joint activity (consortium), taking into account the peculiarities of this Article, shall be governed by the Civil Code of Georgia.

Article 13. Fee🔗

1. The amount of the fee for submitting a tender bid is 100 GEL.

2. Payment of the fee is possible only electronically, through the system, after the submission of the electronic guarantee and before uploading the technical documentation into the system.

3. Refund of the paid fee shall be permissible only if the fee was paid by mistake in an amount exceeding the established rate. In this case, the difference between the paid amount and the established rate shall be refunded.

4. A request for the refund of the overpaid amount, indicating the relevant ground and with the attached documentation, shall be submitted to the Agency within three months from the erroneous payment of the amount. The Agency shall consider the request within one month. If the request is granted, the amount shall be refunded to the interested person within 10 working days. After the expiry of the three-month period, the overpaid amount shall not be refunded. Extension of the period or restoration of a missed period shall not be permitted.

Article 14. Electronic Guarantee🔗

1. A person wishing to participate in procurement shall submit a guarantee through the system, after agreeing to the terms of the affidavit, before payment of the fee.

2. The beneficiary/recipient of the electronic guarantee is the agency.

3. The electronic guarantee shall be valid from the submission of the tender bid throughout the entire term of validity of the winner's bid, unless the tender documentation provides for a shorter term of validity of the electronic guarantee.

4. Except for the cases provided for by paragraph 5 of this Article, the electronic guarantee shall be returned:

a) in the case of the winning tenderer – after the expiry of the term provided for by paragraph 3 of this Article or after it concludes all contracts that it is obliged to conclude;

b) in the case of another tenderer – after receiving disqualification on the basis of paragraph 4, 7 or 8 of Article 18 of this rule or, if it has not received disqualification, after the commencement of the process of concluding a contract with the winning tenderer(s).

5. The tenderer loses the electronic guarantee in one of the following cases:

a) it refuses the tender bid in electronic trading or receives disqualification for refusing the tender bid;

b) it receives disqualification for committing an unfair act for the purpose of obtaining the right to conclude a contract;

c) it receives disqualification for failure to submit document(s) reflecting registration/legal data within the established term and/or for inconsistency of document(s) reflecting registration/legal data and/or registration legal data with the tender conditions;

d) it receives disqualification for refusal to conclude a contract and/or otherwise expressing refusal to conclude a contract;

e) it refuses to conclude a contract with one or several procuring organizations that apply to it in this regard.

6. If the electronic guarantee is returned to the tenderer in violation of the conditions established by this Article, it shall be obliged to return the amount of the electronic guarantee to the agency immediately upon the corresponding demand.

7. The guarantor shall be obliged, immediately upon the agency's demand, to ensure the fulfillment of the demand sent by the agency through the system in the form of an electronic notification regarding the performance of the electronic guarantee registered in the electronic system of guarantees or the waiver of the right provided for by the guarantee.

Article 15. Conducting a consolidated tender by a method that provides for additional rounds of electronic trading🔗

1. If a consolidated tender is announced by the method provided for by subparagraph „a“ of paragraph 1 of Article 3 of this Rule, during the main period the tenderer is entitled to reduce the bid price several times, by not less than one step compared to the previously offered price.

2. Only the tenderer who, during the main period, submitted a tender bid in accordance with the established procedure has the right to participate in the additional rounds. In the first additional round, the order of offers is determined according to the bid prices submitted by the tenderers during the main period. In particular, in the first additional round, the first offer is made by the tenderer who recorded the highest bid price during the main period, and in each subsequent round – by the tenderer who recorded the highest bid price in the previous round. If equal bid prices are recorded, the first offer in the round is made by the tenderer who was the last to record such a price. Participation in the additional rounds is not mandatory.

3. During the main period, the system ensures the anonymity of the number of tenderers, their identity and the tender bids. The number of tenderers and the bid prices become public from the moment the additional rounds begin. The identity of the tenderers and the technical documentation become public immediately upon completion of the additional rounds.

4. Immediately upon completion of the additional rounds, the system shall automatically determine the ranking of the tenderers (if any) according to the lowest bid price. If two or more tenderers indicate in the system the lowest equal bid price, the system shall automatically give preference to the tenderer who was the first to indicate the lowest bid price.

5. If the tenderer with the lowest bid price is disqualified, the tender commission shall evaluate the tenderer with the next lowest bid price (if any) or adopt a decision on termination of the consolidated tender in accordance with paragraph 14 of Article 18 of this Rule.

Article 16. Conducting a consolidated tender by a method that does not provide for additional rounds of electronic trading🔗

1. If a consolidated tender is announced by the method provided for by subparagraph "b" of paragraph 1 of Article 3 of these Rules, electronic trading shall proceed only during the main time. After the bid price is fixed, the tenderer has the right, before the end of the main time, to reduce the price of the submitted bid only once by not less than one step.

2. During the main time, the system ensures the anonymity of the number of tenderers, their identity and tender bids. Immediately upon the end of the main time, only the identity and tender bid of the tenderer with the lowest bid price become public. The number of tenderers, the identity of other tenderers and their tender bids become public only in the event of identification of the winning tenderer, immediately upon the commencement of the process of concluding a contract with all winning tenderers.

3. Immediately upon the end of the main time, the identity and tender bid of the tenderer who declines the tender bid during the main time (if any) shall also become public.

4. Immediately upon the end of the main time, the system shall automatically determine the ranking of the tenderers (if any) according to the lowest bid price; if two or more tenderers indicate the same lowest bid price in the system, the system shall automatically give preference to the tenderer who was the first to indicate the lowest bid price.

5. If the tenderer with the lowest bid price is disqualified, the tender commission shall evaluate the next tenderer with the lowest bid price (if any), whose identity and tender bid become public immediately upon the disqualification of the previous tenderer from the consolidated tender, or shall adopt a decision on termination of the consolidated tender in accordance with paragraph 14 of Article 18 of these Rules.

Article 17. Conducting a consolidated tender by a method that does not provide for electronic trading🔗

1. If a consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these Rules, the tenderer, by submitting a tender bid, agrees to the fixed price indicated in the tender notice and/or documentation.

2. At the stage of submission of bids, the system ensures the anonymity of the number of tenderers, their identity and tender bids. The number of tenderers, their identity and tender bids become public immediately upon the end of the stage of submission of bids.

3. Immediately upon the end of the stage of submission of bids, the identity and tender bid of the tenderer who declines the tender bid at the stage of submission of bids (if any) shall also become public.

4. After the end of the stage of submission of bids, the tender commission shall evaluate all tenderers participating in the consolidated tender (if any).

Article 18. Evaluation of tenderers🔗

1. The tender commission shall evaluate tenderers according to the tender bids submitted by them, in accordance with this rule and the tender conditions.

2. It shall be inadmissible to require a tenderer to submit information that was not provided for by the tender conditions, except for the case where the obligation to submit the information required of the person directly follows from the legislation of Georgia.

3. It shall be inadmissible to consider as a defect a circumstance that was not provided for by the tender conditions, except for the case where considering the said circumstance as a defect directly follows from the legislation of Georgia.

4. In the event that the technical documentation does not comply with the tender conditions, the tenderer shall be subject to disqualification, except for the case provided for by paragraph 5 of this Article.

5. The tender commission shall not disqualify a tenderer if its technical documentation (except for the expert opinion and the document(s) reflecting registration/rights data) does not contain such data and/or contains such inaccuracy/inaccuracies, the submission and/or correction of which will not cause a substantial change of the technical documentation and/or will not increase the price of the bid. The expert opinion and/or the document(s) reflecting registration/rights data shall not be subject to correction.

6. In the case provided for by paragraph 5 of this Article, the tender commission shall address the tenderer with a request to correct the technical documentation in the manner established by the tender documentation, for which it shall set for it the time limit provided for by the tender documentation. The tender commission shall be obliged to indicate precisely to the tenderer the position/part to be corrected. The corrected technical documentation shall be submitted to the tender commission through the system.

7. In the case provided for by paragraph 6 of this Article, a tenderer that does not correct the technical documentation within the established time limit, corrects it incompletely and/or as a result of correction substantially changes it, shall be subject to disqualification.

8. If the tender documentation contains an obligation to submit a sample and/or a document confirming the adequacy of pricing, the tender commission shall address the tenderer with a request to submit the sample and/or the document confirming the adequacy of pricing in the manner established by the tender documentation, for which it shall set for it the time limit provided for by the tender documentation. A tenderer that does not submit the sample and/or the document confirming the adequacy of pricing within the established time limit or whose submitted sample and/or document confirming the adequacy of pricing does not comply with the tender conditions and/or the technical documentation shall be subject to disqualification.

9. The corrected technical documentation, as well as the sample and/or the document confirming the adequacy of pricing, shall not be subject to correction.

10. If a consolidated tender is announced by the method provided for by subparagraph “a” or “b” of paragraph 1 of Article 3 of this Rule, the tenderer with the lowest bid price whose tender bid fully complies with the tender conditions shall be identified as the winner.

11. If a consolidated tender is announced by the method provided for by subparagraph “c” of paragraph 1 of Article 3 of this Rule, all tenderers whose tender bid fully complies with the tender conditions shall be identified as winners.

12. A tenderer who, for the purpose of obtaining the right to conclude a contract, commits an unfair act is subject to disqualification, which entails the consequence provided for by paragraph 5 of Article 14 of this Rule.

13. A tenderer who fails to submit the document(s) reflecting registration/legal data within the established period, and/or whose registration/legal data and/or document(s) reflecting registration/legal data do not comply with the tender conditions, is subject to disqualification, which entails the consequence provided for by paragraph 5 of Article 14 of this Rule.

14. If a consolidated tender is announced by the method provided for by subparagraph “a” or “b” of paragraph 1 of Article 3 of this Rule, in the event of disqualification of the tenderer with the lowest bid price, the tender commission shall evaluate the next tenderer with the lowest bid price (if any) or shall adopt a decision on termination of the consolidated tender, if the bid price of the next tenderer, as a result of changed circumstances on the market, significantly exceeds the market value of the object of this procurement.

Article 19. Amount payable by the winning tenderer🔗

1. Within the framework of a consolidated tender, the winning tenderer shall pay to the account of the central purchasing body 1% of the value of the contract to be concluded. The specific amount of this sum is indicated in the system by the central purchasing body, except where the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these rules.

2. The sum provided for by paragraph 1 of this Article shall be paid by the winning tenderer, and the document confirming payment of the sum shall be uploaded in the relevant field of the system within the period determined by the tender documentation. If the consolidated tender is announced by the method provided for by subparagraph "a" or "b" of paragraph 1 of Article 3 of these rules, the said period may not exceed 3 (three) working days from the identification of the winning tenderer, and if the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these rules, the rules and conditions for payment of this sum, including the period, shall be determined by the tender documentation.

3. The document confirming payment of the sum submitted by the winning tenderer shall be considered by the tender commission immediately upon its submission, within a reasonable period, except where the consolidated tender is announced by the method provided for by subparagraph "c" of paragraph 1 of Article 3 of these rules.

4. The minutes of the tender commission meeting related to the payment of the sum shall be uploaded in the system immediately, upon signature, with the assignment of the relevant status.

5. Within the framework of a consolidated tender, conclusion of a contract with the winning tenderer shall be possible only if full payment of the sum provided for by this Article and/or the tender documentation is confirmed.

6. By failing to pay within the established period the sum provided for by this Article and/or the tender documentation, the tenderer refuses to conclude the contract and is subject to disqualification, which entails the consequence provided for by paragraph 5 of Article 14 of these rules.

7. In the case provided for by paragraph 6 of this Article, if the consolidated tender is announced by the method provided for by subparagraph "a" or "b" of paragraph 1 of Article 3 of these rules, in the event of disqualification of the tenderer with the lowest bid price, the tender commission shall evaluate the next tenderer with the lowest bid price (if any) or shall adopt a decision on termination of the consolidated tender, if the bid price of the next tenderer, as a result of circumstances changed on the market, significantly exceeds the market value of the object of this procurement.

8. In the event of extension of the term of the consolidated tender, the sum payable by the winning tenderer shall be determined proportionally, on the basis of the data of the elapsed period.

9. In those tenders where the quantity of the procurement object is indicated in the tender documentation with allowance for minus and/or plus, if contracts were concluded for a quantity less than 100% or more than 100%, the amount payable by the winning tenderer may be adjusted in accordance with the value of the initially concluded contract.

10. In the case provided for by paragraph 9 of this Article, the winning tenderer shall apply to the central purchasing body with a request for the return of the overpaid amount within no later than 1 (one) month from the expiry of the validity period of the consolidated tender. The tenderer shall submit to the central purchasing body the relevant information and supporting documentation on the amount to be returned. At the same time, the central purchasing body is entitled to require from the winning tenderer additional information and/or documentation for the purpose of clarifying the submitted data.

11. Except for the case provided for by paragraph 10 of this Article, within 1 (one) month from the expiry of the validity period of the consolidated tender, the central purchasing body is entitled to consider the issue of the amount paid by the winning tenderer within the relevant consolidated tender and, if an obligation to pay an additional amount exists, within the same period apply to the winning tenderer with a request for payment of the relevant amount.

12. The return/covering of the overpaid or additional amount arising from the adjusted price shall be carried out within the period and in the manner determined by a decision of the tender commission.

Article 20. Conclusion of a contract with the winning tenderer🔗

1. The contract shall be concluded between the purchasing organizations and the winning tenderer(s) identified as a result of the consolidated tender, on the basis of the draft contract contained in the tender documentation, in accordance with the tender conditions and the tender bid of the winning tenderer.

2. The winning tenderer undertakes the obligation to conclude a contract with any purchasing organization defined by the tender documentation to which the effect of the consolidated tender extends on a mandatory basis.

3. The contract shall be concluded in written form and shall contain:

a) the exact names and details of the parties;

b) the number of the tender notice;

c) the name of the procurement object and its corresponding CPV code (category, class, group or division of the classifier. In the event of impossibility of indicating a lower hierarchical level of the classifier, the purchasing organization shall indicate the next higher hierarchical level thereof);

d) the value of the contract;

e) the term for performance of the contract;

f) the terms of the guarantee for securing performance of the contract (if any);

g) the settlement procedure, as well as, if any, the terms of advance settlement;

h) the specific term of validity of the contract;

i) the terms of inspection and control.

4. The purchasing organization is entitled to include additional terms in the contract. It is inadmissible to include in the contract such additional terms as were not indicated in the tender documentation.

5. The purchasing organization shall be obliged to address the winning tenderer in written form regarding the conclusion of the contract.

6. The contract may be concluded in both Georgian and a foreign language. In the event of concluding the contract in a foreign language, it shall be translated into Georgian in the manner established by the legislation of Georgia. The contract does not need translation if it is concluded as a single document, in parallel in Georgian and a foreign language.

7. Taking into account the specifics of the law and this Rule, the additional requirements regarding contracts provided for by the Civil Code of Georgia shall apply to a contract on state procurement.

8. In the case provided for by subparagraph „e“ of paragraph 5 of Article 14 of this Rule, if the winning tenderer refuses to conclude the contract, the tender commission has the right to act in accordance with paragraph 3 of Article 26 of this Rule.

9. The contract shall be uploaded by the purchasing organization into the system no later than within 10 days from its conclusion. Together with the contract, the purchasing organization shall be obliged to upload into the system the documents related to the conclusion of the contract, including the guarantee for securing performance of the contract (if any) and the guarantee of the corresponding amount of the advance payment amount (if any).

Article 21. Guarantee of performance of the contract🔗

1. If, within the framework of a consolidated tender, the value of the contract to be concluded amounts to or exceeds 200,000 GEL, the purchasing organization shall require the winning tenderer to provide a guarantee of performance of the contract, in the amount provided for by the tender documentation.

2. The amount of the guarantee of performance of the contract shall be determined:

a) from 2% to 5% inclusive of the contract value;

b) from 2% to 10% inclusive of the contract value – if the final price of the bid recorded by the winning tenderer as a result of electronic trading is less by 20% or more than the estimated value of the procurement object.

3. It is inadmissible to require the winning tenderer to submit a guarantee of performance of the contract, except for a substantiated case provided for by the tender documentation.

4. The guarantee of performance of the contract shall be submitted to the purchasing organization before the conclusion of the contract.

5. The purchasing organization has the right, by a substantiated decision, not to accept such a guarantee of performance of the contract as contradicts the legislation of Georgia.

Article 22. Conclusion of a contract with a non-winning person🔗

The purchasing organization defined by the tender documentation, to which the effect of the consolidated tender extends on a mandatory basis, in the case of the need to purchase the procurement object provided for by the tender documentation from a non-winning person, with appropriate substantiation, shall apply to the tender commission. In the case of the consent of the tender commission, the procurement shall be carried out in the manner established by the legislation of Georgia.

Article 23. Terms of settlement🔗

1. Settlement with the supplier shall be carried out in non-cash form, in national currency, and includes all taxes established by the legislation of Georgia.

2. The procedure for drawing up the acceptance-transfer act and the settlement periods shall be determined by the tender documentation.

Article 24. Determination of fuel price and settlement terms🔗

1. Z in US dollars (costs related to transportation, logistics and storage, overhead costs and enterprise profit) shall be calculated from the price of the bid recorded as a result of electronic trading by the tenderer that won the consolidated tender announced for the purchase of petroleum products (fuel), using the following formula:

where the variables are designated as follows:

Cbid – final price recorded as a result of electronic trading for 1 litre of the corresponding grade of fuel (in GEL);

Rnov – arithmetic mean for the month preceding the completion of electronic trading in the consolidated tender of the official exchange rate of the GEL against the US dollar;

D – density indicator of the corresponding grade of fuel submitted in the supplier's tender bid (g/cm3);

Pnov – arithmetic mean price in US dollars for the month preceding the completion of electronic trading in the consolidated tender of one metric ton of the corresponding grade of fuel recorded (published) on the PLATTS EUROPEAN MARKETSCAN FOB Med (Italy) exchange (hereinafter – the Platts marker);

Anov – amount of excise duty in GEL per metric ton of the corresponding grade of fuel in the month preceding the completion of electronic trading in the consolidated tender.

The values of Z and D shall remain unchanged for the period established by the tender documentation.

2. The supplier shall determine, for each current calendar month, the nominal value of 1 litre of the corresponding grade of fuel (hereinafter – nominal value – Cnom) using the following formula:

where: P and R represent the arithmetic mean values of the corresponding data for the calendar month preceding each current month, A – the amount of excise duty in GEL per metric ton of the corresponding grade of fuel in effect for the current month, 18% – VAT, and Z and D – the unchanged values submitted in the winning tender bid as provided for by paragraph 1 of this Article.

3. Due to the specificity of the price of petroleum products (fuel), because of the dependence of its value on the changing price on the international commodity exchange (P), the official exchange rate of the national currency against the US dollar (R) and/or the amount of excise duty per metric ton of fuel, the supplier shall monthly submit to the purchasing organization the unit price of the goods to be supplied during the current month, calculated on the basis of the nominal value (current month's contractual price – C1).

4. The contractual price for the first month of the term of the consolidated tender shall be determined as an amount equal to the final price (Cbid) of 1 litre of the corresponding brand of fuel recorded as a result of electronic trading. The contractual price for each subsequent month shall be determined on the basis of the nominal value of 1 litre of fuel. The supplier, taking into account the variability of the Platts quotation and the exchange rate, and on the first day of each calendar month, shall determine the contractual price of 1 litre of fuel for the current month according to the following principle: in the event that a change in P and R causes a change of less than three per cent in the nominal value (Cnom) of 1 litre of fuel calculated by the formula in relation to the contractual price of the previous month, then the contractual price of the current month shall be equal to the contractual price of the previous month, and in the event that a change in P and R causes a change of three or more per cent in the nominal value (Cnom) of 1 litre of fuel calculated by the formula in relation to the contractual price of the previous month, then the contractual price of the current month shall be equal to the nominal price of the current month calculated by the formula.

5. Settlements between the supplier and the purchasing organisation shall be effected according to the settlement price (C2) determined on the basis of the contractual price of the current month, in non-cash form, in the national currency, and shall include all taxes established by the legislation of Georgia.

6. When determining the settlement price, the following circumstances shall be taken into account:

a) in the case of purchase of fuel by means of a card system and/or a system which physically ensures the connection and identification of the fuel dispenser nozzle of a filling station and the fuel tank of an authorised vehicle, as a result of which it ensures the filling of fuel at the supplier's filling station only into the fuel tank of an authorised vehicle (a vehicle on the balance sheet of the purchasing organisation, equipped with components of the vehicle servicing and automatic identification system – AGAI), the supplier shall submit monthly to the purchasing organisation a tax invoice for the fuel supplied during the current month, at the end of the month. In the case of such a purchase, when determining the settlement price, the parties shall take into account the following circumstance: the settlement price shall be less than the arithmetic average amount (CAV) of the prices of one litre of the corresponding brand of fuel existing in the supplier's retail network during the current month, by the amount established by the tender documentation;

b) in the case of purchase of fuel by a non-card system, on the day of withdrawal of the fuel, the supplier shall submit to the purchasing organisation an invoice issued for the corresponding brand of fuel to be withdrawn at one time. The settlement price shall be calculated according to the settlement price determined on the basis of the nominal value, which shall be less than the price existing in the supplier's retail network for the day of the fuel request, by the amount established by the tender documentation.

7. The procuring organization shall, within five working days from the submission of a tax invoice by the supplier, confirm or refuse to confirm the invoice with the relevant justification. When supplying fuel of the corresponding grade through the non-card, card or AGAI system, settlement shall be made within five working days from the submission of the invoice.

8. The supplier shall, on the first working day of each month, submit to the tender commission the P and R defined by paragraph 2 of this Article and, calculated on their basis, the contractual price (C1) for the current month of 1 liter of fuel of the corresponding grade, which shall be immediately posted on the supplier's official website.

9. The supplier shall also post on its official website information on the daily price of 1 liter of fuel of the corresponding grade available in its retail sale network, in such a way that it is possible to view the price of each day during the term of the consolidated tender. The supplier shall also, at the beginning of each working day, provide to the tender commission information on the daily price of 1 liter of fuel of the corresponding grade available in its retail sale network, to the email address indicated in the tender documentation.

10. The supplier shall be responsible for the accuracy of any information submitted in connection with the fuel price, as well as posted on its website.

11. Within the framework of state procurement of petroleum products (fuel) through the card system, settlement related to the continuous service of supply of the fuel of the volume required for the month of December of each year shall be made in accordance with the procedure established by the legislation of Georgia for settlement during state procurement of continuous service.

Article 25. Amendment of the contract🔗

1. In the event of any amendment to the contract, the said amendment shall be agreed with the tender commission, executed in written form and, in accordance with the established procedure, uploaded to the system within a period of no later than 10 days from the amendment.

2. For the purpose of deciding the issue of amending the contract, the relevant purchasing organisation shall apply to the tender commission. When taking a decision, the tender commission shall be guided by this Rule, as well as by the principles of proportionality, expediency and commensurateness. The tender documentation may determine issues that do not require agreement with the tender commission.

3. Amendment of the contract shall be inadmissible if, as a result of such amendment, the value of the contract increases or the terms of the contract worsen for the purchasing organisation, except for the cases established by Article 398 of the Civil Code of Georgia.

4. In the event of the occurrence of the conditions provided for by Article 398 of the Civil Code of Georgia, it shall be permissible to increase the amount of the value of the initially concluded contract by the amount determined by the tender documentation (if such exists). At the same time, if the tender documentation does not provide for the amount provided for by this paragraph, the issue of increasing the value of the contract shall be decided by the tender commission.

5. Replacement of the supplier in the contract shall be inadmissible, except for the cases provided for by the legislation of Georgia (merger, division of the organisation, etc.).

Article 26. Non-fulfilment and/or improper fulfilment of obligations🔗

1. In the event of non-fulfilment and/or improper fulfilment by the supplier of the obligations assumed under the legislation of Georgia and as a result of the consolidated tender, the relevant purchasing organisation shall apply to the tender commission for the purpose of deciding the issue of termination of the contract. When taking a decision, the tender commission shall be guided by the principles of proportionality, expediency and commensurateness.

2. In the event of the tender commission issuing an instruction on the termination of the contract, the purchasing organisation shall terminate the contract.

3. In the case provided for by paragraph 2 of this Article, the tender commission shall be entitled to consider the termination of the consolidated tender as a whole, and if the consolidated tender has been announced by the method provided for by subparagraph „c“ of paragraph 1 of Article 3 of this Rule – partially, in relation to a specific supplier, as well as the expediency of holding a new consolidated tender or using alternative means of procurement. When taking a decision, the tender commission shall be guided by the principles of proportionality, expediency and commensurateness.

4. In the event of non-fulfilment and/or improper fulfilment of the obligations assumed as a result of the consolidated tender, the return of the amount provided for by Article 19 of this Rule shall be inadmissible.

Article 27. Status of the contract🔗

1. In the event of performance/non-performance of the contract, within a period of no later than 10 days, the purchasing organization shall upload into the relevant field of the system the documentation confirming the performance/non-performance of the contract, shall reflect information on the final settlement and shall assign to this contract the relevant status of the contract ("performed contract" or "non-performed contract").

2. In the event of phased performance of the contract, the purchasing organization shall upload into the relevant field of the system the documentation confirming the performance/non-performance of the contract and shall reflect information on settlement (if any) within a period of no later than 10 days from the performance/non-performance of the specific stage of the contract.

3. Any document related to the performance/non-performance of the obligation undertaken under the contract shall be considered documentation confirming the performance/non-performance of the contract (including an acceptance-handover act, a waybill, an invoice, the conclusion of the person responsible for monitoring the contract, an expert opinion, correspondence, a photograph, etc.).

Article 28. Activities related to centralized procurement on the basis of an application by the purchasing organization🔗

1. The central purchasing body, on the basis of an application by the purchasing organization, shall carry out activities related to centralized procurement on the basis of and in accordance with a contract concluded with the relevant purchasing organization.

2. For the provision of consultations related to the planning or implementation of procurement and/or for planning and implementation in favour of and at the expense of the relevant purchasing organization, the amount of the determined fee may not be less than 1,000 (one thousand) GEL. The specific amount of the fee shall be determined by the contract concluded with the relevant purchasing organization.

3. When planning and implementing in favour of and at the expense of the relevant purchasing organization, the central purchasing body shall act in the name of the purchasing organization and it shall be limited by the rights and obligations determined for the purchasing organization by the Law of Georgia "On State Procurement" and the relevant normative act.

4. The essential and other additional terms of each specific contract to be concluded in accordance with this article, including the rights and obligations of the parties, as well as the procedural issues of its conclusion and performance, shall be determined by an individual administrative-legal act issued by the head of the central purchasing body.

Article 29. Coordination and Supervision🔗

1. For the purposes of coordination and supervision, the Agency shall be entitled, at any stage of the conduct of procurement, to request from the central purchasing body, the purchasing organisation, the supplier and/or the tenderer any document and information related to the procurement, including information related to the performance of the contract.

2. For the purposes of reporting by the central purchasing body and the purchasing organisation, the information submitted to the Agency through the system shall be accessible to any registered user, taking into account the specifics of this rule.

3. The Agency shall ensure the storage in the system of the information submitted to the Agency by the central purchasing body and the purchasing organisations in accordance with this rule for a period of not less than 3 years from the submission.

4. The central purchasing body, as well as the purchasing organisation, shall be obliged to ensure the storage of any document related to the procurement for 6 years from the completion of the relevant procedure, and in the case of the conclusion of a long-term (two years or more) contract – for 3 years from the expiry of the term of the contract.

Annex

Form and Terms of the Affidavit

Affidavit

on the Independent Determination of the Tender Bid

For the purpose of participating in the announced consolidated tender, I confirm that:

the tender bid submitted by me has been developed independently of a competitor;

for the purpose of obtaining a material gain or advantage, no consultation, communication, agreement or negotiation has been conducted between me and a competitor in relation to the following matters:

the price of the tender bid, the method of its calculation, the coefficient or formula;

the technical/quality indicators, quantity/volume and/or delivery details of the procurement object to which the tender bid relates;

the submission/clarification of the tender bid or refraining from submission/clarification;

the submission of a tender bid/clarified bid that does not meet the tender conditions.

the tenderer has not disclosed, directly or indirectly, and/or will not disclose the tender bid or its component to a competitor before the moment of public disclosure of the tender bid (its respective component);

I am aware of the meaning of the term "competitor" for the purposes of the affidavit (any person who is or may be a tenderer in this tender);

no false information has been submitted in order to satisfy the tender conditions, which the tenderer knew or ought to have known;

the information submitted in the form of the tender bid has been created/obtained in good faith;

I am duly authorised by the tenderer to sign the affidavit and submit this tender bid;

any person whose signature is recorded on the tender bid is duly authorised by the tenderer;

in the event of a violation of the terms of the affidavit, the tenderer shall be disqualified for committing an unfair act for the purpose of obtaining the right to conclude a contract.

I have read the terms of the affidavit, agree to it and confirm the accuracy of the submitted information.

Consent

For the purposes of state procurement, an affidavit constitutes a written document on the independent determination of a tender bid, the signatory of which, on behalf of the tenderer, confirms the accuracy of the information and circumstances indicated in the document and, in accordance with the procedure established by the legislation of Georgia, bears liability for the accuracy of the said information and circumstances. Violation of the terms defined by the affidavit entails criminal liability in accordance with Article 1951 of the Criminal Code of Georgia.