On Approval of the Grounds, Principles and Rules for the Use of Price Indexation for the Purpose of Facilitating the Implementation of Infrastructure Projects

Machine translation. This text was translated from Georgian automatically and may contain inaccuracies. Only the Georgian text is legally binding: the original on legali.ge · the official publication on matsne.gov.ge. Translation of the consolidated version of 03.06.2026.

This document in other languages: ქართული (original) · Русский · Türkçe

Type of act
Resolution of the Government of Georgia
Number
№245
Date adopted
03.06.2026

Text of the document

📑 Contents (21 articles)

Government of Georgia

Resolution No. 245

3 June 2026

Tbilisi

On Approval of the Grounds, Principles and Rules for the Use of Price Indexation for the Purpose of Facilitating the Implementation of Infrastructure Projects

Article 1🔗

On the basis of paragraph 5¹ of Article 21 and subparagraphs „a.b“ and „b“ of Article 24³ of the Law of Georgia „On State Procurement“, as well as subparagraphs „i“ and „gg³“ of Article 5 of the Law of Georgia „On the Structure, Powers and Rules of Activity of the Government of Georgia“, the attached „Grounds, Principles and Rules for the Use of Price Indexation for the Purpose of Facilitating the Implementation of Infrastructure Projects“ shall be approved.

Article 2🔗

The Resolution applies to contracts to be concluded for the purpose of procurement of works in accordance with the Law of Georgia „On State Procurement“, including state procurement related to state secrets, as well as, in the cases provided for by Articles 12 and 13 of this Resolution – to contracts concluded/to be concluded within the framework of road infrastructure projects and to announced/to be announced tenders.

Article 3🔗

The LEPL − State Procurement Agency shall, within 10 working days from the entry into force of this Resolution, ensure that the relevant amendments are made to the relevant subordinate normative acts.

Article 4🔗

After the amendments made in accordance with Article 3 of this Resolution, purchasers shall, where necessary, ensure that the relevant contractual terms related to price indexation are reflected in existing contracts.

Article 5🔗

For the purposes of the rules approved by this Resolution:

a) the Legal Entity of Public Law − National Statistics Office of Georgia (hereinafter − Geostat) shall ensure the introduction of accompanying procedures, in accordance with which the calculation of price indexation provided for by the rules approved by this Resolution shall be carried out (price indexation calculator);

b) the LEPL − Levan Samkharauli National Bureau of Forensic Expertise (hereinafter − the Bureau) shall, in the cases provided for by the transitional provisions of the rules approved by this Resolution, ensure the calculation/confirmation of the proportion (share) of the component subject to price indexation (diesel). The proportion (share) of the component subject to price indexation (diesel) shall be calculated by the Bureau in accordance with the value determined for the operation of machinery and mechanisms published publicly by the Bureau.

Article 6🔗

In accordance with the rules approved by this Resolution, the purchaser shall ensure the determined compensation of price indexation within the limits of its allocations.

Article 7🔗

Where, in accordance with the rule approved by this Resolution, compensation is received through price indexation, it shall not be permitted, on the same basis, to raise the claim provided for by the first and 2nd paragraphs of Article 36 of the rule approved by Order No. 12 of 14 June 2017 of the Chairman of the LEPL — State Procurement Agency "On the approval of the rule for conducting an electronic tender".

Article 8🔗

The rule approved by this Resolution shall not apply to cases where compensation of costs caused by a change in prices (indexation) is already being carried out on the basis of the conditions and mechanisms defined by another act of the Government of Georgia.

Article 9🔗

All administrative bodies shall be required to take into account the measures defined by this Resolution.

Article 10🔗

The supplier shall be obliged to apply to Geostat for the purpose of obtaining the conclusion defined in Article 3 of the rule approved by this Resolution.

Article 11🔗

In the event of non-fulfilment by the supplier of the obligation provided for by Article 10 of this Resolution, the purchaser shall be entitled to call, in full, the bank guarantee for the performance of the contract submitted by the supplier within the framework of the contract (if such exists), and, in the absence of a bank guarantee for the performance of the contract, to apply the relevant sanctions provided for by the contract (penalty and/or termination of the contract).

Article 12🔗

Until 1 January 2027, price indexation in respect of road infrastructure projects shall be carried out in accordance with the temporary rule defined by the transitional provisions of the rule approved by this Resolution.

Article 13🔗

The temporary rule provided for by Article 12 of this Resolution shall apply to:

a) works performed from 1 April 2026 within the framework of ongoing contracts;

b) works performed within the framework of tenders announced from 1 June 2026 until 1 January 2027;

c) works performed within the framework of ongoing tenders and tenders announced before 1 June 2026.

Article 14🔗

In the case provided for by Article 12 of this Resolution, the supplier shall be entitled, within 60 calendar days from the entry into force of this Resolution, to apply to the purchaser with a request to extend to the contract the temporary rule defined by the transitional provisions of the rule approved by this Resolution. In the event of breach of the said time limit, the regulations provided for by the temporary rule shall not apply to the supplier.

Article 15🔗

In the case provided for by subparagraphs "b" and "c" of Article 13 of this Resolution, the supplier shall be entitled, within 60 calendar days from the conclusion of the contract, to apply to the purchaser with a request to extend to the contract the temporary rule defined by the transitional provisions of the rule approved by this Resolution. In the event of breach of the said time limit, the regulations provided for by the temporary rule shall not apply to the supplier.

Article 16🔗

The main provisions of the rule approved by this Resolution shall apply to tenders announced from 1 January 2027.

Article 17🔗

The Resolution shall enter into force upon publication.

Prime Minister Irakli Kobakhidze — Grounds, principles and rules for the use of price indexation for the purpose of facilitating the implementation of infrastructure projects

Article 1. General Provisions🔗

1. The grounds, principles and rules for the use of price indexation for the purpose of facilitating the implementation of infrastructure projects (hereinafter – the Rules) determine the grounds, principles and rules for the use of price indexation within the framework of the implementation of infrastructure projects.

2. The purpose of these Rules is to determine, for the purpose of facilitating the implementation of infrastructure projects, in the cases provided for by these Rules, the grounds and principles for the reimbursement of costs caused by price changes (indexation).

Article 2. Conditions for the use of price indexation🔗

1. For the purposes of these Rules, price indexation is the amount to be reimbursed to the supplier within the framework of the performance of works, where the grounds provided for by these Rules exist.

2. Price indexation provided for by these Rules shall be applied to works performed within the framework of tenders announced from 1 January 2027 (hereinafter – the indexation period).

3. Price indexation shall not apply to:

a) works performed in a period of delay through the fault of the supplier;

b) works procured/to be procured by simplified procurement;

c) any period other than the indexation period provided for by paragraph 2 of this Article;

d) projects financed by international financial institutions and donor organisations;

e) tenders announced under the rules of international financial institutions and donor organisations;

f) contracts where the period for the performance of works is 12 months or less.

4. Price indexation shall be applied only to works performed in accordance with the terms of the contract after 12 months have elapsed from the commencement of the works. Indexation shall be applied monthly after 12 months have elapsed.

5. In accordance with paragraph 4 of this Article, price indexation shall be applied only within the framework of contracts in which, in accordance with the tender documentation, a monthly schedule is provided for.

6. If the period for the performance of the works provided for by the contract exceeds 12 months and the supplier ensures the completion of the works within 12 months or less, price indexation, in accordance with the principles and conditions established by these Rules, shall apply to the works actually performed in the last month(s) in accordance with the number of months by which the supplier completed the works between the completion deadline provided for by the contract and 12 months. In the said case, the supplier shall not be obliged to reimburse the negative difference caused by price indexation, if any.

Article 3. Rule for the Calculation and Compensation of Price Indexation🔗

1. For price indexation, the relevant index established by the Legal Entity of Public Law – National Statistics Office of Georgia (hereinafter – Geostat) shall be used (construction cost index).

2. In the case provided for by paragraph 2 of Article 2 of this Rule, the month corresponding to the date 28 days prior to the opening of the tender shall be used as the base. The said month shall determine the base period of the index, and, accordingly, the base index existing in the said period is 100 (hereinafter – the base index).

3. Price indexation shall not apply to labour remuneration, except where it is carried out within the percentage amount provided for by paragraph 4 of this Article.

4. Price indexation shall apply to 60% of the value of works performed under the contract (hereinafter – the amount of the indexation sum).

5. In accordance with this Article, compensation shall be made monthly in accordance with the submitted documentation confirming the performed works, by means of the relevant index established monthly by Geostat in relation to the base index, in accordance with paragraphs 7 and 8 of this Article.

6. For the value of works performed in the indexation period determined by this Rule, price indexation shall be carried out 49 days before the last day of the period of works performed monthly, according to the index for the relevant month established by Geostat in relation to the base index.

7. For the purposes of this Rule, the basis for compensation shall be the submission by the supplier to the customer of the conclusion issued by Geostat, in compliance with the principles provided for by Articles 2 and 3 of this Rule.

8. The conclusion provided for by paragraph 7 of this Article shall confirm the increase/decrease in the value to be compensated to the supplier as a result of price indexation, indicating the amount.

9. The supplier shall be responsible for the accuracy and completeness of the information provided to Geostat.

10. In the event of detection of the provision by the supplier to Geostat of incorrect/incomplete information, the purchaser shall return the documentation to the supplier for correction.

11. In the event of an increase in the contract value on the basis of price indexation, the supplier shall not be entitled to request an additional advance payment in respect of the part of the amount determined by the said increase.

12. The purchaser shall not be entitled to request an increase in the amount of the bank guarantee for the performance of the contract in proportion to the amount of the increase in the contract value caused by price indexation.

13. In the event of unilateral termination of the contract by the purchaser on the grounds of non-performance and/or improper performance of an obligation, the supplier shall be obliged to return to the purchaser the increased value compensated as a result of price indexation.

Article 4. Transitional Provisions🔗

1. Until 1 January 2027, within the framework of road infrastructure projects, price indexation shall be carried out in accordance with the rule defined by this Article:

a) for works performed from 1 April 2026 within the framework of current contracts;

b) for works performed within the framework of tenders announced from 1 June 2026 to 1 January 2027;

c) for works performed within the framework of current tenders and tenders announced before 1 June 2026.

2. The price indexation provided for by this Article shall not apply to:

a) works performed in the overdue period through the fault of the supplier;

b) works purchased/to be purchased through simplified procurement;

c) any period other than the indexation period provided for by paragraph 1 of this Article;

d) projects financed by international financial institutions and donor organizations;

e) tenders announced under the rules of international financial institutions and donor organizations.

3. For the price indexation provided for by this Article, the relevant index established by Geostat shall be used.

4. In the case provided for by subparagraphs “a” and “b” of paragraph 1 of this Article, the month corresponding to the date 28 days before the opening of the tender shall be used as the base period, while in the case provided for by subparagraph “c” of paragraph 1 of this Article, December 2025 shall be used as the base period. The base period of the price shall be determined by the said month.

5. In the cases provided for by this Article, for the purpose of promoting the implementation of road infrastructure projects, the following two components shall be subject to price indexation: bitumen and diesel.

6. For the purposes of this Article, in contracts concluded/to be concluded for the procurement of works in accordance with the Law of Georgia on Public Procurement, as well as in tenders announced and to be announced before 1 January 2027, the proportion (share) of each component subject to price indexation shall be determined. The calculation of the diesel share in each project shall be confirmed/calculated by the LEPL – Levan Samkharauli National Bureau of Forensic Expertise. At the same time, a fixed coefficient shall be determined, which constitutes the non-adjustable part of the contractual value, while within the framework of current repair works, 85% constitutes the non-adjustable part of the contract and the remaining 15% constitutes the part subject to indexation (adjustable part).

7. For the purposes of this Article, the calculation of price indexation shall be carried out using the following formula: Pn = a + b Ln/ Lo + c En/Eo, where:

“Pn” is the adjustment multiplier that shall be applied to works performed in period “n”;

“a” is a fixed coefficient that constitutes the non-adjustable part of the contractual value;

“b”, “c” are the proportion (share) of components subject to indexation;

“Ln”, “En” represent the prices existing as of the date 49 days before the current (reporting) period for period “n”;

“Lo”, “Eo” represent the base period prices.

8. Within the scope of current repair works (which does not involve construction, rehabilitation, modernization, reconstruction), the calculation of the price indexation provided for by this Article shall be carried out using the relevant index established by Geostat (construction cost index).

9. In the case provided for by this Article, the price indexation shall be submitted by the supplier/supervisor, in accordance with the procedure provided for by the relevant contract for payment for completed works. The supplier shall be responsible for the accuracy and completeness of the data used to determine the prices provided for by this Article.

10. Paragraphs 9–13 of Article 3 of this Rule shall also apply to the cases provided for by this Article.

11. For determining the prices of components subject to the price indexation provided for by this Article, the relevant indices published by Geostat shall be used.