Property and housing
Developer missed the completion date: what to do under Georgian law
What to do when a developer misses the agreed handover date for an apartment: the penalty, damages, withdrawal from the contract with a refund, the developer's likely objections, and limitation periods.
What to do
- Find the handover date and the penalty clause in the contract. Delay is non-performance within the set period (Civil Code, Art. 400). There is no delay if the cause does not depend on the developer's fault (Civil Code, Art. 401). The limitation period for property claims is 6 years (Civil Code, Art. 129).
- Claims for the flat: a penalty (პირგასამტეხლო) exists only by agreement of the parties (Civil Code, Art. 417) and only in writing (Civil Code, Art. 418). A penalty for delay may be claimed together with the handover of the flat (Civil Code, Art. 419). Losses caused by the delay (for example, rent of other housing) are recoverable (Civil Code, Art. 404), including lost profit (Civil Code, Art. 411), but only foreseeable direct damage (Civil Code, Art. 412).
- Getting money back: a written claim, then withdrawal from the contract after the additional period set by the buyer has expired (Civil Code, Art. 405). Without such a period, withdrawal is possible if the contract expressly tied its continuation to the deadline, or if the deadline has become pointless (Civil Code, Art. 405). It is not possible for an insignificant breach (Civil Code, Art. 405). Withdrawal is made by notice (Civil Code, Art. 355). The developer returns what was paid (Civil Code, Art. 352), plus damages for non-performance (Civil Code, Art. 407).
- The developer's objections: where circumstances have changed, the contract should first be adapted by agreement, not extended unilaterally (Civil Code, Art. 398). An unfair standard term (an extension of the deadline without consequences) is void (Civil Code, Art. 346). The court may reduce a disproportionate penalty (Civil Code, Art. 420).
- Court: the district (city) court. The claim may be secured by attaching the developer's property and funds (Civil Procedure Code, Art. 198). Check the registry extract for the plot (mortgage, repeat sale).
- Where to apply: the district (city) court; the Public Registry, for an extract.
- Evidence: the contract (handover date, penalty), payments, notices of postponement, rental agreement and receipts, the claim with proof of dispatch.
- Pitfalls: there is no 'statutory penalty' for buyers; withdrawal without the required additional period; a supplementary agreement on postponement without a penalty clause; if the developer is already insolvent, a different strategy applies.
Be sure to check
- penalty only under a written contract term; the court may reduce it; it can be claimed together with the handover of the flat
- losses from the delay (rent, lost profit) independently of the penalty
- withdrawal from the contract after an additional period and notice; refund and damages
- the developer's objections (no fault, changed circumstances) and limitation periods
Provisions in force (texts in Georgian)
საქართველოს სამოქალაქო კოდექსი
- მუხლი 405. დამატებითი ვადის დაწესება ვალდებულების დარღვევისას
- მუხლი 129. სახელშეკრულებო მოთხოვნათა ხანდაზმულობის ვადა
- მუხლი 401. ვალდებულების შესრულების შეუძლებლობა
- მუხლი 404. კრედიტორის უფლება ზიანის ანაზღაურებაზე
- მუხლი 411. ზიანის ანაზღაურება მიუღებელი შემოსავლისათვის
- მუხლი 412. ზიანი, რომელზედაც ვრცელდება ანაზღაურების მოვალეობა
- მუხლი 417. ცნება
- მუხლი 418. პირგასამტეხლოს განსაზღვრის ფორმა
- მუხლი 419. პირგასამტეხლოს გადახდისა და ვალდებულების შესრულების ერთდროულად მოთხოვნის დაუშვებლობა
- მუხლი 420. პირგასამტეხლოს შემცირება სასამართლოს მიერ
- მუხლი 352. ხელშეკრულებაზე უარის თქმის შედეგები
- მუხლი 407. ზიანის ანაზღაურება ხელშეკრულებიდან გასვლისას
- მუხლი 398. ხელშეკრულების მისადაგება შეცვლილი გარემოებებისადმი
- მუხლი 346. ნდობისა და კეთილსინდისიერების პრინციპების საწინააღმდეგო პირობათა ბათილობა
- მუხლი 400. ცნება
- მუხლი 392. მოვალის პასუხისმგებლობა კრედიტორის მიერ ვადის გადაცილებისას
- მუხლი 393. კრედიტორის მიერ ვადის გადაცილების შედეგები
- მუხლი 403. პროცენტის გადახდა ფულადი თანხის გადახდის ვადის გადაცილებისას
- მუხლი 354. ხელშეკრულებიდან გასვლის შედეგად წარმოშობილ ვალდებულებათა შესრულება
- მუხლი 356. ხელშეკრულებიდან გასვლის ვადა
- მუხლი 408. პირვანდელი მდგომარეობის აღდგენის მოვალეობა
- მუხლი 409. პირვანდელი მდგომარეობის აღდგენის შეუძლებლობა