Technical Regulation − On Approval of the Rules for Determining Overhead Costs, Planned Profit and Other Charges in the State Procurement of Construction Works
Text of the document
Government of Georgia
Resolution No. 241
1 June 2026
Tbilisi
Technical Regulation − On Approval of the Rules for Determining Overhead Costs, Planned Profit and Other Charges in the State Procurement of Construction Works
Article 1🔗
In accordance with paragraph 2 of Article 58 of the Code of Product Safety and Free Movement and Article 12 of the Organic Law of Georgia “On Normative Acts”, the attached Technical Regulation − Rules for Determining Overhead Costs, Planned Profit and Other Charges in the State Procurement of Construction Works shall be approved”.
Article 2🔗
The effect of this Technical Regulation shall not extend to construction works recognized before 1 July 2012, to the state procurement of construction works performed or to be performed with financial resources (including in the form of credit) allocated by a foreign country to an enterprise established with 100% state share participation, to state procurements carried out by means of simplified procurement of cleaning works in areas damaged as a result of the natural disaster caused by heavy rain on 13-14 June 2015, as well as to simplified procurements of construction works that are performed in accordance with subparagraph “d” of paragraph 3 of Article 10¹ of the Law of Georgia “On State Procurement” at a pre-determined, unchanged and single (fixed) price (lump sum), on the basis of a preliminary market study conducted by way of public expression of interest. The Government of Georgia shall determine, in each specific case, the issue of considering the said state procurement contract as a lump sum type.
Article 3🔗
In accordance with subparagraph “b” of paragraph 1 of Article 25 of the Organic Law of Georgia “On Normative Acts”, Resolution No. 55 of the Government of Georgia of 14 January 2014 “On Approval of the Technical Regulation − ‘Rules for Determining Overhead Costs and Planned Profit in State Procurement of Construction Works’” shall be declared invalid.
Article 4🔗
The Resolution shall enter into force upon publication.
Prime Minister Irakli Kobakhidze
Technical Regulation − Rules for Determining Overhead Costs, Planned Profit and Other Charges in State Procurement of Construction Works
1. For calculating the initial estimated price, as well as actual costs, in state procurement of construction works, the Resolutions of the Government of Georgia No. 50 of 7 March 2013, “On the Admission into Effect in Georgia of Technical Regulations of Other Countries, Recognition of Conformity Attestation Documents, Admission into Georgia without Additional Conformity Assessment Procedures of Products Bearing the Relevant Marking, and also on the Placement on the Georgian Market without Restrictions of Products Manufactured in Other Countries and Assigned to the Regulated Sphere”, and No. 52 of 14 January 2014, “On the Recognition and Admission into Effect of Technical Regulations Regulating the Construction Sector in the Territory of Georgia”, shall be applied. For determining the cost of construction works, the rules for planned profit, overhead costs and other charges for general construction works in the cost estimate documentation shall be determined in accordance with the Annex.
2. In the case of an electronic tender, the maximum norms of planned profit, overhead costs and other charges provided for by the Annex to the “Technical Regulation – Rules for Determining Overhead Costs, Planned Profit and Other Charges in State Procurement of Construction Works” (hereinafter – the Technical Regulation) shall be mandatory for procuring organizations for determining the initial estimated price. At the same time, the tenderer/supplier shall, when preparing the cost estimate, including in the case of simultaneous procurement of construction works and design services (Design-build), be guided by paragraph 1 of this Technical Regulation and the conditions provided for by the tender documentation, except for the case provided for by paragraph 3 of this Technical Regulation.
3. When state procurement is carried out on the basis of design and cost estimate documentation, the tenderer/supplier shall not be obliged to present separately in the cost estimate the maximum norms of planned profit, overhead costs and other charges (except for unforeseen costs) provided for by this Resolution and the tender documentation. In such a case, planned profit, overhead costs and other charges (except for unforeseen costs) shall be taken into account in the unit cost.
4. For the purpose of determining the adequacy of price formation, a cost estimate prepared by the resource method shall be submitted by the tenderer/supplier to an institution/person recognized by the State in the relevant field in accordance with the procedure provided for by the legislation of Georgia. The assessment of the compliance of the said cost estimate with the requirements provided for in the construction norms and rules permitted for application by the legislation of Georgia shall be carried out in accordance with Resolution No. 439 of 26 September 2017 of the Government of Georgia “on approval of the Technical Regulation – ‘Methodology for Determining the Adequacy of Price Formation of Construction Works Estimates’”.
5. In the state procurement of works, when construction works and design-estimate services are procured simultaneously (Design-build), the supplier, at the stage of performance of the contract, shall submit to the procuring organization a cost estimate prepared by the resource method, in compliance with the maximum norms of planned profit, overhead costs and other charges provided for by this Resolution and the tender documentation. At the same time, at the stage of performance of the contract, settlement and acceptance-handover of the works may be carried out according to the unit cost provided for in the estimate of the relevant works determined by the procuring organization, where planned profit, overhead costs and other charges are not presented separately (except for unforeseen expenses).
6. In the simplified procurement of construction works:
a) The value of the completed works shall be determined within the unit prices provided for by the estimate of the relevant contract, according to actual expenses. At the same time, in accordance with the procedure provided for by the legislation of Georgia, by a decision of the Government of Georgia, in the case of exceptions established for a specific contract/procurement, when the supplier is released from the obligation to submit a cost estimate, the value of the completed works shall be determined according to actual expenses. Overhead costs, planned profit and other charges shall be charged to the works performed by the subcontractor (direct costs) within the percentage determined by the contract concluded between the supplier and the procuring organization, taking into account paragraph 1 of this Technical Regulation;
b) The rental cost of construction machinery, mechanisms and inventory hired by the company performing the works shall be included in the act of completed works without charging overhead costs, planned profit and other charges;
c) In the case where, by a construction company, for the performance of the installation works given in columns 1 and 2 of Table No. 2 of the Annex, the acquisition of units and equipment is carried out directly from the manufacturer, with subsequent delivery directly to the construction site (without an intermediary company), planned profit shall be charged to their cost price in the act of completed works.
7. The operation of subparagraphs „a“ and „b“ of paragraph 6 of this Technical Regulation shall not extend to the simplified procurement by a municipality of construction works the value of which does not exceed GEL 60,000. In the event that the value of the simplified procurement of construction works by a municipality does not exceed GEL 60,000, the value of the performed works shall be determined according to the unit prices provided for by the cost estimate of the respective works.
8. The operation of subparagraph „a“ of paragraph 6 of this Technical Regulation shall not extend to the simplified procurement by a municipality of construction works that are formalized within the framework of the „Citizen Engagement Development Support“ initiative. In this case, the value of the performed works shall be determined according to the unit prices provided for by the cost estimate of the respective works.
9. The operation of subparagraph „a“ of paragraph 6 of this Technical Regulation shall not extend to the simplified procurement of construction works carried out by means of the electronic procurement procedure (GEO) on the basis of the rules approved by Resolution No. 10-48 of 6 May 2022 of the Sakrebulo of Tbilisi City Municipality „On Approving the Rules for the Replacement of Emergency Multi-Apartment Residential Buildings in the Territory of Tbilisi City Municipality“, within the framework of the „Replacement of Emergency Buildings“ programme, by the project implementer determined by the same rules. In this case, the value of the performed works shall be determined according to the unit prices provided for by the cost estimate of the respective works.
Annex
Marginal norms of overhead costs, planned profit and other charges in the state procurement of construction works
1. For construction, installation and special construction works, the marginal amount of planned profit constitutes 8%, which is charged on the sum of direct costs and overhead costs, excluding the value of equipment and machinery. For the purposes of this Resolution, direct costs are the sum of materials and articles, the operation of machines and mechanisms, and the wages of the works.
2. For general construction and special construction works, the charging of the marginal amount of the percentage of overhead costs in the case of construction works is effected on the entire direct costs (Table No. 1), while in the case of special construction works it is effected on wages (Table No. 2).
Table No. 1
Name of work
Overhead costs from direct costs
Construction works
14.1%
Construction works on objects of state secret significance
15.1%
Construction works performed by internal economic procedure
6.7%
Installation works of metal structures
8.6%
Internal sanitary-technical works
13.3%
All construction works for the construction of tunnels and subways by the closed method, as well as for works after the roofing of tunnels under construction by the open method (except for the facing works of stations, vestibules and underground structures of special purpose)
27.1%
Drilling and blasting works
17.3%
Drilling works on water wells
17.0%
Table No. 2
Name of work
Overhead costs from wages
Installation of equipment and machinery
80.0%
Installation of radio-television and electronic equipment and machinery
84.0%
Laying of low-current networks
77.0%
Laying of intercity communication networks
153.0%
Electrical installation works
87.0%
Installation works for railway signalling, centralisation, blocking and communication
97.0%
Installation works for airport runway facilities and air traffic control systems
99.0%
3. In construction, the percentage of warehouse and supply costs is charged to the estimated cost of material (taking into account the cost of transportation to the site warehouse): on construction, sanitary-technical and electrical-technical materials, products and structures – in the amount of 2%, on equipment and machinery – 1.2% and on metal structures – 0.75% (Collection on the norms of overhead costs in construction – 1983).
3.1. Warehouse and supply costs are charged to the total column of the cost of materials in the estimate and are included in direct costs.
4. When establishing estimated prices for materials and semi-finished products that are manufactured directly under construction site conditions, overhead costs are charged to the manufacturing wage in the amount of 54% (Collection on the norms of overhead costs in construction – 1983).
4.1. The determination of the cost of materials and semi-finished products under construction site conditions shall be carried out individually, by drawing up a separate calculation, the unit cost of which shall be transferred to the main estimate, in the part of the unit price of the material.
5. When determining the cost of construction, the determination of the costs of temporary buildings and structures shall be carried out depending on the purpose of the construction site, as a percentage (r.m. and item IV-9-82).
5.1. Temporary buildings and structures are a list of measures to be carried out, which are intended to ensure the needs of construction and are necessary during the performance of construction and installation works.
5.1.1. The main examples of temporary buildings and structures are:
a) for the purpose of servicing persons employed in construction, the temporary arrangement of newly built permanent buildings and structures, as well as their restoration and repair after the completion of use;
b) the lease and arrangement of existing buildings (premises) with subsequent dismantling;
c) for the production needs of construction, the temporary arrangement of newly built and existing permanent buildings and structures, as well as their restoration and repair after the completion of use;
d) movement on the construction site of structures and details of production, warehouse, auxiliary, residential and public container and prefabricated-disassemblable mobile (inventory) buildings and structures, arrangement of bases and foundations, installation with the necessary cladding, installation of equipment, introduction of engineering networks, creation and improvement of temporary dwellings (including of the shift type), dismantling and demounting, restoration of the site, redistribution of structures and details to the warehouse;
e) arrangement and maintenance of temporary railways, motor and dirt-hauling (earth-hauling) roads, including arrangement and maintenance, with artificial structures, trestles and crossings, of the connecting sections between the roadside road and the linear structure under construction and of the exits to the construction site. Dismantling of roads and exits;
f) arrangement and subsequent dismantling of networks and temporary communications for the supply of electricity, water, heat supply from distribution devices on the construction site to the object and for the provision of a.y.;
g) arrangement and dismantling of temporary suspended (cable) roads and cable cranes for moving materials and details;
h) temporary material-technical closed (with and without heating) and open warehouses intended for materials, products, structures and equipment on the construction site, storerooms for work superintendents and foremen, as well as warehouse premises and sheds existing at construction sites;
i) temporary devices (sites, platforms and others) intended for materials, products, structures and equipment, as well as for loading and unloading works;
j) temporary production workshops (repair-mechanical, reinforcement, joinery-carpentry and others) and forges;
k) temporary-purpose power plants, boilers, pumping stations, compressors, calorifiers, ventilation and other similar units;
l) mobile (movable) temporary stone-crushing-sorting units, concrete-mixing units and units for preparing concrete and mortar with the corresponding devices, existing on the construction territory or at linear construction;
m) temporary units for preparing soils treated with organic and inorganic binders, temporary cement-concrete and asphalt-concrete plants for preparing concrete and asphalt-concrete mixtures, with bitumen storages and other similar structures;
n) polygons for manufacturing reinforced-concrete and concrete products and additional elements with drying chambers;
o) sites and stands intended for the enlargement and preliminary assembly of equipment;
p) bases for assembling railway track sections;
q) buildings and equipment existing in temporary quarries, except roads;
r) arrangement and dismantling of temporary networks of compressed air, water, energy supply, communications and other temporary communications in shafts, tunnels and subways;
s) temporary laboratories for testing construction materials and products on construction sites;
t) the arrangement of foundations and footings for those machines-mechanisms for which these costs are not envisaged in the cost of a machine-hour (except for the rail tracks of tower, jib and portal-jib cranes);
u) temporary structures related to fire-prevention measures and security at the construction site and in temporary accommodation;
v) temporary offices of construction-installation sections, construction-installation trains, construction directorates or production sites;
w) special and architecturally designed fences and enclosures existing in cities;
x) all other safety measures related to construction (temporary fences, closing of lift shafts, closing of stairwells, closing of the perimeter on floors, and a.y.).
5.2. The costs of temporary buildings and structures are established as a percentage, are determined on the basis of the name of the construction (r.m. and ch. IV-9-82) and shall be charged in the estimate after the charging of overhead costs and planned profit. During the expansion-reconstruction of existing production, or when carrying out works of the next stage on the same construction site, the estimate norm is taken with a coefficient of 0.8 (Table No. 3).
Table No. 3
No.
Types of construction of enterprises, buildings and structures
Norm %
Coeff. 0.8
Industrial construction
1
Enterprises of the ferrous metallurgy industry (except mining)
3.9
3.1
2
Enterprises of the non-ferrous metallurgy industry (except mining)
2.8
2.2
3
Enterprises of the oil-extracting and gas industry. With total estimated cost in million GEL:
a - up to 230
2.9
2.3
b - more than 230
2.7
2.2
c
Production of oil, gas and gas-condensate deposit (field) facilities
3.9
3.1
4
Machine-building enterprises
3.1
2.5
5
Mining industry enterprises:
a - construction of new mines and shafts
5.0
4.0
b - construction of concentrating plants and opening of new horizons (deposits) in operating mining enterprises
3.5
2.8
c - construction of coal open pits
3.8
3.0
6
Chemical industry enterprises:
a - oil-refining and petrochemical plants
4.3
3.4
b - other chemical industry facilities
3.3
2.6
7
Peat and shale industry enterprises
4.6
3.7
8
Shipbuilding and ship-repair enterprises
4.6
3.7
9
Timber harvesting and processing industry enterprises
2.8
2.2
10
Construction materials industry and construction industry enterprises with total estimated cost in million GEL:
a - up to 80
2.5
2.0
b - more than 80
2.2
1.8
11
Cellulose-paper industry enterprises
4.0
3.2
12
Light industry enterprises with total estimated cost, million GEL:
a - up to 40
2.4
1.9
b - more than 40
2.1
1.7
13
Food industry enterprises with total estimated cost, million GEL:
a - up to 20
2.6
2.1
b - more than 20
2.0
1.6
14
Medical industry enterprises with total estimated cost, million GEL:
a - up to 80
2.1
1.7
b - more than 80
1.7
1.4
Energy construction
15
Thermal power plants with capacity:
a
with condensing units up to 300 MW (300 thousand kW), with total capacity up to 2400 MW (2400 thousand MW)
5.1
4.1
b
with condensing units of 500 MW (500 thousand kW) and 800 MW (800 thousand kW), with total capacity up to 5000 MW (5000 thousand kW)
4.7
3.8
16
Nuclear power plants with capacity:
a - 2000 MW (2000 thousand kW)
9.3
7.4
b - 4000 MW (4000 thousand kW)
7.5
6.0
17
Industrial-heating thermal power plants with capacity:
a - up to 300 MW (300 thousand kW)
5.4
4.3
b - more than 300 MW (300 thousand kW)
4.8
3.8
18
Independent boiler houses
3.3
2.6
19
Overhead power transmission lines of 35 kV and more
3.1
2.5
20
Transformer substations of 35 kV and more, other energy construction facilities
3.9
3.1
21
Overhead power transmission lines and transformer substations with capacity of 0.4 - 0.35 kV (including lighting substations)
2.5
2.0
Transport construction
22
New railways, without tunnels and bridges (road bridges), with length of more than 50 m
7.8
6.2
23
Second tracks of main railway lines without tunnels and bridges (road bridges), with length of more than 50 metres
5.3
4.2
24
Electrification of railways
4.2
3.4
25
Development of railway junctions, stations, reconstruction of railways (reinforcement of individual sections and other directions) and other types of construction on operating networks
3.4
2.7
26
State-wide, republican significance and local motor roads (with hard surface) of category I-V, without tunnels and bridges (road bridges), with length of more than 50 m:
a - use of temporary mobile asphalt-concrete and cement-concrete plants during road construction
6.2
5.0
b - use of existing stationary plants for obtaining asphalt-concrete or cement-concrete during road construction
4.3
3.4
27
Subways
6.0
4.8
28
Bridges of railways and motor roads with length of more than 50 m and road bridges
9.0
7.2
29
City bridges and road bridges:
a - at places of permanent deployment of bridge-building organisations
4.6
3.7
b - at other points
6.1
4.9
30
Aerodromes:
a - aerodrome areas
4.6
3.7
b - buildings and structures of technical service and service zones
3.1
2.5
31
Sea ports and structures
5.3
4.2
32
River transport facilities
5.1
4.1
33
Communication (collector) tunnels
5.9
4.7
Housing and civil construction in cities and urban-type settlements
34
Residential houses and improvement:
a - residential houses
1.0
0.8
b - micro-districts, blocks, complexes of residential and civil buildings (including external networks and improvement)
1.1
0.9
c - improvement of cities and settlements (including works on arrangement of driveways, pavements, green plantings)
1.3
1.0
35
Schools, kindergartens, nursery-kindergartens, shops, administrative buildings, cinemas, theatres, art galleries and other buildings of civil construction
1.5
1.2
36
Educational and medical buildings and structures, scientific-research, design and construction institutes
1.5
1.2
37
Public utility facilities (bathhouses, laundries, crematoria, etc. a.y.)
1.6
1.3
38
Sewerage, external water supply, heat supply and gas supply networks within the city
1.5
1.2
39
Trolleybus and tram lines
1.7
1.4
40
High-speed tram lines
3.8
3.0
41
Sanatoria, rest homes, tourist camps and boarding houses
2.3
1.8
Other types of construction
42
Buildings and structures for receiving, storing and processing grain
3.0
2.4
43
Construction of facilities of the Ministry of Defence:
a – for general military and special purposes
3.8
3.0
b – for housing, barracks, public utility and cultural-community purposes
2.8
2.2
44
Communication structures and networks:
a
– stationary structures, cable trunk lines, overhead lines of zonal (district) and rural communications, radio relay lines
3.2
2.6
b – city telephone networks and lines of inter-station communication nodes
2.5
2.0
c – other facilities (post, district communication nodes, etc. a.y.)
2.7
2.2
d – radio broadcasting and television facilities
4.2
3.4
45
Construction of agricultural facilities, including housing and civil construction in rural areas (except construction of motor roads and electrification facilities)
2.9
2.3
46
Construction of water management facilities and hydrotechnical structures, fish amelioration and pond fish farming structures, fish hatcheries producing fish stock from roe, and fish industry farms
4.5
3.6
47
Trunk pipelines outside the city:
a – water supply, sewerage
3.0
2.4
b
gas pipelines and oil pipelines:
b1 – site structures (compressors and pumping stations)
7.9
6.3
b2 – line part (electrochemical protection and communication technical lines)
2.7
2.2
c – heat networks
2.2
1.8
48
Treatment facilities
4.2
3.4
49
Enterprises of other branches of industry, by total estimated cost, million GEL:
a – up to 80
2.5
2.0
b – more than 80
2.3
1.8
5.3. The percentage amount for temporary buildings and structures shall not be subject to change in the estimate of the design organisation and the tenderer (nor shall it be subject to itemisation in the act of completed works, Form No. 2), except in cases where the design decision justifies the necessity of increasing the costs indicated as a percentage in the table. In such a case, the costs of temporary buildings and structures shall be itemised and accordingly entered in the estimate (instead of the percentage amount).
5.4. When drawing up an estimate for works not indicated in the table (e.g.: hydroelectric power plants, tunnels, sports complexes, etc. a.y.), the costs of temporary buildings and structures shall be calculated on the basis of the construction organisation project, and the costs shall be itemised and accordingly entered in the estimate (instead of the percentage amount).
6. When determining the construction cost, the percentage costs shall be added in the case of performance of works in winter conditions (r.m. and item IV-7-82).
6.1. When carrying out works in winter conditions, costs are established for the climatic zones of Georgia and depending on the designation of the construction, which is determined as a percentage and shall be added to the estimate after temporary buildings and structures.
6.2. In accordance with the construction organization project, if the implementation of the construction does not include the winter period, the specified charge shall not be taken into account.
6.3. When carrying out construction and installation works in winter conditions, costs are established for the climatic zones of Georgia.
6.4. When drawing up the estimate, the norms for costs are applied according to the types of construction.
6.5. The norm is differentiated into temperature zones in accordance with the temperature conditions characteristic of the winter period (Table No. 4).
Table No. 4
Temperature zones
Average and monthly average negative (-) temperature of the winter period, °C
I
up to 3
II
up to 5
III
up to 8
6.6. In the norms, the average annual value of the specific weight of the duration of the winter period is adopted (Table No. 5).
Table No. 5
Temperature zone
Specific share of the winter period on average per year
I
0.23
II
0.33
III
0.40
6.7. Estimated norms for additional costs according to the types of construction, in accordance with Table No. 6 and the note.
Table No. 6
No.
Types of construction
Zone I
Zone II
Zone III
1. Industrial construction
1
Enterprises of the oil and gas industry
0.8
1.6
3.1
2
Enterprises of the oil refining and petrochemical industry
0.6
1.4
2.7
3
Enterprises of the coal industry (except tunnel-driving works)
0.7
1.6
3.4
4
Enterprises of ferrous metallurgy
0.6
1.3
1.9
5
Enterprises of non-ferrous metallurgy
0.5
1.0
1.7
6
Enterprises of the chemical industry
1.0
1.7
2.8
7
Enterprises of the energy and machine-building industries
0.7
1.3
2.3
8
Enterprises of tractor and agricultural machine building
0.7
1.3
2.1
9
Enterprises of light and other machine building
0.6
1.3
2.1
10
Enterprises of the electrical engineering industry
0.7
1.5
2.4
11
Enterprises of machine-tool and instrument-making industries
0.7
1.4
2.1
12
Enterprises of tool-making and automation equipment
0.6
1.2
2.2
13
Enterprises of communications
0.6
1.2
2.2
14
Enterprises of the automotive industry
0.7
1.4
2.3
15
Enterprises of the shipbuilding industry
0.8
1.5
2.3
16
Enterprises of the aviation industry
0.7
1.3
2.4
17
Enterprises of the printing industry
0.6
1.1
1.8
18
Enterprises of the timber harvesting and fuel industry
0.8
1.7
3.6
19
Enterprises of the pulp-and-paper and wood-processing industries
0.9
1.9
3.5
20
Enterprises of the construction materials industry: - plants and polygons of precast reinforced concrete and concrete structures
0.9
1.5
2.6 - crushing and sorting plants, quarries of clay and sand-gravel materials
0.6
1.4
2.5 - plants of wall materials, ceramic products, roofing and waterproofing materials
0.8
1.5
2.6 - Cement plants, asbestos-cement and sanitary-technical industry enterprises
0.7
1.3
2.3 - Glass industry enterprises
0.4
0.8
1.3
21
Light industry enterprises
0.9
1.6
2.6
22
Food industry enterprises
0.7
1.2
2.1
23
Meat industry enterprises, enterprises for primary processing of agricultural products
0.8
1.3
2.2
24
Dairy industry enterprises, sugar and canning factories
0.6
1.0
1.7
25
Fish farming enterprises
0.7
1.4
2.4
26
Medical industry enterprises
0.6
1.0
1.7
27
Microbiological industry enterprises
0.7
1.5
2.5
28
Warehouses and storages
0.6
1.3
2.5
29
Elevators of precast reinforced concrete
0.6
1.1
2.1
30
Elevators of monolithic reinforced concrete
2.4
3.7
5.1
31
Refrigerators
0.8
1.7
3.3
2. Energy construction
1
Thermal power plants
0.7
1.6
3.1
2
Hydroelectric power plants
0.9
1.8
3.5
3
Electrical substations
0.6
1.2
2.1
4
Heating networks
0.6
1.3
2.5
5
Overhead power transmission lines of 35 kV and more
0.3
0.7
1.0
6
Overhead power transmission lines of 0.4-10 kV
0.4
1.0
1.9
3. Road construction
1
Route development and preparation of the construction area
0.5
1.5
2.6
2
Earth embankment from borrow pits: ordinary
2.1
4.0
7.0
3
Earth embankment from borrow pits: drainage
0.5
1.2
2.4
4
Earth embankment from borrow pits: rocky
0.2
0.7
1.3
5
Reinforcement of the earth embankment and regulatory structures
0.3
0.5
0.8
6
Large bridges with reinforced concrete span structure
1.5
2.8
4.2
7
Large bridges with metal span structure
0.6
1.3
2.0
Note: the expenditure norm for above-ground metro lines shall be adopted according to norm PP 3.1-3.13
8
Other artificial structures
0.9
1.9
3.4
9
Superstructure of tracks
0.5
0.9
1.3
10
Railway electrification, other remaining energy structures and devices
0.8
1.4
2.0
11
Communication, signalling, centralization and blocking devices
0.6
1.6
3.0
12
Water supply and sewerage (excluding external pipelines and external networks)
1.3
2.7
5.1
13
Road pavement: precast reinforced concrete slabs
0.3
0.5
0.6
14
Road pavement: cement concrete
1.3
1.8
2.1
15
Road pavement: asphalt concrete
1.4
1.5
1.6
16
Road pavement: black gravel
1.0
1.2
1.3
17
Road pavement: gravel or crushed stone
0.4
0.7
0.8
4. Metro construction
1
Work by the closed method, with air heating
0.4
0.6
1.0
2
The same, without heating
0.2
0.4
0.7
3
Work by the open method
0.8
1.6
2.9
5. Construction of oil-gas product pipelines
1
In the regions of Georgia
0.4
0.7
1.5
6. Construction of production and service buildings for the operation of transport:
1
Railway transport
1.4
2.0
3.0
2
Road transport
0.7
1.2
1.8
3
Sea transport
0.6
1.3
2.4
4
River transport
0.6
1.1
1.7
5
Air transport (except the airfield)
0.5
1.1
2.0
6
Airfield of air transport
1.0
1.6
2.9
7. Construction of communication buildings and structures
0.7
1.3
2.4
8. Agricultural construction
0.7
1.3
2.3
Note: For construction of agricultural purpose, livestock and poultry premises and farms, greenhouse combines, timber-protective stations, game-breeding farms, fruit-and-vegetable and seed storages, repair workshops, supply bases and warehouse premises, agro-industrial complexes and a.y. facilities are meant.
9. Construction of land reclamation and irrigation economy
1
Irrigation and drainage
2.0
3.1
2.8
10. Construction of housing and public buildings
1
Residential houses: large-panel
0.3
0.5
1.0
2
Residential houses: brick and block
0.4
0.7
1.2
3
Residential houses: wooden
0.4
0.8
1.2
4
Residential houses: public purpose buildings (schools, educational institutions, clubs, nurseries and kindergartens, hospitals, sanatoriums, rest homes and others. 0.61.11.9
11. Mining and tunnel-driving works (costs without a common shaft)
1
Shaft sinking (including the costs of heating the air supplied to the shaft)
0.7
1.8
2.8
2
Including air heating costs
0.6
1.6
2.4
3
Horizontal and inclined tunnels (including the costs of heating the air supplied in the tunnels)
1.2
2.1
3.0
4
Including air heating costs
1.1
1.9
2.5
12. Construction of external pipelines
1
Water supply and gas pipelines in soft soils (with earthworks)
0.6
1.2
2.1
2
Sewerage in soft soils (with earthworks)
0.8
1.4
2.4
3
Water supply, gas pipelines or sewerage in rocky soils
0.3
0.6
1.0
4
Pumping stations: water supply
1.6
2.2
3.3
5
Pumping stations: sewerage
1.8
2.7
3.9
6
Treatment facilities: water supply
0.8
1.4
2.6
7
Treatment facilities: sewerage
1.0
1.6
2.6
13. Other types of construction
1
Collectors for underground structures
0.8
1.6
3.0
2
Underground pedestrian crossing
0.6
1.2
2.0
3
Bank reinforcement and embankment structures
0.6
1.2
2.2
4
Planting and transplanting of trees and shrubs with preparation of planting sites (including the cost of trees and shrubs)
2.1
5.0
10.5
Note:
1. The norm of winter conditions costs in the construction of residential houses whose project does not provide for the laying of external networks, vertical planning and improvement works is given in Table No. 6 (paragraphs: 10.1, 10.2 and 10.3).
2. In the construction of residential houses where the project provides for external engineering networks, internal block planning, driveways, improvement, landscaping and a.y., the norm of costs is determined in accordance with Table No. 7:
Table No. 7
Type of construction
Temperature zone I
Temperature zone II
Temperature zone III
Large-panel, volumetric-block, wooden
0.6
1.1
1.9
Brick and block
0.7
1.2
2.2
3. The division of the territory of Georgia according to temperature zones, according to winter periods (beginning and end) and coefficients, in relation to the norms of Table No. 6, is established in accordance with Table No. 8.
Table No. 8
No.
Name of districts
Zone
Beginning
End
Coefficient
1
Lentekhi, Oni
I
20.XI
10.III
1.3
2
Akhaltsikhe, Dmanisi, Znauri, Akhalgori, Mestia, Tetri Tskaro and Tskhinvali
I
10.XII
28.II
1.0
3
Aspindza, Ambrolauri, Bolnisi, Gori (including Gori), Kareli and Khashuri
I
25.XII
25.II
0.8
4
Akhmeta, Khelvachauri, Marneuli, Khulo, Dedoplistskaro, Chokhatauri
I
15.XII
10.II
0.7
5
Gardabani, Gurjaani, Kvareli, Kaspi, Lagodekhi, Mtskheta, Sagarejo, Sighnaghi, Tsageri, Telavi. Cities: Tbilisi, Rustavi, Tkibuli, Chiatura and the subordinate territories under the governance of these cities
I
25.XII
5.II
0.5
6
The remaining districts of the first zone, except Keda, Kobuleti, Shuakhevi and all districts of Abkhazia
I
15.I
1.II
0.2
7
Java
II
20.XI
20.III
1.0
8
Adigeni, Akhaltsikhe, Borjomi, Dusheti, Tianeti and Tsalka
II
25.XI
15.III
0.9
9
Ninotsminda, Stepantsminda
III
20.XI
1.IV
1.0
4. When performing works under winter conditions, expenses shall not be subject to change in the cost estimate of the design organisation and the tenderer (nor shall they be subject to itemisation in the act of completed works, Form No. 2).
5. When determining the construction cost, the percentage of unforeseen expenses for an individual project shall be determined ((r.m. and note 1.02.01-85):
a) for reinforced concrete bridges with a span length of more than 80 metres, for metal bridges with a metal span length of more than 100 metres, for tunnels, for underground railways, for hydroelectric power stations, for large bridges with supports having deep foundations, for mining combines, for facilities for the development of oil and gas fields, and for unique, technically complex public buildings and structures – 10%;
b) for metallurgical, chemical, oil-refining, gas-refining, pharmaceutical, microbiological plants, for the construction of a land reclamation facility and for the construction of marine hydraulic structures (berths of 13 metres and more in depth, shore protection structures, breakwaters) and for the reconstruction-restoration and recovery-rehabilitation of buildings and structures – 7%;
c) industry, agriculture, transport, communications and other enterprises and structures, linear structures, public buildings and structures (except residential buildings) – 5%;
d) residential buildings – 3%.
5.1. Unforeseen expenses may be used in the event of unforeseen works (works not covered by the cost estimate), in agreement with the purchaser, which must be justified by the relevant documentation and a cost estimate drawn up on its basis. The percentage of unforeseen expenses shall be accrued before VAT.
6. When determining the construction cost, the prepared cost-estimate documentation shall contain an explanatory note and, accordingly, all the above-mentioned accrual matters shall be taken into account.
7. When procuring construction works, taking into account existing resources, in accordance with the design-estimate and tender documentation, the qualitative components and characteristics of the materials to be used shall be taken into account.
8. In the estimate, additional coefficients required for the works may also be provided for, in accordance with the circumstances established by the explanatory card.